On March 17, 2011, in Docket No. RM11-14-000, the Federal Energy Regulatory Commission (FERC) issued a Notice of Inquiry (NOI) in which it solicited comments on how, if at all, it should revise its method for analyzing market power when considering: (a) transactions that require approval under Section 203 of the Federal Power Act; and (b) requests for market-based rate authority.

For nearly 20 years, FERC has been analyzing market power based on guidelines that were adopted in 1992 by the Department of Justice (DOJ) and the Federal Trade Commission (FTC).  For transactions subject to Section 203, FERC has been identifying relevant products, customers that may be affected by the transaction and potential suppliers.  FERC would then examine market concentration using the Herfindahl-Hirschman Index (HHI).  For market-based rate requests, as a preliminary screen, FERC has been applying a "wholesale market share" indicative screen and a "pivotal supplier" indicative screen.  If the applicant failed either of those preliminary screens, it would then provide data to rebut the presumption that it had market power.  That could be accomplished in many ways, including by submitting a delivered price test analysis.

In 2010, DOJ and the FTC adopted new guidelines, which implemented many changes.  The HHI thresholds used to determine the level of market concentration (high, medium or not concentrated) were raised.  Less emphasis is now placed on market definition, in favor of fact-specific inquiries that include examining evidence of competition and use of economic models that quantify the extent to which a firm can raise prices as a result of a merger.  The guidelines also address competitive effects arising from partial acquisitions and minority ownership.

Through this NOI, FERC seeks comment on whether it should adopt any particular elements of the revised guidelines and how it should incorporate those elements into its analysis.  Of particular interest to FERC is whether it should follow DOJ and the FTC in adopting these revisions given that, unlike those other agencies, FERC's analysis is done publicly and a decision is rendered based on a factual record that is the product not only of the applicant's submission, but also intervenor submissions and FERC's own analysis.

Comments must be filed with FERC no later than May 23, 2011.