UK: Case Law On NEC3

Last Updated: 8 June 2015
Article by Lisa Kingston

Since being endorsed by the Office of Government Commerce in 2013, NEC3 has fast become the standard form of choice for construction and maintenance works in the public sector, as well as being used occasionally in the private sector for major engineering projects. Despite this being so, historically at least, case law on NEC3 has been relatively scarce. Mr Justice Akenhead expressed his concern two and a half years ago about the lack of consideration by the courts of the NEC form.

But are things really that bad? The form has been before the Technology and Construction Court on several occasions over the past four years and was considered for the first time by the Court of Appeal in February 2014, so it is at long last starting to receive some judicial scrutiny. This 47th issue of Insight examines the more important of these decisions and considers the court's evolving approach to the NEC3 form.

Since being endorsed by the Office of Government Commerce in 2013, NEC3 has fast become the standard form of choice for construction and maintenance works in the public sector, as well as being used occasionally in the private sector for major engineering projects. Despite this being so, historically at least, case law on NEC3 has been relatively scarce. Mr Justice Akenhead expressed his concern two and a half years ago about the lack of consideration by the courts of the NEC form, noting that the NEC3 Conditions:

"are used throughout the construction and engineering industries and are highly regarded in the sense that they are perceived by many as providing material support to assist the parties in avoiding disputes and ultimately in resolving any which do arise. There are some sirens or other voices which criticise these Conditions for some loose language, which is mostly in the present tense, which can give rise to confusion as to whether and to what extent actual obligations and liabilities actually arise. Very few cases involving material disputes as to the interpretation of the NEC3 Conditions have made their way through to reported court decisions."1

This paints rather a dim picture of the NEC form, but are things really that bad? The form has been before the Technology and Construction Court on several occasions over the past four years and was considered for the first time by the Court of Appeal in February 2014, so it is at long last starting to receive some judicial scrutiny. This 47th issue of Insight examines the more important of these decisions and considers the court's evolving approach to the NEC3 form.

Atkins Ltd v Secretary of State for Transport [2013] EWHC 139 (TCC), 1 February 2013

This case was concerned with the validity of a compensation event under a Highways Agency Managing Agent Contractor contract which was a heavily amended form of NEC3 that was entered into between Atkins Ltd ("Atkins") and the Secretary of State for Transport ("SST") to maintain various trunk roads in East Anglia. Payment was broadly on a lump sum basis subject to Atkins' right to claim relief for any compensation events.

During the course of the works, Atkins encountered a greater number of potholes (which it was obliged to repair) than it had anticipated and sought to claim additional payment on the basis that this constituted a compensation event under clause 60.1(11). That clause stated (in similar terms to clause 60.1 of the NEC3 Conditions) that:

"The Provider encounters a defect in the physical condition of the Area Network which ... an experienced contractor or consultant would have judged at the Contract Date to have such a small chance of being present that it would have been unreasonable for him to have allowed for it."

The SST rejected Atkins' contention on the basis that the volume of potholes could have been reasonably foreseen, and that any excess in number did not give rise to a compensation event.

Mr Justice Akenhead agreed with the SST and dismissed Atkins' claim that a higher prevalence of potholes than was expected constituted a compensation event under clause 60.1(11), either as a matter of the language of the clause itself, or as a matter of commercial interpretation. The Judge noted that there was nothing in the clause which expressly suggested that the number of defects was a key or important element in the compensation event equation, and it was very difficult to conclude that an excess number of potholes over and above a reasonable number which could be considered to have been allowed for could form the basis of a compensation event. It would also be very difficult in practical terms to determine how many potholes would constitute an excessive number and such an exercise would be both difficult and artificial.

Taking a commercial view, because the contract was a lump sum contract, the parties collectively took the risk that any defects might be more or less in number and expense than the contract actually allowed for, and indeed this was not unusual in such contracts. If Atkins' argument was accepted, there would be no commercial risk at all, and Aktins would effectively be in a win-win situation, whereby it could keep the whole of the lump sum if the number of potholes were less than reasonably anticipated, and it almost automatically gets additional payments if the number of potholes exceeds that which was reasonably anticipated. In other words, Atkins' argument would have converted what was a lump sum contract into a re-measurement arrangement and this was not what the parties had intended.

WSP Cel Ltd v Dalkia Utilities Services Plc [2012] EWHC 2428 (TCC), 28 August 2012 2

This case centred on the issue of whether, by virtue of the parties' consent agreement which varied the terms of clause W1.3(1) and W1.3(2) of the NEC3 Professional Services Contract, the adjudicator had jurisdiction to determine his own jurisdiction in a final account dispute. Dalkia Utilities Services Plc ("Dalkia") claimed that the adjudicator did not have jurisdiction as WSP Cel Ltd ("WSP") had failed to refer the dispute within the period provided for by the time bar in clauses W1.3(1) and W1.3(2). WSP argued that the adjudicator had been afforded jurisdiction under the terms of the consent agreement, which varied the procedure for adjudication such that the time bar for referring a dispute to adjudication under clauses W1.3(1) and W1.3(2) was superseded.

As is often the case, the decision of the court was based heavily on the specific facts of the case, but the judgment provides useful obiter comments on the application and interpretation of clause W1.3 and the Adjudication Table in the NEC3 Professional Services Contract.

Mr Justice Ramsey emphasised that the philosophy of the NEC Conditions is to avoid disputes at the end of a project by having intensive management machinery to deal with issues arising whilst the project is on foot. The notification of disputes and the reference to an adjudicator is a necessary part of the detailed management philosophy under the NEC Conditions which requires disputes to be referred to the adjudicator in a timely manner so that they can be resolved at the time. The Judge concluded obiter that in the absence of the consent agreement, WSP could not have sought adjudication of issues arising under Grounds 1 and 2 unless they had been referred within the time set out under those grounds. The court therefore interpreted clause W1 effectively as a condition precedent.

Mr Justice Ramsey further considered whether, had it not been for the consent agreement, the dispute on the final account came within Ground 4 in the Adjudication Table, or Grounds 1 or 2. He found that just because a claim forms part of a composite claim at termination, this does not necessarily change its character under the machinery of the NEC Conditions. Claims based on compensation events should be dealt with under the compensation event machinery, and any disputes arising either from an action of the Employer, or the Employer not having taken action, should be referred to adjudication under Grounds 1 or 2. Those claims do not change to become "any other matter" under Ground 4 just because they are included in the final account and are part of a larger composite claim. If they fall within Grounds 1 and 2 then they should remain there, unless the claim is not based on any action or inaction of the Employer.

Ecovision Systems Limited v Vinci Construction UK Limited [2015] EWHC 587 (TCC), 11 March 2015

It is worth noting that NEC3 was also considered in the adjudication context in Ecovision, in which Vinci Construction UK Limited ("Vinci") engaged Ecovision Systems Limited ("Ecovision") under a NEC3 subcontract to design, supply and install a ground source heating and cooling system which subsequently broke down.

Vinci initiated adjudication proceedings but its adjudication notice failed to specify which set of adjudication rules applied out of a possible total of three adjudication rules that appeared to be prescribed by the terms of the subcontract under the main contract, sub-contract and Scheme. The adjudicator confirmed that Option W2 of the subcontract rules applied. Ecovision sought a declaration that the adjudicator had no jurisdiction by virtue of the fact there were conflicting adjudication rules, and that the applicable adjudication rules were the TeCSA adjudication rules that were prescribed by Option W2 of the main contract as amended by clause Z16.

His Honour Judge Havelock-Allan QC agreed with Ecovision in holding that the adjudicator did not have jurisdiction to determine his own jurisdiction as the main contract rules applied, and so the adjudicator had been appointed under the wrong rules. Even if the subcontract rules had applied, the Judge commented that the adjudicator had probably been appointed one day too late.

Whilst this case does not teach us anything new about NEC3, it provides a stark reminder for parties to make sure (i) their contract has clear, back-toback provisions for the appointment of adjudicators, and (ii) that those provisions are followed by the parties to the letter to avoid any arguments as to the adjudicator's jurisdiction further down the line.

RWE Npower Renewables Ltd v J N Bentley Ltd [2014] EWCA Civ 150, 19 February 2014

In this case, J N Bentley Ltd ("Bentley") carried out civil engineering works for RWE Npower Renewables Ltd ("RWE") on a hydroelectrical plant in Scotland. The agreement included the NEC3 Engineering and Construction Contract Conditions Data Sheets Parts 1 and 2, Post Tender Clarifications, Works Information and Site Information, and, importantly, contained an order of preference clause.

A dispute arose as to whether Part 1 of the Contract Data or clause 6.2 of the Works Information took precedence, the answer to which prescribed whether all work that was described as forming part of section 2 had to be finished before the section as a whole could be regarded as being complete. If that was the case, then the intake, penstock pipeline and tailrace all had to be tested and completed.

Mr Justice Akenhead held at first instance that the agreement should be read as a whole and construed as far as possible to avoid inconsistencies between different parts of the agreement, on the assumption that the parties had intended to express their intentions in a consistent and coherent manner. In the Judge's view, there was no significant inconsistency between Option X5 and clause 6.2, which could be read together without undue difficulty.

Bentley disagreed with the decision at first instance and took the view that there was a clear discrepancy between Option X5 and clause 6.2, as the former only required the installation of the hydroelectrical plant as part of section 2 whereas the latter called for the hydroelectrical plant to be tested and commissioned.

Moore-Bick LJ agreed with Mr Justice Akenhead, adding that Option X5 was worded in more general terms than clause 6.2, which identified the work that was included in each section in much greater detail. Despite the difference in the level of detail in the two clauses, the Court of Appeal held that the two provisions would be expected to complement each other and that it would only be necessary to resort to the contractual order of precedence clause in circumstances where different provisions on their true construction imposed different obligations in relation to the same subject matter.

If the order of precedence provisions fell to be considered, Moore-Bick LJ confirmed that the correct approach would be to resolve discrepancies relating to individual obligations rather than forcing a choice between one clause and another. Under both Option X5 and clause 6.2, there was a single obligation to carry out the whole of the prescribed work in order to complete section 2 and it was not possible to extract the part relating to pipelines and treat that as a free-standing obligation as there was no freestanding obligation as a matter of fact.

On the facts, Moore-Bick LJ found that both clauses referred to the completion and testing of the penstock pipeline and they were capable of being read sensibly together on the basis that section 2 was intended to compromise substantially the whole of Bentley's work, other than the part that fell within section 1. It therefore made no difference whether the reference was to installing the hydroelectrical plant (Option X5), or testing and commissioning it (clause 6.2) as in practice none of that formed part of Bentley's work. To the extent there was any discrepancy, the obvious place to start was clause 6.2 which contained more detailed provisions about what was required.

Conclusion

The above decisions demonstrate that the courts are able to easily interpret NEC3 clauses by adopting a common sense approach to the language that is used, having regard at all times to the facts of each case. As Mr Justice Akenhead said of the NEC3 form in RWE:

"It needs to be borne in mind that much of the language of these conditions is in the present tense, although that factor does not seem to impact upon contractual interpretation..."

It is hoped that this comment and the decisions above will go some way towards dispelling the sentiment that is held by some in the construction industry that NEC3 contracts can be difficult to understand and problematic to enforce, which the case law to date shows not to be the case.


Footnotes

1. See Atkins Ltd v Secretary of State for Transport [2013] EWHC 139 (TCC) at para 9.

2. It should be noted that whilst the judgment was handed down on 28 August 2012, it was only made available in early spring 2013

Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.