United States: Audit Evaluates Compliance With Accounting And Reporting Regulations - The Division Of Audits Addresses Deficiencies In The AFUDC Rate Computation
22 February 2012
Article by John D. McGrane, Pamela C. Tsang and Glen S. Bernstein
On February 7, the Division of Audits of the Office of
Enforcement of the Federal Energy Regulatory Commission (FERC)
issued a report presenting the areas of noncompliance it identified
during an audit of PNM Resources (PNMR), an energy holding company,
and Public Service Company of New Mexico (PNM), a wholly owned
public utility operating company subsidiary of PNMR.1
Audit Staff evaluated PNMR and PNM's compliance with
cross-subsidization restrictions on affiliate transactions;
accounting, recordkeeping, and reporting requirements; the Uniform
System of Accounts (USofA) for...
Specific Questions relating to this article should be addressed directly to the author.
The Federal Energy Regulatory Commission ("FERC") issued a Notice of Inquiry on April 19th ("NOI") seeking comment on its policy regarding capacity priority rights and open access on developer-owned interconnection facilities that connect generation facilities to the integrated transmission grid ("Interconnection Facilities").
At FERC’s open meeting on April 19, 2012, FERC approved several orders addressing core aspects of Reliability Standards compliance, including cybersecurity Reliability Standards, compliance registration, and contingency planning issues.
The Federal Energy Regulatory Commission ("FERC"), on April 19, 2012, approved the eight modified Critical Infrastructure Protection ("CIP") Reliability Standards, CIP-002-4 through CIP-009-4 ("Version 4 CIP Standards"), which were developed and submitted for approval by the North American Electric Reliability Corporation ("NERC") ("Final Order").
On May 4, 2012, the US Bureau of Land Management ("BLM" or the "Bureau"), which is part of the Department of the Interior, released its proposed rule for regulating hydraulic fracturing on public and Indian lands. As expected, the proposal addresses public disclosure of fracturing fluid constituents, well-bore integrity, and wastewater management.
On April 20, 2012, the Federal Energy Regulatory Commission ("FERC") issued an order accepting proposed revisions to the WSPP Agreement addressing sales of renewable energy certificates ("RECs") made pursuant to that agreement.
The U.S. lags behind Europe in the development of offshore wind (OSW) projects in part due to the lack of a mandatory national renewable energy standard and other tax incentives.
On April 27, 2012, the Massachusetts Department of Energy Resources (DOER) proposed final regulations governing the eligibility of biomass energy for Renewable Energy Credits (RECs) for compliance with the Massachusetts Renewable Energy Portfolio Standard (RPS).