The Electricity Market Law numbered 6446 (the "EML") came into force on March 30, 2013. Along with its many novelties the new law introduced a highly debated provision related to generation licenses, which subsequently resulted in the cancellation of 27 generation licenses by the Energy Market Regulatory Authority ("EMRA") in August 2014. It is estimated that more than 500 generation license holders with an estimated total installed capacity of 23,000 MW are within the scope of the provision and may also suffer a similar fate upon the evaluation of their construction status.

The EML's Provisional Article 9 laid out that the legal entities whose pre-construction terms provided under their generation licenses had expired would be granted an additional six-month grace period and further stipulated that any failure to complete the obligations of the pre-construction term, except for force majeure events, would result in cancellation of the generation license. However, because Provisional Article 9 did not set out any timeline in relation to the starting point of the foregoing six-month period, the exact date to complete the obligations remained unclear until the issuance of secondary legislation.

Seven months after the effective date of the EML, the Electricity Market Licensing Regulation (the "Licensing Regulation") was published in the Official Gazette No. 28809 on November 2, 2013 and introduced the provisions for the implementation and interpretation of Provisional Article 9. The provisional article of the Licensing Regulation stipulated that legal entities, whose pre-construction term had expired as of the effective date of the Licensing Regulation (November 2, 2013), had to submit all documentation proving that they completed their pre-construction obligations within six months starting from November 2, 2013. In the case that the pre-construction term of the legal entities has not expired, they would be granted an additional six months in addition to their remaining license term. The foregoing period expired on May 2 for the legal entities whose pre-construction terms had already expired by November 2, 2013.

Even though the timeline to complete the obligations and the nature of the sanctions became prominent with the issuance of the Licensing Regulation, the EMRA did not cancel any licenses immediately after May 2. This was regarded as a sign that a new arrangement or evaluation method was being considered by the EMRA. This understanding was further supported by the unofficial statements of the EMRA officials, which indicated that the target of the provision was to prevent the license exchanges and "actual investors" would not be subjected to sanctions.

However, contrary to the general belief by the market players, the EMRA cancelled the licenses of 13 legal entities that were unable to complete their pre-construction phase obligations on August 71. After the initial cancellations, the EMRA cancelled another nine licenses on August 212 and five other licenses on August 273.

The EMRA has reportedly stated that there were 500 projects that failed to complete their pre-construction phase obligations and the status of 132 of the 500 projects, whose construction completion rates are below 5 percent, would be evaluated initially and be made subject to cancellation. In addition to the cancellation of the licenses of the facilities, holders of the cancelled licenses and their board members and the shareholders above 10 percent will be prohibited from obtaining new licenses in the electricity market for three years. Furthermore, the bank letters of guarantees provided by the license holders gets recorded as revenue by the EMRA as a result of the cancellations.

The major criticisms raised against the Provisional Article 15 of the Licensing Regulation are in relation to the scope and nature of obligations that should be accomplished during the pre-construction phase. Below is a list of these obligations, which will then follow a look into the background of the criticisms:

  1. The legal entity must acquire the property and/or usufruct rights pertaining to the field where the generation plant will be constructed (Provisional Article 15/a).
  2. Development plans for the generation plant must be approved by the relevant authority (Provisional Article 15/b).
  3. Project pre-approval for the generation plant must be obtained (Provisional Article 15/c).
  4. Application to execute System Connection Agreement and System Utilization Agreement with TEİAŞ or relevant distribution company shall be submitted (Provisional Article 15/ç).
  5. Opinion in accordance with the Regulation on Forbidden Military Zones must be obtained (Provisional Article 15/d).
  6. Application to obtain the Technical Interaction Permission must be submitted (Provisional Article 15/e).
  7. Environmental Impact Assessment decision must be obtained (Provisional Article 15/f).

At the time the former legislation was in place almost all of the above requirements were to be completed during the construction period of the generation plants, if not after the construction phase is finalized. From the start, the market perceived the six-month completion period suggested under the EML and Licensing Regulation unrealistic, as the completion of certain items on the above list usually requires a minimum 12 to 24 months and sometimes even last after the plant is under operation. It came with no surprise that almost all investors who suffered from cancellation decisions by EMRA claimed that their failure to complete the obligations was mainly driven by the delays experienced before multiple public institutions. Those claims will obviously be settled before administrative courts, which have the competence to try cases against EMRA rulings.

On the other hand, there is always room to evaluate and discuss the ratio legis behind these legislative efforts. In fact, although some of the above-mentioned requirements such as obtaining the military zone approvals may be accomplished timely, the above cited market perception is hardly debatable, especially for some more sophisticated procedures that require trying cases before civil and/or administrative courts or those that require the involvement of different branches administration.

If we look at the requirement seeking for finalization of the development plans, the major obstacle awaiting the investors is to obtain the opinion and/or approvals of approximately 40 different public institutions. In most cases investors complain of being unable to locate the correct institution or point of contact for any specific matter in question. Even if the correct institution is located, there are many shifts in the planning and development of lands and forest areas on a major scale, which delays or sometimes even blocks the approval of the plead request. In most operational power plants the development plans must have been finalized during the construction period, but not in the pre-construction period due to delays experienced on the basis of the identified circumstance.

When one looks at the expropriation process the situation is even worse, as it usually takes a minimum of two to three years to finalize the whole process after the expropriation decision is taken by the EMRA. One can hardly argue a statement that it is even harder to finalize the acquisition of the usufruct rights on the expropriated property than to finalize the long-lasting expropriation process itself. The timeline for the expropriation process is mostly dependent on the approach of the property owners to the process and if the owners incline to settle with the expropriation order a long lasting court phase is initiated, which alone may take even longer than the average estimated time for the whole expropriation process itself. Due to this very reason, it is a well-known fact that in today's Turkey that there are power plants operating without completing the expropriation process. Actually, the Ministry of Energy and Natural Resources, as the authorized public entity to carry out the acceptance procedures of the energy facilities, orders "temporary acceptance" of such plants. These temporary acceptances are converted into "definite acceptances" once the expropriation and all other formalities are completed. It is surprising to see that there are no time restrictions to convert the temporary acceptances into permanent acceptances. This mere approach itself shows that a shift in law making and legislation is being experienced in the field by the introduction of the EML and the Licensing Regulation.

Current Environment and What to Expect

The EMRA has not made any cancellations since the decisions taken in August, which affected 27 generation licenses and their holders. While the reasons behind the EMRA's silence are unclear, an expectation has arisen in the market that a new legislative effort to follow soon for enactment of new regulations to supersede the currently relevant provisions of the EML and License Regulation.

One reason behind the EMRA's move to stop of the cancellations might be reconsideration of the potential impact of such a large number of license cancellations on the targets the government has set in its efforts to decrease the percentage of imported energy. Considering that banned legal entities and their shareholders above 10 percent are not able to apply for new licenses in the electricity market for three years the effects of cancellation of all licenses on the amount of energy generated cannot be set aside.

The ongoing debate regarding identification of the delays caused by the other public authorities as force majeure might be another reason behind EMRA's hesitation to cancel the remaining licenses within the scope of Provisional Article 9 of the EML. Many reports received from the sources of energy associations indicate that the EMRA intends to re-evaluate the projects considering their force majeure status and start to grant additional time to projects having problems with the other public authorities.

A draft law dated June 16 amending Provisional Article 9 of the EML (the "Draft Law") was presented to the Grand National Assembly of Turkey by the Ministry of Energy and Natural Resources. The Draft Law suggested amending Provisional Article 9 of the EML to provide an additional year for license holders to complete their pre-construction obligations. In addition to an extra one-year period, the Draft Law was foreseeing defenses for investors on the basis of "reasonable causes that are not related to the license holder". These defenses, once put forward by the license holders in view of their pre-construction phase requirements would enable the EMRA to grant additional time and amend the generation license so that the license holders are able to complete the construction of the facilities. While the Draft Law has still not been passed as of November, in the event that it does, any further license cancellations would be ceased.

In case the EMRA decides to grant additional time to remaining license holders or a new legal arrangement is accepted throughout the ongoing legislative efforts, not only the future circumstances regarding the concerned 500 licenses may change, but also the status of the license holders that previously had their licenses cancelled by the EMRA may be positively affected. It is therefore worthwhile keeping an eye on the future developments in this end.

1 Decisions dated 7.08.2014 numbered 5156/4-6-8-13-15-17-19-20-21-23-26-27-29 published in the Official Gazette dated 19 September 2014 numbered 29124.

2 Decisions dated 21.08.2014 numbered 5176/2-4-5-17-31-32-36-37-40 published in the Official Gazette dated 19 September 2014 numbered 29124.

3 Decisions dated 27.08.2014 numbered 5187/40-7-8-13-14-15 published in the Official Gazette dated 19 September 2014 numbered 29124.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Burcu Tuzcu Ersin, LL.M.
C. Hazal Tunçay
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.