UK: JCT Design And Build 2016 Contract

Last Updated: 13 December 2016
Article by Suzanne Reeves

JCT has published the new edition of 2016 Design and Build Contract in conjunction with the Design and Build Sub-Contract for use with it. The purpose of this note is to outline the principal changes from the previous 2011 edition and answer some frequently asked questions.

In summary, these are:

  • Introduction of common "Interim Valuation Dates" which will apply throughout the contract chain including at sub-contract and sub-sub-contract tiers.
  • Introduction of a procedure for prompt assessment of Loss and Expense claims.
  • Consolidation in a single sub-section of the payment notice requirements of the Construction Act.
  • Amendments to reflect the CDM Regulations 2015.
  • Consolidation within the main text of the general provisions of Insurance Options A, B and C and ability to adapt bespoke existing structures requirements.
  • Flexibility in relation to adoption of Fluctuations Provisions (if used).
  • Inclusion of provisions for the grant of Performance Bonds and Parent Company Guarantees.
  • Inclusion as an option of Third Party Rights instead of collateral warranties for sub-contractors.
  • Updating of the wording of clause 1.8 (Effect of Final Certificate) to bring JCT Design and Build into line with amendments already been made to other JCT contracts in the 2011 editions.
  • Inclusion of a new clause 1.10 to eliminate the need for multiple repetitions of the requirements for consents and/or approvals not to be unreasonably delayed or withheld.
  • Inclusion of the Public Contract Regulations 2015 for public sector works.
  • Minor updating of the intellectual property provisions.

JCT Standard Building (SBC) Contract 2016

(November 2016)

In addition to the amendments referred to above:

  • The main contract form now incorporates (in Supplemental Provision 9 in Schedule) the provisions of the JCT 2012 Named Specialist Update which previously was published separately. Clause 3.8 of the SBC contract conditions continues to offer the employer some control over the selection of specialists by providing for selection from an (adjustable) list of three or more approved sub-contractors. This is for discrete work packages identified in the Contract Documents. However, where Optional Supplemental Provision 8 is utilised by reference in the Contract Particulars, the employer can name individual specialists for work packages that fall outside the Contractors Designed Portion. This can be either pre-contract or post-contract. In the latter case the work will be identified as the subject of a Provisional Sum.
  • The Articles of Agreement remain in their previous format but reference to them has been dropped from the Agreement heading.
  • "Measurement Rules" are defined as the RICS New Measurement Rules, unless otherwise stated. These rules supersede the Standard Method of Measurement.
  • "Site Manager" now supersedes "Person in Charge".

Frequently asked Questions on JCT Design and Build (DB) and Standard Building (SBC) Contracts 2016

Q. Has there been a change in the risk profile?

A. JCT's stated aim was that the 2016 edition amendments do not materially affect risk allocation. However it is unusual for an unamended JCT contract to be used particulary where JCT Design and Build is the form of procurement. Where there is a Schedule of Amendments agreed between the parties, those amendments will themselves change the risk allocation.

Q. How will Third Party Rights (TPR's) be granted in the new editions now that this is an option for sub-contractors to grant such rights?

A. The Contract Particulars in the Articles of Agreement have been simplified by the deletion of part 2 of the Particulars. This used to set out the warranty and TPR requirements but sometimes caused confusion. Instead employers who have developed their own forms of third party rights and collateral warranty requirements can now incorporate these by reference in the Particulars. Alternatively JCT has on its website model forms for the "Rights Particulars" if the Employer does not have bespoke ones. (See below for more detail on TPR's.)

Q. Are the Contract Particulars entries the same?

A. The Contract Particulars have been simplified by the deletion of part 2 of the Particulars (as referred to above); the insertion of a new entry against clause 1.1 for the identification of any BIM protocol and to give a wider choice of provision in respect of fluctuations provisions in section 4 (if they start to be adopted again). There is also an additional entry for clause 6.7 and Schedule 3 relating to insurance to reflect the amendments made to insurance option C. This allows a replacement schedule for existing structures insurance (as to which see below).

Q. Are the contracts still executed in the same way?

A. Yes each contract can still be executed either as a deed thereby attracting a twelve year limitation period or underhand thereby attracting a six year limitation period. The only change is to allow a foreign company Employee, which is not operating through a UK subsidiary, to be able to execute the contract in accordance with its own corporate requirements.

Q. If a BIM protocol is included in the contract what order of precedence does the protocol take?

A. Some model protocols provide that the provisions of the protocol override the Agreement and other Contract Documents, JCT does not consider that unqualified overriding provisions are appropriate and therefore clause 1.3 which deals with the precedence of documents has been amended slightly to make it clear that the Articles of Agreement and Conditions take precedence over any BIM protocol. However, a new clause 1.4.6 has been added to provide that where there is a BIM protocol or other protocol relating to the supply of documents or information documents should be in a form or medium conforming to that protocol.

Q. If there is a BIM protocol what effect will that have on the Design Submission Procedure?

A. Clause 2.8 provides for the supply of the Contractors Design Documents as specified by the BIM Protocol, if one is applicable. If not the procedure set out in Schedule 1 (the existing Design Submission Procedure) will apply subject to any modifications to it specified in the Contract Documents (the definition of which includes the BIM Protocol, if there is one).

Q. What changes have been made to the intellectual property provisions?

A. The wording in clauses 2.19 and 2.20 of DB and clause 2.21 to 2.23 of SBC have been amended. There is some minor rewording in clauses 2.19 of DB and clause 2.21 of SBC. New clause 2.20.2 of DB and 2.23.2 of SBC requires the Contractor promptly to notify the Employer if he is or becomes aware that complying with any instructions may infringe any patent rights. Such instructions will not then take effect unless confirmed by the Employer. If so confirmed any royalties damages or other sums payable by the Contractor will be added to the Contract Sum. However the general principles embodied in the clauses remain the same.

Q. What changes have been made to the payment provisions in Section 4?

A. Generally the section has been rearranged with a view to simplification. There are now eight subsections in a more logical order. A general payments and notices provision has also been included.

However, the main change is the establishment of Interim Valuation Dates which are common valuation dates also intended to apply to sub-contracts and sub-sub-contracts. This has been introduced in order to comply with the Government's Fair Payment campaign by providing a common assessment date throughout all tiers in the contractual chain. If the payment provisions are unamended, payment will be made from the top to the bottom of the chain within thirty days. The Interim Valuation Dates will be specified in the Contract Particulars and Sub Contract Particulars.

Under clause 4.7.3 of DB the Contractor is required to make an Interim Payment Application in respect of each interim payment before each Interim Valuation Date. Subject to the application being made late, (which is dealt with in clause 4.7.3), the due dates for interim payments are 7 days after the relevant Interim Valuation Date.

Under SBC the Contract Administrator is required to issue an Interim Certificate no later than 5 days after each Interim Valuation Date, being the due date in each case. The Contractor may (but is not required to) make an application for payment by the Interim Valuation Date.

Employers (and in relation to sub-contracts, Contractors) should bear in mind that under the Contract Particulars, Interim Valuation Dates in certain months will be altered to the nearest Business Day in the month. That alteration will directly affect the due date and also the five day period for the issue of the payment notice, the last day for giving a Pay Less Notice and the Final Payment Date. This is particularly noteworthy given the importance of serving the relevant notices in time and the consequences of not doing so as determined by the Court in recent cases when the amount of the Contractor's application may become payable however inflated.

Q. What are the Public Contract Regulations 2015 (PC Regulations) and when will they apply?

A. These apply to works procured by a local or public authority employer and not to private sector projects. Where they do apply new Supplemental Provision 12 includes provisions to reflect the sub-contracting requirements of Regulation 71. Under this regulation there is an obligation on a public employer to require the main contractor to provide basic information on his sub-contractors and to keep that information updated.

The inclusion in the contracts of relevant provisions relating to the PC Regulations also means that there are three new termination events set out in Section 8. These would be implied into the contract in any event but JCT has chosen to include (in express provisions) both the basis on which they will be exercised and the consequence of termination. Obviously it remains to be seen if the PC Regulations are repealed or amended in the light of Brexit.

Q. How is Loss and Expense for delay dealt with?

A. Section 4 which deals with loss and expense still requires prompt initial notification of claims, or the likelihood of claims as before that notification is required "to be accompanied, or as soon as reasonably practicable, followed by the Contractor's initial assessment of the loss and expense incurred and any further amounts likely to be incurred...". However, it goes on to provide for monthly updates from the Contractor "for as long as is necessary for final ascertainment".

These requirements are an attempt to avoid the practice of loss of and expense claims not being made or the particulars of them not being given until late in the project after the events giving rise to delay and consequent loss and expense have long since passed.

JCT has not adopted the approach of some bespoke amendments whereby notification by the Contractor in accordance with a time limit is a condition precedent to entitlement to loss and expense, which means that in principle non-compliance avoids the claim.

The Employer (through the Employer's Agent in the case of DB and the Contract Administrator in the case of SBC) Variations (in the case of SBC) is required to notify the Contractor of his initial ascertainment within 28 days of receiving the required information from the Contractor with further notifications being made within 14 days of each subsequent update. In each case the Employer/Contract Administrator is required to identify any points on which that ascertainment differs from the Contractor's assessment.

In the amended JCT provisions not only does the Contractor have to notify circumstances which may give rise to loss and expense and keep the Employer/Contract Administrator updated, but also the Employer (through the Employers Agent/Contract Administrator) should not be able to leave loss and expense to one side pending practical completion.

The Relevant Matters which give rise to loss and expense are unchanged and still include Changes to the Employers Requirements (in the case of DB) or Variations (in the case of SBC).

However, loss and expense is now to be included in the valuation of a Change in DB if the procedure set out in Supplemental Provision 24 (Valuation of Changes – Contractor's Estimates) is used. So clause 4.21 which deals with Changes to the Employers Requirements will only be relevant if Supplemental Provision 24 does not apply.

Q. Any changes to the Final Account Provisions?

A. Clause 4.12 of DB requires the Contractor to submit the Final Statement to the Employer within three months from practical completion of the Works, as was previously the case. If he fails to do so either within that period or within two months of a reminder notice from the Employer, the Employer may issue the statement. Either way, unless the final balance shown is disputed within the time limits specified by the contract, the statement then becomes conclusive as to the final balance. It then has further conclusive effects in accordance with clause 1.8 (materials, goods and workmanship being to the Employer's Requirements standards, extensions of time given and loss and expense awarded) except where and to the extent that proceedings have been instituted and until those claims have determined.

Clause 4.25 of SBC deals with the final adjustment and final payment. The relevant Quantity Surveyor statement and ascertainment is to be provided to the Contractor, within 3 months of the Contractor providing the relevant documentation. That documentation is to be supplied within a maximum of 6 months after Practical Completion of the works. Clause 4.26 then deals with the issue of the Final Certificate. That Final Certificate must be issued within 2 months of the last of the end of the Rectification Period of the Works, the date of issue of the Certificate of Making Good Defects or the date on which the Contractor is sent the Final Certificate. Then the Final Certificate has the same conclusive effects under Clause 1.9 as referred to above regarding Clause 1.8 of DB.

Q. What changes have been made to the insurance provisions?

A. There remains three principal Joint Names Works Insurance Options (A, B and C). However, Option C, which usually applies where there are existing structures, has been amended so as to allow alternative (non JCT prescribed) solutions for existing structures and contents cover to be adopted through a Replacement Schedule. This is an attempt to provide flexibility where works are being undertaken in only part of a multiple occupancy building. In such circumstances it can be difficult for the Employer to obtain Contractors All Risks cover because of the risk of a specified peril such as a fire starting with the works and also causing damage to neighbouring properties or their contents in the rest of the building

Works Insurance may also not be available for works carried out by tenants where insurance of the existing structures is the landlord's responsibility.

Often the value of the works themselves and the additional risk in respect of the structures and contents of the rest of the building is within the cover that a contractor has or can obtain under the contractor's public liability insurance. However where a tenant-employer is in a building in multiple occupancy, the overall value of the structures for the whole of the building and contents belonging to the other tenants or the Landlord, may be beyond the contractor's public liability cover. Where this is the case alternative insurance arrangements involving different layers of cover and risk may be necessary. Such insurance becomes more complex the higher the value of the works and the greater the risks to the adjoining properties. Where the potential liabilities to the contractor exceed any agreed level of cover, the contractor may require an indemnity from the Employer in respect of any claims above those agreed limits.

Where there are existing structures on site but they consist of the building shell or retained façades that have a reinstatement value substantially less than the value of the works to be undertaken, the contractor's works insurers may be prepared to extend Option A cover to include such structures and this is worth exploring before investigating alternative Option C cover.

It is therefore very important that a prospective employer seeks special insurance advice ideally prior to tender. Any employer-tenant should also consult his landlord on the insurance arrangements.

Q. Any change to the provisions relating to terrorism cover?

A. No. The position remains that often joint names or risks cover of the Works excludes cover for acts of terrorism apart from (depending on the terms of the cover) a small level of cover. Accordingly terrorism cover needs to have been specifically required and an appropriate entry to this effect needs to be made in the Contract Particulars. This can be under the Pool Re scheme or other cover such as that provided by the Lloyds market. However, the terms of the cover should be checked carefully. Lloyds market cover does not include chemical and biological damage. Pool Re cover excludes nuclear, chemical and biological risks in respect of a residential property. Pool Re cover also always requires annual renewal. However, Lloyds market cover may be available on a project basis.

Q. Does the contract require evidence of insurance to be provided?

A. Helpfully the provisions relating to evidence of insurance previously set out in each of the three Works Insurance Options are now consolidated into Section 6 and the insuring party is required to provide evidence of cover as the other party reasonably requires within seven days of a request to do so.

Q. How are performance bonds and guarantees dealt with?

A. If a parent company guarantee or performance bond (or conceivably both) are required an appropriate entry will be made against Section 7 in the Contract Particulars. The new enabling provisions are dealt with in section 7 of each Contract which previously dealt only with assignment, third party rights and collateral warranties. This is a welcome addition as previously the requirement for such security from a contractor had to be added by way of amendment to the standard form.

Q. What are Third Party Rights (TPRs) and how have they been amended in the Contract?

A. TPRs are an alternative to standalone collateral warranties. They are in similar terms to collateral warranties but importantly can be invoked simply by serving a notice on the party giving the warranty rather than that party having to execute a collateral warranty. In practice sub-contractor warranties are often difficult to obtain. Unlike other design parties on a project, design sub-contractors may be engaged as the works progress and the collateral warranty requirements can be overlooked or sought later when a sub-contractor has left site. JCT has now included as an option TPR's from sub-contractors which if used may reduce these difficulties. Previously the 2011 edition only provided for TPR's from the contractor.

JCT TPR's comprise Rights Particulars and Rights Conditions. As stated above the former part 2 of the Contract Particulars (in which the Contractor Rights Particulars were previously dealt with) has been deleted. JCT has also made certain other amendments as follows:

  • the provisions in relation to professional indemnity insurance have been harmonised so that the provisions are the same in both the JCT standard collateral warranties in favour of a purchaser tenant and funder, as they are under the TPR's. Therefore the beneficiary of a warranty or the TPR's (as the case may be) will automatically receive an undertaking from the Contractor in relation to such insurance in the same terms as those given to the employer under the main contract. However, in sub-contracts it is still necessary for the employer in his Rights Particulars to specify the level of professional indemnity or product liability cover (as the case may be) that the contractor is to require from various sub-contract trades.
  • there is now a net contribution clause included in the terms of the TPR's from the contractor and the JCT contractor warranties.
  • a default provision has also been added (in clause 7.4.2) so that where the Employer or Contractor (as the case may be) has failed to specify whether rights are to be granted to a beneficiary by TPR's or a collateral warranty. In that case the grantee contractor or sub-contractor can choose how to provide the rights whether by TPR's or a warranty.

Q. Will Schedules of Amendments to the JCT terms still be used?

A. We anticipate that the answer is yes. Whilst JCT have addressed some of the amendments commonly made in the market, they have not included the principal amendments often sought by Employers.

In respect of DB (and the design portion of SBC) these often require the Contractor to accept full design responsibility. This may involve the novation of design consultants to the Contractor. As yet there is not a JCT novation agreement nor any operative provisions allowing for it in the new form. It is generally the case that under an unamended JCT DB Contract (and SBC design portion) the Contractor does not take full design responsibility. The Contractor is liable for the Contractors Proposals only in response to the Employers Requirements.

Many main contractors also amend the JCT subcontracts to reflect their standard terms as well as to step down amendments made to the main contacts terms and conditions.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions