In the concluding of a two-part article, (to read part 1 please click here) Nicholas Gould considers some of the alternative and more innovative dispute resolution procedures that are used in the construction industry.

Mediation and Conciliation

ADR is usually taken to mean "alternative dispute resolution", or "appropriate dispute resolution". The most frequently encountered ADR technique is mediation or conciliation. There is little difference between the processes, however, a distinction that can be drawn is that in the construction industry conciliation might be more evaluative. An example of this is the ICE conciliation procedure. If the parties cannot agree a settlement then the conciliator will make a binding recommendation. On the other hand, CEDR promote a process of mediation whereby the mediator does not make a recommendation.

Mediation is essentially an informal process in which the parties are assisted by one or more neutral third parties in their efforts towards settlement. Mediators do not judge or arbitrate disputes. They advise or consult impartially with the parties in order to try to find a mutually agreeable resolution to the dispute. Normally, a mediator cannot and does not impose a decision on the parties, but assists them through their own settlement.

This does not mean that mediation is a soft option. Mediators should and do use a variety of techniques to explore the basis of the dispute and seek a resolution. This can often mean that the parties need to make some tough decisions during the course of the mediation. Essentially, the parties must reach an agreement, and so need to take a sensible and pragmatic view about the issues in dispute. In some respects, the soft option is to allow the judge or arbitrator to make that decision for them. In many mediations, the parties need to make some difficult decisions about whether to pursue or abandon parts of their claim.

The main benefits of mediation are:

  • Speed. The average mediation lasts 1-2 days. Complex multi-party, multi-million pound disputes can be resolved in this period. There is of course a short period of time leading up to the mediation during which the parties exchange relevant documents and outline their position.
  • Costs. Clearly a short mediation is far cheaper than a lengthy trial or arbitration.
  • Confidentiality. The proceedings are, like mediation, confidential.

Mediation has grown steadily in the UK since 1990, and is now used in a wide range of disputes, especially construction and engineering disputes.

Dispute Boards

The collective term Dispute Board "DB" covers the concept of Dispute Review Boards "DRB" and Dispute Adjudication Boards "DAB". DRBs initially developed in the USA. DRB comprises three independent people who evaluate disputes during the course of the project and make settlement recommendations to the parties. The recommendations are not binding.

Each party selects a board member and the parties may then agree on the third, or if they cannot agree the two board members will select the third board member. The DRB then periodically visits the site to gain familiarity with the project and the individuals working on the project. This means that if a dispute arises the board members understand the project and have already built some rapport with the individuals working on the project. They can then deal with disputes by hearing presentations from the parties and suggest solutions.

The term DRB can be misleading, as many contracts that include a DRB now provide for the DRB to make binding decisions. One should therefore carefully check the contracts in order to see what it is the DRB is actually doing.

More recently, a DAB process has been included in the 1999 FIDIC suite of standard form contracts. The key distinction between a DRB and a DAB is that a DAB considers submissions from the parties and then issues a written binding decision. The parties are obliged to comply with the decision, and unless they issue a notice of dissatisfaction within 28 days of the giving of the decision, the decision becomes final and binding.

The FIDIC form of contract provides a period of 84 days from the notice of dispute to the giving of the decision. The FIDIC contract is relatively widely used on substantial international projects. If FIDIC were to be used in the UK, then the DAB procedure would not comply with the HGCRA (because the decision is not given within 28 days) and so the parties will be able to refer a dispute to adjudication under the Scheme for a decision within 28 days.

However, FIDIC is used on large international projects where the UK legislation does not apply. Further, the 84 day period is more appropriate for international projects where the DAB members will probably need to travel from various parts of the world in order to meet up and review the projects. Co-ordinating DAB meetings therefore takes time.

DBs are particularly suited to large complex projects. The benefits of DB’s include:

  • Project based. Disputes are resolved during the project in order to keep the project progressing towards completion;
  • Dispute avoidance. The mere existence of the board encourages the avoidance of disputes: and
  • Project knowledge. The board members visit the project and get to know the individuals involved with the delivery of the project. This means the board can turn its attention to the detail of the dispute without the need to spend time understanding the parties, the contract and the general details of the project.

Project Mediation

Project mediation attempts to fuse team building, dispute avoidance and dispute resolution in a single procedure. A project mediation panel is appointed at the commencement of a project. It comprises usually a lawyer and one commercial expert who are additionally trained as mediators. There is an initial meeting at the start of the project in order to familiarise the project team with the procedures.

The panel visits the project during the course of construction. They become familiar with the project and the individuals working on the project. The project mediators are then available to resolve any differences, hopefully before they escalate. Project mediation is, therefore, very much a dispute avoidance technique, although with the ability to hold informal or formal one day mediations during the project to resolve any issue that might arise.

It is a recent development and has only been used on a small of occasions. However, it does offer some distinct advantages:-

  • Economy. It is far more economic than a DRB or DAB, and is therefore available for use on many small and medium sized contracts. A single project mediator could of course be used on a smaller project.
  • Avoidance. Many in the construction industry now place great emphasis upon dispute avoidance and are more willing to face up to and deal with disputes in a commercial manner. Project mediation allows such players in the industry to avoid and resolve disputes more economically.
  • Confidential. It is confidential and effective.

The author has drafted a project mediation procedure that CEDR is hoping to launch later this year. A standard procedure will be available for those that would like to use project mediation on their projects.

Conclusion

There are clearly a wide range of dispute resolution techniques available to those working within the construction industry. Many of the standard forms will dictate the applicable dispute resolution technique for a particular project. Care is therefore needed when putting together contract documents. Thought should be given to the most appropriate dispute resolution technique for a particular project, or better still a dispute escalation clause should be included which provides for disputes first to be considered by senior managers before progressing to mediation and then either litigation or arbitration.

If the Housing Grants Act applies, then adjudication will always be available "at any time". In respect of arbitration, thought should be given to whether the 100-day procedure is an appropriate one that could be adopted for the project. For lower value projects the 100-day procedure should certainly be seriously considered, however, for larger projects it is perhaps less desirable.

For further articles by Nicholas Gould please visit www.fenwickelliott.co.uk.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Nicholas Gould
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.