UK: English High Court Orders Indemnity Costs In Discontinued S.68 Proceedings To Challenge Awards

Last Updated: 7 March 2019
Article by Craig Tevendale, Rebecca Warder and Louise Barber

In Koshigi Ltd and another company v Donna Union Foundation and another [2019] EWHC 122 (Comm) the English High Court considered an application for costs arising from discontinued proceedings under s.68 Arbitration Act 1996 to challenge two arbitral awards. The claimant in the underlying arbitration had successfully obtained two awards in its favour from the tribunal, which the respondents then sought to challenge in the English courts through two related sets of proceedings for serious irregularity under s.68, alleging bias on the part of the chairman of the tribunal. The respondents then discontinued the s.68 proceedings before they reached a hearing, asserting that the awards which they were seeking to challenge had become unenforceable.

In considering the claimant's application for costs in relation to the discontinued proceedings, the Court decided that the liability for the costs rested with the applicants (the respondents in the arbitration) and that the costs should be assessed on an indemnity basis rather than the usual – and typically lower – standard basis. The Court's approach, which disincentivizes the pursuit of s.68 applications without a strong substantive basis, is consistent with other attempts by the English courts to block applicants who bring weak s.68 appeals.

Background

The underlying arbitration concerned a dispute between the shareholders of a Maltese company concerning a provision of the Maltese Companies Act requiring the compulsory purchase of the claimant's minority shareholding in certain circumstances.

Following the issue of the first award, the respondents commenced s.68 proceedings, alleging that the chairman of the tribunal breached his duty to act fairly and impartially and was biased. The claimant issued an application for security for costs in relation to this application. Shortly thereafter, the tribunal issued its second award. The respondents then issued a further s.68 challenge in relation to this award, relying on the same allegations of bias regarding the chairman.

However, within a month of issuing the second set of s.68 proceedings, the respondents discontinued both sets of s.68 proceedings, alleging that the underlying awards which they had been seeking to challenge had become unenforceable. The tribunal had ordered the purchase of the shareholding by way of a mechanism that involved the claimant transferring its shares to be held in escrow and the respondents paying the purchase price to be held in escrow. The respondents argued that as the claimant had not delivered the shares into escrow by the relevant deadline (even though the respondents had not paid the purchase price either), the mechanism had failed. They argued that the tribunal, having already delivered its awards, was now functus officio and could not be called on to substitute another mechanism. The respondents had decided to discontinue their s.68 proceedings challenging the awards on this basis.

The Court's approach to costs

The Court decided that the respondents should bear the costs of the discontinued s.68 proceedings and should do so on an indemnity basis.

The Court applied the test from Brookes v HSBC Bank plc [2011] EWCA Civ 354 regarding costs liability for discontinued proceedings. This set out a presumption that the defendant in the discontinued proceedings should recover their costs and that there is a burden on the claimant in those proceedings to show a good reason for departing from that position.

In this case, the respondents argued that the claimant had acted unreasonably by first pursuing the arbitration but then failing to comply with the tribunal's deadline to deliver the shares and that the consequence was that their s.68 challenge to the awards had become redundant. The respondents contended that they had a reasonable belief that the awards were unenforceable at the time they discontinued the s.68 proceedings and that the circumstances of the claimant's failure to deliver the shares amounted to unreasonable conduct which justified a departure from the usual rule of cost allocation for discontinued proceedings.

In response, the claimant argued that the enforceability of the awards remained in dispute and that the question of their enforceability was not to be determined in costs proceedings. There were otherwise no circumstances to justify the departure from the presumption in Brookes.

The Court agreed with the claimant. In reaching its decision, it noted that the burden on the respondents to discharge the Brookes presumption was high. It also noted that many of the respondents' contentions relied on factual matters which were in dispute and which would have required extensive examination of the facts in order to determine them, stating that "the court cannot on a costs application embark on what would amount to a hearing of the case on the merits and on the evidence". Engaging in any assessment of the enforceability of the awards would require the Court to conduct a de novo hearing on highly contentious matters involving extensive evidence (including on Maltese law), which was not appropriate or permissible as part of a costs application and would in any event "usurp the function of any court which ultimately has to decide enforcement proceedings". The respondents' alleged 'reasonable belief' in the unenforceability of the awards could not be relied on by the Court for these purposes.

On this basis, the Court held that the respondents were liable to pay the costs of the s.68 proceedings.

Standard costs v indemnity costs

The Court then had to decide whether to order costs on a standard basis or an indemnity basis, which will usually be higher.

The usual rule is that the costs of discontinued proceedings should be assessed on a standard basis. The Court noted that there must be some conduct or circumstances which "takes the case out of the norm" before an indemnity costs order can be made, although this conduct need not be exceptional.

In addressing whether there were any circumstances to take this case 'out of the norm', the parties focused on the strength of the substantive basis for the respondents' s.68 challenges: the allegations of apparent bias in relation to the chairman. The respondents argued that they had had good grounds to assert bias and that the allegations of bias had not been waived during the arbitration. The claimant argued that the allegations of bias were "thoroughly bad" and had been waived by the respondents' continued conduct of the arbitration. The respondents' subsequent pursuit and then abandonment of the s.68 challenges on this basis (and in reliance on such serious allegations) was, on the claimant's case, enough to take this case 'out of the norm' and justified an order of indemnity costs.

The Court concluded that the respondents' case regarding bias had been very weak. The respondents' allegations of bias concerned various professional links between the chairman and both the solicitors and QC representing the claimant as well as the chairman's relationship with the head of the company acting as funder and adviser to the claimant – facts discovered by the respondents during the hearing in the arbitration – and the chairman's failure to disclose certain of these facts.

The Court noted that the circumstances in this case were very unlikely to have given rise to bias in the legal sense or to have required disclosure by the chairman. The Court also noted, however, that it was not required to decide whether the allegations of bias were true. The Court was required to consider the strength of the allegations in the context of costs liability in respect of a discontinued claim, where the question was whether the circumstances give rise to some conduct which takes the case out of the norm so as to justify the award of indemnity costs.

The Court noted that the weakness of the case on bias in itself may be sufficient to justify the award of indemnity costs, but that an additional factor weighing in favour of this decision was that the respondents had discontinued the proceedings shortly before the claimant's application for security for costs was due to be heard and that there was no doubt that such an application would have been granted.

Consequently, the Court ordered the respondents to pay the costs of the s.68 proceedings (including the costs hearing itself) on an indemnity basis, and to make an interim payment of 70% of the amount claimed.

Comment

This case demonstrates the way in which the English courts discourage the pursuit of weak s.68 challenges, using indemnity costs to disincentivize appeals with very low prospects of success. Parties considering a s.68 challenge on shaky grounds need to be aware at the outset that withdrawing their appeal, whether for tactical or other reasons, will be likely to incur costs, which may be on an indemnity basis. It is important to give careful consideration to this costs exposure before choosing to commence s.68 proceedings, particularly in light of the success rates for such challenges which show that in the recent past more than 90% of s.68 applications have failed.

The case also demonstrates the difficulties inherent in costs orders for s.68 proceedings. The court will not conduct a de novo hearing on the evidence or on the issues arising from the underlying case, even where they might be relevant to the costs allocation (in this case, questions around the enforceability of the awards and the allegations of bias in relation to the chairman). This limits the parties' ability to rely on circumstances that involve disputed facts. It is important for a party considering a s.68 challenge to take account of these limitations from the start, even where there is a strong belief in the underlying arguments, particularly if there is any likelihood that other factors in play may lead to a need to discontinue the proceedings.

More generally, while some s.68 challenges are brought for tactical reasons, others are born out of a strong sense of grievance (whether well-founded or not) about the result. Given how difficult it is to succeed and the costs consequences for abandoning or failing in the attempt, it is vital for parties to reflect both coolly and dispassionately before embarking on a s.68 challenge.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.