UK: BIM: The Countdown To January 2016 And Beyond

Last Updated: 4 November 2015
Article by Lisa Kingston

This article looks at the key measures that have been introduced by the government in the run-up to BIM Level 2 since we last looked at BIM in the 23rd issue of Insight,1 and the government's strategy for BIM Level 3.


The use of BIM by the construction industry appears to be on a steady upward trend,2 but the "BIM readiness" survey report3 which has just been published by the Electrical Contractors' Association suggests that only 16% of firms in the building service sector are fully ready to use BIM, which makes for startling reading in the lead-up to BIM Level 2 becoming mandatory for all government procured projects from January 2016.

Whilst the industry seems to be lagging behind, the government is already thinking well past BIM Level 2 and has released its Digital Built Britain Strategic Plan ("Digital Built Britain"), which puts the building blocks in place for BIM in the future by prescribing tools and standards that it hopes will encourage consistent BIM adoption and direct those in the industry towards BIM Level 3.4

The seven ingredients of Level 2 BIM

During the course of the past 19 months, the government's BIM Task Group has laid out seven vital ingredients of Level 2 BIM which will be mandatory for all government procured projects from January 2016 and with which the industry in general should be familiar:

(i) CIC BIM Protocol ("the CIC Protocol")5

The CIC Protocol (which was published by the Construction Industry Council in March 2013 specifically for the use of Level 2 BIM) is a contract addendum which establishes the contractual and legal framework for the use of BIM, and clarifies the obligations of team members. The CIC Protocol is intended to take precedence over other contract documents in relation to BIM issues, and envisages the appointment of a BIM Information Manager whose role is to (i) manage the processes and procedures for information exchange on projects, and (ii) implement the Project Information Plan which dictates who does what and when as regards BIM.

If (as is hoped) the CIC Protocol is embraced by the industry, it should set the standard for BIM best practice for the future.

The publicly available standards ("PAS")6

The PAS prescribe how information should be shared on BIM projects and their use is encouraged by the CIC Protocol as examples of best practice which aim to eliminate problems that may be caused by the use of different (and sometimes contradictory) BIM practices, standards and software.

(ii) PAS 1192-2: 2013

PAS 1192-2: 2013 was introduced on 28 February 2012 and defines the information management requirements that are associated with the capital and delivery phase of assets. Its use enables employers to define their lifetime asset information and operational informational requirements, allowing BIM to be planned with the final outcome of the building firmly in mind.

(iii) Government Soft Landings Policy ("GSL")

GSL (which the government announced in September 2012 would apply to all government projects from 2016) is the government's management approach to the specification and measurement of building performance and is based on the government's philosophy that the ongoing maintenance and operational cost of a building during its life cycle far outweighs the original capital construction cost: if this can be recognised during the design process, there will be greater scope to achieve cost savings and improved functionality.

GSL's7 primary focus therefore is  on functionality and effectiveness (buildings should be designed to meet the needs of their occupiers with effective, productive working environments); environmental factors (buildings should meet government performance targets in energy efficiency, water usage and waste production); facilities management (there should be a clear, costefficient strategy for managing the operations of buildings); and finally, commissioning, training and handover (projects should be delivered, handed over and supported such that they meet the needs of end-users).

During the design and construction phase, the interests of the ultimate end-user are represented by a "GSL Champion", whose role is to ensure the goals identified at the beginning of the project are maintained and incorporated into the design and construction phase.

The GSL Champion will also need to ensure that any post-completion data associated with the building is managed and properly earmarked during the build.

(iv) PAS 1192-3: 2014

PAS 1192-3: 2014 serves as a continuation of PAS 1192: 2013 (and should therefore be read in tandem with it) in that it was introduced in March 2014 to provide a specification for information management for the operational phase (i.e. handover onwards) of construction projects in a nod to the growing importance that is being attached to BIM and facilities management.

PAS 1192-3: 2014 supports GSL by encouraging greater engagement with BIM from the outset of the project by ensuring that the data and information required (i) to achieve the organisational information's objectives and (ii) to support the organisation's asset management system are linked to the Employer's Information Requirements ("EIR"). The EIRs form part of the appointment and tender documents on a BIM Project to which the BIM model also links.

(v) BS 1192-4

BS 1192-4 is a British Standard released in September 2014 which concerns the UK usage of Construction Operations Building Information Exchange, an internationally agreed scheme for the exchange of information between the employer and the supply chain using the standard Excel-based format COBie.

COBie is an open format for data delivery. It is the best standard to use to enable the transfer of information from one software platform to another, since it provides a common structure for the exchange of information about new and existing facilities, and does not require knowledge about sending or receiving applications and databases of members of the project team. COBie also serves as the standard against which data delivery and compliance can be tested.

(vi) PAS 1192-5: 2015

PAS 1192-5: 2015 is a companion document to (and should therefore be read in conjunction with) PAS 1192-2: 2013, PAS 1192-3: 2014 and BS 1192-4, and came into effect in May 2015. PAS 1192-5: 2015 is the specification for security-minded BIM which enables BIM to be mobilised in a secure manner by adopting a need-to-know approach to the sharing and publication of data and information with a view to deterring hostile behaviours. It is process-driven and sets out six steps which enable the development of an approach that will minimise the risk of misuse, loss, unintentional disclosure or theft of information which may impact upon the safety and security of the project. The first step is an assessment of the extent of the security-minded approach that is required, followed by an assessment of the security risk to the built asset; a decision on appropriate and proportionate mitigation measures that are commensurate with the risk appetite; a formal record of the organisation's security strategy and management plan for the built asset; implementation of appropriate and proportionate policies, processes and procedures; and regular review in response to incidents, breaches and significant internal or external changes.

In cases where assets are pre-existing, or are already being managed or modified, the security process should be carried out prior to the commencement of asset data collection, or following a change in the operating or contracting arrangements. The latter may include a change in the asset management system, facilities or asset management/maintenance contract; the integration of asset control/management systems with other asset management systems; or a significant change in the use or occupation of an asset.

The security process should be overseen by a Built Asset Security Manager whose role is to provide a holistic view of the security issues and threats relating to assets, and who will be accountable for any ensuing security decisions that are made.

(vii) The BIM Toolkit

The BIM Toolkit was launched in April 2015 and is the final piece of the jigsaw which completes the government's BIM Task Group Level 2 programme. It aims to (i) provide employers with the ability to develop EIRs at an early stage of the project prior to appointing the project team, and (ii) enable the project team to agree responsibilities and deliverables through the project timeline to ensure everyone is clear on who is doing what and when.

The Toolkit comprises two parts: the Digital Plan of Work and the Uniclass 2015 classification tables.

(a) The Digital Plan of Work

The Digital Plan of Work was released in July 2015 and fulfils the requirement of PAS 1192-2: 2103 for a task information delivery plan. It is currently in public Beta 3 format for use and feedback by users ahead of its formal launch this autumn and a copy can be downloaded free of charge from the NBS website.8

The purpose of the Digital Plan of Work is to enable the practical implication of Level 2 by assisting employers to procure digital data by defining what data they require at different work stages. Various editable templates and standards are incorporated into it, and tasks and information requirements are allocated in accordance with the agreed contractual responsibilities, which allows the project team to manage and validate responsibility for information development and delivery at each stage of the asset life cycle. It is open to the owner of the Digital Plan of Work to invite named individuals in the project team to have read-only access to the Toolkit via their own PC, Mac or mobile device, and those named individuals can post comments and updates on the tasks and deliverables within the Digital Plan of Work to aid communication, making the Toolkit collaborative.

(b) Uniclass 2015 classification tables

The BIM classification system is based on a common language of classification known as Uniclass, which enables the project team to describe the various objects they use in a uniform manner. The use of Uniclass will make the BIM model much easier to use as the project team will be speaking the same language.

The classification tables are currently being completed in response to user feedback on the Digital Plan of Work. When the tables are in their final form, they will incorporate definitions for over 5,000 construction objects at each delivery stage of a project and will sit alongside the Digital Plan of Work.

The future: Digital Built Britain (DBB)

On 26 February 2015, the government launched DBB which is its strategic high level plan for BIM Level 3. DBB builds upon the "data exchange" process that is characteristic of Level 2 BIM by the use of Model Views which facilitate the sharing of information at various key stages in the project. DBB introduces a set of new, advanced, international "open data" standards to facilitate the sharing of data; establishes a new contractual framework and commercial models for BIM projects to ensure consistency of working with BIM and collaborative working; calls for the training of public sector clients in the use of new BIM techniques and technologies; and highlights that new technologies need to be identified to transform the approach to social infrastructure, development and construction.

It is the government's hope that Level 3 BIM will enable digital design to be interconnected to all elements of the built environment, and will extend the use of BIM into the operation of assets over their lifetime, which is where the majority of costs arise.

Conclusion

From the legal perspective, GSL (Level 2 BIM) is likely to create contractual issues since it raises a brand new concept of responsibility for the whole life cycle of buildings which involves the setting of targets and measuring performance against those targets in a new postoccupancy period. The post-occupancy period is intended to last for three years post-completion (i.e. two years in excess of the traditional defects liability period) and amendments to the standard forms will be necessary to provide for the associated extended monitoring on site (which may or may not overlap with the defects liability period). Amendments will also be necessary to provide for the precise maintenance and operational requirements and standards that need to be met during the life cycle of a building, which may lead to a shift towards routine fitness for purpose obligations and absolute warranties which are currently construed very narrowly by the courts in the absence of very clear words to the contrary.9 Insurance arrangements may also change in response to what will probably be a much greater scope for the allocation of contractual risks and responsibilities over a longer period of time which will need to be insured.

As for DBB and Level 3 BIM, DBB introduces truly collaborative models of working which focus on a brand new concept of project feedback and the capture of performancebased intelligence which does not have a place in the current standard forms and therefore quite substantial amendments will be necessary. Project insurance may also become increasingly popular at BIM Level 3 as it may be the most effective way to cover a collaborative team in which there is no allocation of fault.

Watch this space!

Footnotes

1. See http://www.fenwickelliott.com/files/insight_issue_23.pdf.

2. BIM has been central to the success of Gatwick Airport's £1.2bn capital investment programme and the refurbishment of Gatwick's North Terminal.

3. The "BIM readiness" survey was published on 15 October 2015 by the Electrical Contractors' Association alongside the Chartered Institution of Building Services Engineers, The Building Services Research and Information Association ("BSRIA") and a host of trade bodies. The results are to be shared with key players inside government and the wider industry and will enable BSRIA to plan the way forward to BIM maturity.

4. The government predicts this will lead to savings of around 30% of the whole life of construction projects — see Construction 2025 — Industrial Strategy: Government and Industry in Partnership (HM Government).

5. Further details about the CIC Protocol can be found at http://www.fenwickelliott.com/files/insight_issue_23.pdf.

6. Further information on PAS 1192-2: 2013 can be found at http://www.fenwickelliott.com/research-insight/newsletters/insight/23.

7. Which can also be seen in Stage 7 of the RIBA Plan of Work 2013.

8. https://toolkit.thenbs.com/.

9. Most recently, in MT Højgaard A/S v E.On Climate and Renewables UK/ Robin Rigg East Limited and another [2015] EWCA Civ 407, the Court of Appeal was reluctant to impose an absolute warranty on the facts in circumstances where the contract was not worded with sufficient clarity, but it acknowledged that if a contract was sufficiently clear, a contractor could be liable for failing to achieve a specific result (i.e. a particular service life) even though it had otherwise complied with the relevant standard.

Useful link

1. http://www.fenwickelliott.com/research-insight/newsletters/legalbriefing/2015/07


Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.