Qatar: Sit Up And Take Notice - Contractual Notices And Practices In Qatar
Last Updated: 24 July 2012
Article by Laura Warren and Alexa Hall

Contractual notices are a double-edged sword. A common requirement by virtue of the conditions of construction contracts, contractual notices are often overlooked, easily forgotten once works commence on site and yet hugely important in terms of proper financial management of a project and in respect of claims for additional time or money. They are frequently contentious. This article examines notice provisions that are most likely to be encountered in practice, by reference to a main construction contract (although notice provisions may be found in sub-contracts, supply contracts and professional consultancy agreements alike), and looks at the legal issues arising from conflicts involving the failure to give proper contractual notices.

The function and contractual status of notices

The function of contractual notices could be said to depend upon your perspective. For a Contractor, a precise and unambiguous notice provision may assist by making it clear what the Contractor must do if it hits problems such as delay and needs to extend the completion date or claim additional money. Equally, a Contractor may likely perceive notices as an Employer's tool for suppressing otherwise legitimate claims for additional time and payment, and resulting in no more than an unnecessary burden on its project team's time and resources.

For an Employer, notices are an essential means of managing finances and budget. Notices assist the Employer with making informed decisions about whether, for instance, to proceed with a variation, a course of action that may cause delay or disruption or a course of action in order to mitigate such effects. Notices afford the Employer more time to react to problems.

The starting point for contractual treatment of notice provisions is that a failure to comply constitutes a breach of contract for which damages are payable. The local courts and, by extension, arbitrators adopt a pragmatic approach to notices – namely that a notice provision constitutes a term of the contract, to be observed and complied with like any other, and, failing compliance, the innocent party should be compensated for breach. Further, a key legal principle, embodied firmly in local law, is that remedy for breach of contract is monetary damages, the purpose of which is to compensate the injured party for the loss sustained. In short, compensation cannot exceed the innocent party's actual proven loss. This is critical to the subject of notices: it is rare, in practice, that an Employer can prove significant, if any, actual loss flowing from its Contractor's failure to observe a notice provision, particularly in the case of ancillary notice requirements such as providing detailed particulars. Consequently, notice givers generally have little incentive contractually to comply with the terms of notice provisions, as the risks of failing to do so can be relatively small.

Employers soon wised up and various measures have been devised to counter this reasoning, which have generally been incorporated into the majority of construction conditions in some form or another. These measures fall into two discreet categories: (1) express provision for the consequences of a failure to comply; and (2) making a valid notice a condition precedent (namely a contractual term that requires compliance with a defined obligation as a precondition to a right or an entitlement arising) to a right to time or money. There is a subtle but important distinction between the two approaches which has consequences for the challenges that can be advanced by a Contractor in response to these efforts to evade the compensation principles applied by local courts which shall be discussed below.

Conditions of Contract for Plant and Design-Build 1999

1. General requirements

There is no prescribed form within the Conditions of Contract for Plant and Design-Build 1999 ("FIDIC Conditions") for a notice. However, there are a number of general provisions of which it is worth taking note. General Condition 1.3 provides that:

"Wherever these Conditions provide for the giving or issuing of approvals, certificates, consents, determinations, notices and requests, these communications shall be: (a)   in writing ...."

This provision explains why the various notice provisions in the FIDIC Conditions do not expressly state that any notice must be in writing. It therefore creates a potential trap for the unwary Contractor as it will not be apparent by looking at the notice provisions in isolation that the notices must be in writing. Note that in accordance with General Condition 1.2(d), "written or in writing means hand-written, type-written, printed or electronically made, and resulting in a permanent record". Presumably this is intended to cover e-mail but that may depend upon ones interpretation of "a permanent record".

2. Key conditions

There are a handful of the FIDIC Conditions that are worth looking at in further detail on the basis that they contain their own internal notice procedure, in addition to compliance with the provisions governing the procedure for claims (discussed below).

  1. Unforeseeable Physical Conditions (GC-4.12): the trigger for the Engineer to determine the Contractor's entitlement to additional time and or money is the initial provision of notice "as soon as practicable" after having encountered the adverse physical conditions.
  2. Contractor's Entitlement to Suspend Work (GC-16.1): the Contractor's entitlement to suspend work following late payment or late interim payment certification is dependant upon the Contractor giving not less than 21 days' notice to the Employer. This notice is then a further prerequisite to the Contractor's right to an extension of time and/ or additional money in circumstances where the Contract suffers delay and/ or incurs costs as a result of such suspension.
  3. Consequences of Employer's Risks (GC-17.4): the Contractor is required to "promptly give notice" to the Engineer in circumstances where any of the Employer's Risks results in loss or damage to the works, goods or contractor's documents. Again, this notice is an additional precondition to recovery of additional time and/ or money in the event that the Contractor suffers delay and/ or incurs costs in rectifying the loss or damage.
  4. Force Majeure (GC-19.2): if a Contractor is, or will be, prevented from performing any of its obligations under the contract by virtue of Force Majeure, it is obliged to give notice setting out the relevant details "within 14 days after the Party became aware, or should have become aware, of the relevant event or circumstance constituting Force Majeure." By implication, this is an additional pre-requisite to the entitlement to claim for additional time and/ or money following sufferance of delay and/ or additional costs as a result of Force Majeure.

3. Claims procedure

GC-20.1 [Contractor's Claims] is omitted from the list above as GC-20.1 does not, itself, give rise to a claim for time or payment.

In summary, GC-20.1 requires the Contractor, if he considers himself to be entitled to any extension of time and/ or additional payment, to provide notice to the Engineer as soon as practicable, and no later than 28 days after he became aware, or should have become aware, of the event or circumstance giving rise to the claim. This gives rise to debate over the precise moment when the 28-day period begins to run – it is always open to the Employer to argue that the Contractor should have been aware of the event even if, in fact, he was not. GC-20.1 operates as a universal notice provision, adding an additional "notice layer" for the claims highlighted above, and serving as the notice mechanism for the remaining claims provisions, including GC-8.4 [Extension of Time for Completion]. It also introduces a clear and harsh contractual barring provision: if the Contractor fails to given notice within 28 days, he loses his claim entirely and the Employer is released from liability. Further, the condition makes it clear that claims that do survive the barring, will be reduced by the extent to which proper investigation thereof has been prejudiced by a lack of substantiation.

Eluding the contractual notice regime

There are several arguments available, pursuant to a contract and/ or Qatar law, to a Contractor that is found, as a matter of fact, to fall foul of a particular set of contractual notice requirements.

1. Breach of contract only

As stated earlier, failure to comply with a notice provision constitutes a breach of contract, for which compensatory damages become payable. Notwithstanding the fact that the FIDIC Conditions prescribe, in some instances of such failure, consequences that are far harsher than compensatory damages, the "compensatory principle" is still an important weapon for a Contractor. It is therefore always worth checking whether the consequences of a failure to comply are specified or whether this is left to be determined by the "compensatory principle". Notice provisions often comprise many elements. The notice must be given, but it must also be given within the requisite time, to a certain party/ parties, include certain details and in many cases, be followed by further particulars. A time barring mechanism may not cover these ancillary requirements and therefore, a failure to comply with any or all of these components parts may not be fatal to the claim, and may be merely a breach of contract the remedy for which should be a claim for damages alone.

2. Onerous obligations/ Penalty

In accordance with the "General Principle", enunciated in Articles 171 and 172 of Law No. 22 of 2004 ("Qatar Civil Code"), parties shall be bound by the terms they have agreed (provided such provisions are not contrary to public morals or mandatory provisions of local law) unless exceptional, unforeseen circumstances make performance of a particular obligation substantially onerous. Therefore, where the loss of an entitlement to claim is disproportionate to the loss suffered by the party to whom notice ought to be given, a court or tribunal is entitled to construe the notice clauses against the party seeking to rely on them. There might arguably be little or no loss resulting for an Employer from a late or "incomplete" notice, for instance.

By extension, whilst parties are free under local law to agree compensation in advance, the courts retain a discretion to amend the compensation to reflect actual loss. If the effect of the notice provision is to act as a penalty for a failure to serve notice, local law provides a mechanism whereby judges and arbitrators can adjust the effect in order to match the consequences of the failure to give notice to the actual loss suffered by the Employer.

3. Unclear provisions

Where it is arguable that the terms of a contract are unclear or ambiguous, a court or tribunal applying local law has a discretion to "look behind the terms of the contract" in order to assess the intentions of the parties.  Guidance on interpretation of contracts with ambiguous terms is contained in Article 169(2) of the Qatar Civil Code, which provides, "if there is a case for interpreting the contract, the common intention of the contracting parties must be examined without being restricted to the literal meanings of the terms...." Thus, if compliance with a particular notice provision entails an element of ambiguity as to when and how a Contractor must give notice, a discretionary approach may be applied and the notice provision in question may be subject to an interpretation that does not suppress a Contractor's claim entitlement.

4. Notice in Writing?

As set out above, the FIDIC Conditions stipulate that all notices must be given in writing, with "writing" defined as any hand-written, typed-written or printed communication. The question is, what actually amounts to notice in writing and what are the consequences of a failure to comply?

The FIDIC Conditions as discussed above do not specify that notice be given in writing. That is because of the "catch-all" requirement at GC1.3 that requires that where notice is required, this must be in writing. However, GC-1.3 does not specify the consequences of a failure to give notice in writing. Therefore, giving notice in some other form arguably merely constitutes a breach of contract (for which compensatory damages are payable) but is not, necessarily, fatal to a claim.

Further, there are certain forms of notice that are less obvious than the letters or faxes that one generally thinks of when faced with a "written notice" requirement and that should not be overlooked:

  • (a) minutes of meeting, particularly if these must be signed and returned to the Engineer (GC1.3 does not specify who must create the communication);
  • (b) material submittals, on which comments and notes are often written and which are exchanged between the parties;
  • (c) priority lists circulated amongst the parties, that indicate which issues, from a Contractor's perspective, the Engineer should treat as priority so as to prevent delay to the impacted works;
  • (d) a statement on completion; and/ or
  • (e) interim payment applications which may include an amount for variations or other financial claims arising during the period covered.

In short, any documented evidence of an event giving rise to a claim that is sent, given or otherwise produced to the Engineer or Employer, may be argued to constitute written notice.

5. Intention to claim

Some forms of contract (for instance, the Fourth Edition of the Conditions of Contract for Works of Civil Engineering Construction published by FIDIC in 1987 or the Red Book) contain an obligation to give notice of an "intention" to claim (to be followed thereafter with detailed particulars). If a Contractor can show that the intention to claim only arose much later than the event giving rise to the right to claim, this will substantially extend the time for giving notice. It appears that the reasoning makes no difference as it is only the intention that counts. However, there are many reasons that may be advanced. A Contractor may not intend to claim because the Employer stated that it would "see him right" and later reneges on that promise. Alternatively, a Contractor may state that it did not have the resources to investigate claims until a much later stage and as a result, it was not aware of its rights and could not, as a result, form an intention to claim.

6. The Employer's Representation

An Employer or Engineer may sometimes state that the receipt of notices of claims are unwelcome, and further, may seek to persuade a Contractor not to issue proper notices in accordance with the contract on the basis that, of course, the Contractor will be treated fairly regardless. In the case where the Employer fails to make good on such promises, a Contractor may be able to rely on the representations that were given in order to prevent the Employer from using the notice provisions to deny liability for claims that were not properly notified.

The difficulty lies in proving, not only that the representations were made, but also that they were made in a sufficiently clear and forceful way as to make it reasonable for a Contractor to rely on the representation. Whilst there may be some provisions of the Qatar Civil Code that may assist, generally arguments on this ground present a Contractor with an uphill struggle. One option, where the representations are made by the Engineer, may be to demonstrate that the representations constituted instructions pursuant to GC3.3 of the FIDIC Conditions (or similar contract).

7. Alternative causes of action

If a claim has fallen foul of a notice provision, it may be possible in certain circumstances, to reformulate it in a way that brings it within less stringent notice requirements. Some standard form contracts incorporate terms that allow claims to be accepted even though notice provisions have not been complied with. A court or tribunal may be prepared to use such terms to assess and award claims previously disallowed by the certifier under the contract. Under the FIDIC Conditions, this means reviewing each individual claim to establish whether the event giving rise to the claim amounts to a breach of the contract.

8. Conflicts with local law

Where a contract is governed by local law, thought should be given as to whether there are any general, overriding provisions that can be used to a Contractor's advantage.

It may be argued, for instance, that an Employer is not entitled to deny a Contractor its claim on grounds of lack of notice in circumstances where to do so would be a breach of the requirements of good faith as required by Article 172 of the Qatar Civil Code and/ or an abuse of rights contrary to Article 63 of the Qatar Civil Code. The circumstances in which this might apply vary and may be limited in scope. By way of example, in the context of an extension of time claim, it may be a breach of the requirement of good faith and/ or an abuse of rights for an Employer to deny the Contractor an extension of time in circumstances where the Employer and/ or the Engineer knew, or ought to have known, that the Contractor's progress had been delayed by matters for which the Employer was contractually responsible.

Finally, there is an overarching provision that will almost always offer a worthwhile fallback. The general principle under Shari'a law (the overarching law in Qatar) is that "a just claim never expires". In circumstances where a Contractor is found to have factually failed to comply with the relevant notice requirements, and that failure is fatal to its claim, these notice requirements are subject to this principle. In applying this principle, a rounded view of the circumstances would be taken alongside a number of considerations, including the parties' intentions and the requirement for trust and good faith in dealings between contracting parties, to reach what is considered to be a fair and just conclusion.

Recommendations

In the event of non-compliance with contractual notice provisions, there are several arguments available to a Contractor both under contract and pursuant to local law. However, ultimately, much will depend upon the sympathy received from a judge or arbitrator and the skill of the Contractor's legal representatives.

The best policy is clearly, therefore, to know your contract and comply with the letter and spirit of its contractual notice provisions. It is, undoubtedly risky and at the least, time consuming and expensive to have to repair the damage of a failure to comply at a later stage. Sit up and take notice of your contractual notice provisions from the outset.

Note: All Qatari Laws (save for those issued by the Qatar Financial Centre (QFC) to regulate its own business) are issued in Arabic and there are no official translations, therefore for the purposes of drafting this article we have used our own translation and interpreted the same in the context of Qatari regulation and current market practice.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

More Popular Related Articles on Real Estate and Construction from Middle East & Africa
Title to real property in South Africa vests in the landowner and not the state, and there is a comprehensive legal framework for the ownership and transfer or real estate, which is established under statute.
This article briefly examines the typical conveyancing process in Bahrain.
There are a number of structures available to those who intend to undertake developments in Bahrain.
This article examines some of the key legal remedies available to a Landlord where a Tenant is in default under a commercial lease in Bahrain.
Jointly Owned Property (JOP) is the term used to describe a building or land, which has been divided into units and where part of the land is designated as common areas (Article 2 of Law No. 27 of 2007).
Statistics show that construction projects are often exposed to risks and hazards, arising either from purely contractual and legal problems or unforeseen circumstances or natural hazards.
Recently the Land Department issued a press release stating that it has issued "guidelines" implementing Dubai's Strata Law (Law No. 27 of 2007).
Brent Baldwin, a specialist on JOP and Real Estate law, provides some tips for owners and board members.
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert
Email Address
Company Name
Password
Confirm Password
Mondaq Topics -- Select your Interests
Accounting and Audit
Anti-trust/Competition Law
Consumer Protection
Corporate/Commercial Law
Criminal Law
Employment and HR
Energy and Natural Resources
Environment
Family and Matrimonial
Finance and Banking
Food, Drugs, Healthcare, Life Sciences
Government, Public Sector
Immigration
Insolvency/Bankruptcy, Re-structuring
Insurance
Intellectual Property
International Law
Litigation, Mediation & Arbitration
Media, Telecoms, IT, Entertainment
Privacy
Real Estate and Construction
Strategy
Tax
Transport
Wealth Management
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.