UK: Proposed Changes to the Compulsory Purchase Regime

Last Updated: 20 November 2002
Article by Ian Ginbey

Introduction

In December 2001, the Government published its consultation document "Compulsory Purchase and Compensation: delivering a fundamental change" as part of its proposals to review the compulsory purchase regime. This has now been followed by the publication in July 2002 of a draft Circular entitled" Compulsory Purchase Orders". The draft Circular has been issued for public consultation until 31 October 2002. Simultaneously, the Government's policy response, "Compulsory Purchase Powers, Procedures and Compensation: The Way Forward" has been published.

Ultimately, the Circular will replace the extant advice in DOE Circular 14/94 albeit it is designed to address a wider range of issues. Enabling legislation will also follow to facilitate delivery of the Government's response. This ongoing work is being addressed by the Law Commission.

The Government's Response

The Government recognises that the present system of compulsory purchase is lengthy and cumbersome, and proposes (in summary) the following changes:-

1. The planning basis for a compulsory purchase order ("CPO") as set out in Section 226 of the Town and Country Planning Act 1990 ("the Act") will be replaced by a wider power. A local planning authority will be empowered to compulsorily acquire land for the purpose of carrying out development, re-development or improvement which it considers will be for the economic, social and/or environmental benefit of its area. Hence, it will no longer be necessary to demonstrate that the land is "required" (see our comments below).

2. An acquiring authority itself will be able to confirm an unopposed CPO.

3. The asset being acquired will be valued on the date on which the authority enter and take possession.

4. New consolidated Inquiry Procedure Rules will be published.

5. All those with an interest in land (including short term tenants for a month or less) will be treated as a statutory objector with a right to be heard at a public inquiry.

6. A general scheme for "loss" payments will be devised to run in parallel with existing home loss payment arrangements. Although the detail is as yet undecided, it is suggested that the new scheme could take the form of a basic loss payment for each owner, based on a percentage of the value of his interest in the property subject to a maximum cap.

7. Revised time limits for CPOs will be introduced. The overall period within which an acquiring authority has to complete the process following confirmation of a CPO will be reduced from 6 years to 3 years. A maximum of 18 months will be permitted between confirmation and service of a notice to treat (or a general vesting declaration). A notice to treat will only remain effective for a further 18 months.

8. The period between service of a notice of entry and physically taking possession will be increased from 14 days to 2 months. If the authority has not then taken possession within one month of the expiry of the 2 month period then the notice will cease to have effect and no further notice can be served.

9. The Ryde's Scale for determining surveyors fees will be revoked, and surveyors will be reimbursed in full in line with other professional advisers.

10. The current Crichel Down Rules (i.e. that compulsorily acquired property which has become surplus shall be offered back to the original owner) will be revised and the subject of a separate consultation exercise in due course.

There are further initiatives which the Government had originally considered but have now dropped including (i) the imposition of a time limit for submitting compensation claims and (ii) referrals to the Lands Tribunal.

These proposed new measures are designed to ensure that CPOs are properly made and expedited, and this approach is also reflected in the draft Circular. We distil the principal points emerging, many of which should be read in the context of the Government's response above, and proposed amending legislation which will follow completion of the work by the Law Commission.

Grounds for making a CPO

The draft guidance reiterates the principle that a CPO should only be made where there is a compelling case in the public interest. It has, of course, assumed even greater significance with the advent into the UK legal system of the European Convention on Human Rights by virtue of the Human Rights Act 1998. Inevitably, the Secretary of State must balance the intentions of the acquiring authority with the grievances of those whose land is to be expropriated. Acquiring authorities will be unable to justify confirmation of a CPO if it cannot present a clear case as to either how the land is to be used, or that the resources are unlikely to be available to deliver the proposal within a reasonable timescale.

Allied to this, the financial viability of a scheme is critical, and will be taken into account by the Secretary of State. Acquiring authorities can expect to have to demonstrate that the proposed compulsory acquisition will be completed within the statutory period following confirmation of the CPO. For most schemes, securing planning permission will be a key factor.

CPO for Planning Purposes

Section 226 of the Act (soon to be replaced) is commonly used as a justification for a CPO which is required for planning purposes. Either because (in broad terms) land is required to secure the carrying out of development or for a purpose which is necessary to achieve in the interests of the proper planning of the area.

Hence, an acquiring authority must presently demonstrate that the land to be taken is genuinely "required"; the Courts have held that "required" must mean more than "desirable". However, provided that without a CPO the purpose for which the land is required is unlikely to be achieved, acquiring authorities should not be expected to demonstrate they have used all other available powers before resorting to compulsory purchase.

In justifying the CPO, there must be a degree of certainty that the intended scheme will proceed for example by reference to an extant planning permission. However, the draft circular states, a planning permission is not seen by the Secretary of State as an essential requirement to be fulfilled before submitting a CPO for confirmation. It might be possible, for example, to make a CPO in parallel with seeking planning permission. Albeit, this will mean that the authority making the CPO will have to accept the possibility (and the associated risk) that the CPO could be rejected while planning permission is granted.

The Secretary of State will need to be reassured that there is a reasonable prospect the scheme will proceed; and a general indication of funding intentions will be necessary to demonstrate the financial viability of the scheme. The greater the uncertainty of that viability, the more compelling the other grounds for undertaking a compulsory purchase will have to be.

Preparing a CPO

Before commencing a compulsory purchase, acquiring authorities are urged to seek to acquire land by private treaty wherever possible and practicable. Quite often, given the length of time it takes to process a CPO it should be possible to carry out informal negotiations with landowners to run parallel with the CPO preparation.

The draft guidance strongly urges acquiring authorities to offer to third parties full access to alternative dispute resolution ("ADR"). This commonly involves a suitablyqualified independent third party to act as mediator on any dispute. It is speedy and relatively informal. Acquiring authorities are urged to consider ADR throughout the whole process. The draft guidance also sets out additional steps which acquiring authorities might consider during the preparatory stage of a CPO:-

  • to provide detailed information about the CPO process;
  • to appoint a case manager as a point of contact; and
  • to enter into informal contracts with third parties so as to guarantee a minimum level of compensation to be paid if the acquisition proceeds.

Acquiring authorities are urged to avoid delay. The draft guidance is clear this means that the authority should be in a position to make, advertise and submit a fully documented CPO immediately after having resolved to make it. In practice, this is likely to require a significant amount of work to be carried out in advance of referring the matter to committee for a resolution to make a CPO.

Where an authority has any doubts, particularly as to technical points, concerning the proposed CPO it is possible to submit a draft CPO to the relevant Secretary of State for technical examination. While any response from the Secretary of State will be without prejudice, it can be a useful mechanism to iron out any potential flaws in the CPO. Naturally, any response from the Secretary of State will be confined to the technical consideration of the CPO, with no assessment of its merits.

All statutory objectors have a right to be heard at a public inquiry. However, authorities are encouraged to continue any negotiations with objectors (both statutory and non-statutory) even after submitting a CPO for confirmation. This should include having regard to the possibility of ADR.

If objections cannot be resolved, then a public inquiry is likely to be held. The draft guidance suggests that an inquiry will commonly be held around three to four months after submission of the CPO for confirmation. Once an inquiry date is fixed, it will not be changed in the absence of exceptional reasons for example all outstanding objections from statutory objectors have been withdrawn.

Acquiring authorities should also bear in mind the possibility of conjoining with a CPO inquiry any concurrent inquiries; for example, this might include an inquiry to objections into a proposed road closure order. This is quite common in the context of large development schemes.

While the Secretary of State has the power to modify any CPO, such powers are rarely used and, even when they are, cannot be used to re-write CPOs extensively. Significant matters, such as the substitution of a different statutory purpose for which the CPO has been made, cannot be a matter for modification. It would require a new CPO to be made and submitted for confirmation.

Implementing the CPO

The period from confirmation of a CPO until the passing of ownership can be lengthy; a notice to treat need only be served within three years of confirmation, and there then follows a further three years during which the notice to treat remains effective. Third parties, whose land is affected by the CPO, can therefore sometimes face a wait of up to six years before they know for certain that their property will be acquired.

The draft guidance recognises that this can be unsatisfactory for third parties and, therefore, urges acquiring authorities to keep affected third parties fully informed about the process as well as the likely timetable. Allied to this, acquiring authorities are advised to open the possibility of earlier acquisition by agreement where requested by a third party.

It is possible to simultaneously serve both a notice to treat and a notice of entry; in the case of the latter, this provides a third party with no less than 14 days' notice of the authority's intention to gain entry. Acquiring authorities are urged, in the draft circular, to adopt a timetable for entry of premises which is more sympathetic to the needs of those who are being dispossessed having regard to steps which they need to take to vacate their properties.

As an alternative to a notice to treat, an acquiring authority might prefer to adopt the general vesting declaration procedure. In this way, an authority can secure title to the land without first having been satisfied as to title or having to settle the amount of compensation. Such a declaration may be made for any part or all of the land included in the CPO; however, it will not be effective against interests in respect of which notice to treat has already been served, minor tenancies, or long tenancies which are about to expire.

Authorities are advised to execute a general vesting declaration within three years of the CPO becoming operative.

Compensation

The compensation which is payable upon compulsory acquisition should represent the value of the land which comprises:-

  • open market value i.e. the amount which the land might be expected to realise if sold on the open market by a willing seller;
  • severance and/or injurious affection; and
  • disturbance and other losses not directly based on the value of the land.

Where the open market value cannot be ascertained or (even when combined with compensation for disturbance) it would be insufficient to enable the third party to relocate his activity, then compensation is payable on the basis of equivalent reinstatement. In the absence of agreement between the parties as to open market value, it is left for determination by the Lands Tribunal.

In relation to a general vesting declaration, compensation (and interest) is assessed as at and from the vesting date. However, where a notice to treat is served, the valuation date is either the date on which the acquiring authority takes possession (i.e. the date of entry) or, if earlier, the date on which compensation is agreed by the parties (or determined by the Lands Tribunal).

If an acquiring authority takes possession before compensation has been agreed, it is obliged to make an advance payment on account of any compensation which is due. The amount which must be paid is 90% of the acquiring authority's estimate of the compensation due or, if the amount of compensation has been agreed, 90% of that figure. The advance payment must be paid within three months of the claimant's written request. The draft guidance is clear that authorities should adopt a responsible approach towards making such payment, have regard both to timing and quantum, so as to provide claimants with sufficient liquidity to ensure satisfactory relocation. Acquiring authorities should also consider the possibility of making earlier payment where justified to enable claimants to proceed with reinstatement, and alleviate any obvious hardship for third parties.

Summary

It is quite clear that the proposed new guidance, and the Government's response, are designed to ensure that acquiring authorities are cognisant of the need to expedite the compulsory purchase process, whilst balancing the interests and needs of affected landowners. This is a welcome move, since it is generally acknowledged by practitioners that the present system is archaic and overly complex, and quite often acts as a deterrent to early delivery of detailed development schemes. In practice, we suspect material change is unlikely until the Government has formally implemented its proposals in the guise of primary legislation.

This article is intended to raise your awareness of certain issues (as at September 2002) under the laws of England and Wales, and is not intended to be comprehensive or a substitute for proper advice which should always be taken for particular queries.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.