UK: NEC3: Some Areas Of Difficulty And Suggested Amendments

Last Updated: 16 November 2014
Article by Lisa Kingston

This is the third of a three-part series on NEC3.

Part one dealt with problems that are commonly encountered in NEC3 and possible solutions (http://www.fenwickelliott.com/files/insight_issue_32.pdf), and Part two examined the principal responsibilities of the Employer and Consultant respectively (http://www.fenwickelliott.com/files/insight_issue_35.pdf).

This final part considers some of the key areas of difficulty with the NEC form and makes suggestions as to how NEC3 might be amended to overcome them from the contractor's perspective.


Why amend NEC3?

NEC3's focus is on effective management procedures, collaborative working and good working relationships, and it is therefore more of a project-based contract than a legal contract in the sense that what the parties are signing up to is an ethos.

Compared with JCT, it is relatively brief in terms of the parties' obligations, and as a general rule, it is not as comprehensively written as other standard forms. The JCT Design & Build 2011, for example, contains comprehensive detail in relation to insurance at Clause 6 and Schedule 3, but the insurance arrangements at Clause 84 of NEC3 are very brief. NEC3 is also silent on existing buildings insurance and adjacent property insurance.

NEC3 is written completely in the present tense, and, with the exception of Clause 10.1 (which provides that "the Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and cooperation"), the usual series of obligations upon the parties is absent. The absence of obligations other than to act in good faith has the potential to create difficulties, as any breaches of contract will be more difficult to establish in the absence of a positive obligation from which a breach can give rise, and there is no case law on the meaning of Clause 10.1. Even if such case law did exist, the court would inevitably focus on what NEC actually says, rather than take into account the collaborative mindset that is inherent in the operation of NEC3.

That said, the draughtsmen of NEC3 contemplated that amendments may be necessary, and provided a secondary Option Z that allows parties to incorporate bespoke provisions into the contract. The resulting additional clauses are commonly referred to as "Z clauses".

Suggested Z clauses for NEC3

Priority of documents clause

NEC3 usually comprises the Contract Agreement; Contract Data; Conditions of Contract; Schedule of Cost Components and Shorter Schedule of Cost Components; Works Information; Site Information; and an Activity Schedule, or bill of quantities. On occasion, the inclusion of these documents can introduce inconsistencies, in which case a priority of documents clause can be useful.

NEC3 does not include a core clause that deals with the priority of contract documents, as a result of which there is a risk that a provision in another contract document could take precedence over the Conditions of Contract. Clause 17.1 provides some comfort by obliging the contractor and project manager to notify the other if they become aware that there is an ambiguity or inconsistency in any of the contract documents, in which case the Project Manager gives an instruction resolving the ambiguity or inconsistency. However, this falls far short of a priority of documents clause which would deal with such a problem before it arises.

The Court of Appeal emphasised recently in RWE Npower Renewables Limited v JN Bentley Limited [2014] EWCA Civ 150 (19 February 2014) (see http://www.fenwickelliott.com/files/dispatch_issue_165.pdf for full details) that contract documents should be read as complementing each other as far as possible, and only in the case of a clear and irreconcilable discrepancy would it be necessary to resort to the contractual order of precedence, in which case the order of precedence would only apply to the particular discrepancy and would not operate as a mechanism to choose an entire clause over another.

This decision casts some doubt over the efficacy of any priority of documents clause, as it would be unnecessary to refer to it if the documents can be read together as expressing the parties' intentions in a clear and sensible way. However, there is nothing to lose by having a priority of documents clause which should be included by parties as a belt and braces measure in the interests of certainty.

Statutory requirements in relation to materials and workmanship

NEC3 also omits the contractual obligation that is commonly seen in other standard forms to comply with applicable statutory requirements, and there is no clear guidance as to Issue 40, October 2014 the minimum standards that should apply in relation to materials and workmanship.

Pursuant to NEC3 Clause 20.1, "The Contractor Provides the Works in accordance with the Works Information". This means that the Works must comply with any purposes specified in the Works Information. In other standard forms, such as the JCT Standard Building Contract 2011, the contractor is obliged at Clause 2.19.1 to use reasonable skill, care and diligence in carrying out design work.

Under NEC3, if no duty to comply with the relevant statutory requirements appears within the Works Information, it is likely that there would be an implied condition that the materials supplied under the contract are of satisfactory quality (unless, for example, the goods were inspected as a sample prior to the contract being entered into). This would make the contractor liable for any latent defects under the Supply of Goods and Services Act 1982.

A term may also be implied into NEC3 under the Supply of Goods and Services Act 1982 that, where an employer makes known to the contractor (whether expressly, or by implication) the purpose for which materials will be used, there will be an implied condition that the materials are reasonably fit for that purpose. Even if no such obligation exists (which can be the case where the employer has prepared the Works Information and the employer has not relied upon the contractor's assessment of the materials), there may be a duty on the contractor to warn if the materials are unsuitable.

The difficulty with a fitness for purpose obligation is that, unlike a reasonable care and skill obligation, it will not usually fall within the confines of a professional indemnity policy, and contractors should resist the inclusion of an express fitness for purpose provision for that reason.

Design requirements and liability

Clause 21.1 of NEC3 provides that the contractor designs the part of the Works which the Works Information states he is to design. It is the Works Information therefore that dictates the extent of the contractor's design obligations, and, depending on the drafting of the Works Information, it might be that there would be an absolute obligation that the design is fit for purpose. In the absence of an absolute obligation, in a design and build contract, it leaves an implied term that the completed work will be reasonably suitable for the purpose for which the contractor knows it is required.

If they can, contractors should insist on secondary option X15, which provides for the lower standard of reasonable care and skill, which will not include the implied obligation of fitness for purpose. This is because a reasonable care and skill obligation will be covered by professional indemnity insurance.

Contractors should also resist any attempt by employers to widen the scope of Clause 21.1 by providing, for example, that the contractor has to provide the Works in a consistent and diligent manager, as such provisions would also not be covered by professional indemnity insurance.

Building Information Modelling (BIM)

If the works are BIM-enabled, parties to NEC3 should take into account the NEC3 guidance on using Building Information Modelling ("BIM") with NEC3 contracts ("the Guidance") that accompanies the NEC3 April 2013 suite of contracts.1

The Guidance suggests wording for a Z clause that is compatible with the Construction Industry Council (CIC) BIM protocol ("the Protocol"). The Protocol was commissioned by the Commercial Workstream of the government's BIM Implementation Task Group, and is representative of best practice of working on a BIM level 2 project.

The wording proposed by the Guidance makes express provision for the consequences of breaching a requirement of the Protocol by identifying such a breach as a compensation event. As such, it is particularly advantageous for contractors who should ensure it is included as a Z clause.

In addition to including the Guidance, the Works Information or Scope should be amended to include the BIM Working Party Strategy Paper draft protocol document ("the Protocol Document"). The Protocol Document was expressly drafted for inclusion into the Works Information section of an NEC3-style contract. Lastly, the parties' rights and liabilities in relation to the Protocol would need to feature in the conditions of contract, as well as the role of the Information Manager who will co ordinate the BIM.

Risk allocation

Finally, the allocation of risk under the unamended NEC3 is absolute and is firmly swayed in favour of the Employer. Clause 80.1 sets out a relatively short list of employer risks, and under Clause 81.1, as a general rule, the contractor is responsible for all other risks from the commencement of the works until the issue of the defects certificate. Under Clause 83.1, the Contractor must provide an indemnity to the employer in respect of its risks.

The contractor's risks are covered by the provision of joint names insurance under Clauses 84—87 by the contractor, but there is nothing requiring the employer to take out insurance in respect of its risks unless express provision is made for those risks in the Contract Data.

This blanket allocation of risk and the largely uninsured risks that are to be covered by the employer are very onerous to contractors, and contractors should therefore consider what risks should rightly be borne by the employer, having regard to the nature of the works. Any non-standard Employer risks that can be agreed, such as any loss or damage caused by civil war, should be included in the Contract Data, with provision for the employer to insure against them.

Practical tips when amending NEC3

  • Make sure that any Z clauses or other amendments you introduce are drafted in the same style and language as NEC3 and any other contract documents you might have, to avoid creating any discrepancies or contradictions in relation to the remainder of the contract. As a belt and braces measure, ensure that your Z clauses fit into the logic flow charts that accompany NEC3.
  • Check to see whether any Z clause or other amendments you draft have an effect on any other provisions of the contract, or require any further information to be added to the Contract Data or Works Information. If you do not do so, your amendments may create unintended consequences or may not work properly due to the operation of another core clause of the contract.
  • Consider whether your Z clauses impose any additional obligations on the other party, or on the project manager. If so, the other party or project manager should be made aware of what is required.
  • Any amendments you make should be made back to back with any other NEC3 contracts or subcontracts up or down the contractual chain if they are to be effective.
  • Consider whether your Z clauses have any insurance implications. If you can, try not to include a Z clause that cannot be covered by insurance.

Conclusion

Whilst NEC3 invites the parties to prepare their own contract conditions through secondary option Z, extensive use of Z clauses tends to undermine the NEC3 partnering ethos, which requires the parties to act collaboratively and in the spirit of mutual trust and cooperation.

Any amendments to NEC3 should be made in a manner that is consistent with and takes account of the other clauses in NEC3, as in the event of a dispute, the contract will be interpreted as a whole, and unless the contract provides otherwise (and an unamended NEC3 does not), then greater weight will be given to any Z clauses than to the standard form clauses. Unless Z clauses are drafted with great care, they have the potential to create more problems than they solve.

Footnotes

1 See http://codebim.com/wp-content/uploads/2013/06/BIMwithNEC3guide.pdf

Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.