South Africa: Winds Of Change In South Africa

Last Updated: 7 February 2012
Article by Clint Steyn

In 1960 Harold Macmillan made his famous "Winds of Change" speech that was a watershed moment in South African politics and that signaled a seismic shift in attitudes. Today, winds of change of a different sort are blowing in the energy sector in South Africa, with the sector poised to make a significant shift away from an overwhelming reliance on fossil fuels to renewable energy.

Security of electricity supply in South Africa is highly precarious. South Africa's electricity demand has substantially increased since 1994. However, no new power stations were built leading to a decline in reserve margins. In 2008, South Africa endured significant load shedding and rolling black outs. Eskom, South Africa's state-owned utility, says power supply to South Africa will remain tight, with the risk of blackouts "significantly" increasing from 2011 to 2013, and then again from 2018 to 2024.

Eskom has indicated that the country needs to add 50,000 megawatts of new generating capacity by 2028. South Africa's current generating capacity of approximately 40,000 megawatts is predominantly made up of coal, which accounts for about 90% of all domestic generation. Virtually no renewable generation exists currently.

It is a government aspiration that renewables will account for a significant proportion of new capacity.

The year 2011 looks set to be a breakthrough year for the renewable energy sector in South Africa.

On August 3, 2011, the Department of Energy launched the first-ever procurement process for renewable energy in South Africa. Under the first round of this program, South Africa will try to procure 3,725 megawatts of capacity by 2016.

The launch of the renewable procurement program followed from the issuance in March of a long-awaited integrated resource plan that featured a substantial and ambitious increase in renewable energy targets, up from 30% of new-build generation to 42%.

The run up to the launch of the renewable program was not without a few twists and turns along the way. But before we consider in detail the current state of play of the renewable procurement program in South Africa, let's go back to the beginning.

Rich Renewable Resources

As with its coal resources, South Africa is blessed with an abundance of solar and wind resources.

Wind: Africa's wind resource is best around the coasts and in the eastern highlands. It is in Mediterranean North Africa that wind power has been developed at scale, with further significant growth expected. At the end of 2009, about 96% of the continent's total wind installations of 763 megawatts were to be found in Egypt (430 megawatts), Morocco (253 megawatts) and Tunisia (54 megawatts).

Yet, despite the wealth of wind resources in Africa, under the International Energy Agency's reference scenario, only 200 megawatts of new wind capacity would be added every year until 2020. This would increase to 500 megawatts by 2030, leading to 3,000 megawatts of wind power installed in the entire African continent by 2020 and 8,000 megawatts by 2030.

In the case of South Africa, many local commentators are more optimistic, taking into account government targets and policy measures and the fact that the country is ideally suited for wind power development given its abundant wind resources, ample suitable sites and modern high-voltage electrical infrastructure.

Indeed, recent comprehensive wind mapping in South Africa has illustrated proven wind potential within the country, mostly in the coastal areas.

The South Africa Wind Energy Association estimates that with the right policy framework, wind power could provide as much as 20% of the country's energy demand by 2025, translating into 30,000 megawatts of installed wind capacity.

Solar: Every day the sun produces 100,000 billion tons of oil equivalent, while in 1998, the annual global consumption of energy was 9.8 billion tons of oil equivalent.

Both sub-Saharan and Saharan Africa have excellent solar irradiation levels suitable for efficient electricity generation, with South Africa having some of the best solar irradiation levels in Africa.

The annual 24-hour global solar radiation average is about 220 W/m2 for South Africa, compared with about 150 W/m2 for parts of the United States and about 100 W/m2 for Europe and the United Kingdom. This makes South Africa's local resource one of the highest in the world.

Specifically, the Northern Cape has excellent potential for solar power, encompassing concentrated solar power and photovoltaic technologies, with other provinces (like the Free State) also having high potential.

Ready to Take Advantage

Last year was a challenging year for the global wind industry, which saw a global decline in annual installations for the first time in almost 20 years. Structural overcapacity has led to a decline in turbine prices with Bloomberg's recently published Wind Turbine Price Index showing recently signed contracts for 2011 delivery carried a 7% discount on 2009 prices (19% discount on 2007 to 2008 prices).

Global wind power markets have been for the past several years dominated by three major markets: Europe, North America and Asia (China and India). These three markets accounted for 86% of total installed capacity at the end of 2009.

There are signs that things are changing, with emerging markets in Latin America, Asia and Africa reaching critical mass. With emerging markets like South Africa ready to start challenging these main markets in the coming years, the downward pressure on wind turbines due to market overcapacity and increased competition may result in suppliers and developers casting their eyes more intensely at these emerging markets.

It came as no surprise then that the Department of Energy received some 384 responses to a request for information for renewable energy projects issued in September 2010.

Promoting renewable energy technology in South Africa currently requires financial incentives, due to the cheaper and more reliable fossil fuel sources, but many believe that renewable energy will soon not be a more expensive option.

"The difference between the cost of new thermal generation and wind is less that you expect," says Paul Eardley Taylor, head of energy, utilities and infrastructure at Standard Bank. At the beginning of May, Eskom disclosed to Parliament that the current assumed tariff from 2015 onwards is R1.09 per kWh. The wind tariff is R1.15 per kWh, so even without carbon taxes there is not really a significant gap. Given the scale of Eskom's tariff increases, the gap between wholesale tariffs and on-shore wind keeps narrowing. "Solar is also cheaper than diesel," says Eardley Taylor.

Refit Program

With an abundance of solar and wind resources, South Africa, like many emerging markets, has adopted a feed-in tariff mechanism to promote renewable energy.

The South African government published a white paper on renewable energy in 2003, which set a modest initial target for renewable energy of approximately 4% of total generation by 2013. However the renewable energy feed-in tariff or "Refit" program was only officially announced in 2009 as part of the Department of Energy's integrated resource plan.

The Refit program covered nine technologies: onshore wind, small hydro, landfill gas, biomass (solid), biogas, photovoltaic systems, concentrating photovoltaic (without storage), concentrating solar power or "CSP" trough (with or without storage) and CSP tower. South Africa is globally unusual in having three separate CSP tariffs while still not permitting lens and dish technology.

The National Energy Regulator of South Africa — called Nersa — published its Refit tariffs in 2009 for these technologies, including a tariff of R1.25 per kWh for wind and R3.94 per kWh for solar PV.

The Refit program was given a substantial boost by the issuance in March and promulgation in May 2011 of the long-awaited integrated resource plan called "IRP 2010." The IRP 2010 outlines the proposed power generation mix for South Africa for the period 2010 to 2030.

The most striking feature of the final, so-called "policy adjusted" IRP 2010 was the increase in the overall contribution of renewable energy to the generation mix, up from 11,400 megawatts in the draft plan to 17,800 megawatts, some 42% of targeted new generation. The IRP 2010 included a defined technology split of the renewables allocation, with wind and PV each contributing 8,400 megawatts and CSP contributing 1,000 megawatts. Nuclear is expected to contribute 23% and coal 15%.

Many commentators remarked that solar PV emerged as the big winner from this process with the target of 8,400 megawatts translating into the deployment of a "staggering" 300 megawatts of large-scale solar PV per year from 2012 onwards.

By 2030, coal is still likely though to represent some 50% of the total mix at around 41,000 megawatts. Under the plan, a total of approximately 56,000 megawatts of new capacity will be added over the next 20 years, raising the country's total capacity to some 89,000 megawatts by 2030. Of the new capacity, there is a total of about 42,000 megawatts that is yet to be committed, with the balance already being built by Eskom.

Under the IRP 2010, the first phase of 1,025 megawatts of renewable projects was intended to be completed by the end of 2013. The IRP 2010 also includes time frames for the phased development of projects over 20 years, with specific megawatt allocations in different years. It required 300 megawatts of solar PV per year from 2012 to 2024, further increased to 500 to 1000 megawatts per year until 2030, and 200 megawatts of solar CSP by 2015, with 100 megawatts per year through to 2025.

Uncertainty as Nersa Intervened

Following issuance of the IRP 2010, it had been anticipated that the procurement process for the first round of a relatively modest 1,025 megawatts of renewables projects would be quickly launched by the publication of the Refit request for proposals.

However, days after it was confirmed that the role of renewable energy in South Africa's generation mix would be substantially increased, Nersa issued a consultation paper proposing a material decrease in the Refit tariffs when compared to the previously agreed and promulgated 2009 tariffs, rather than commence with the procurement process.

The proposed reductions ranged from 7% on some technologies to 41% on others, including a 25% reduction in the tariff for wind from R1.25 per kWh to around R0.94 per kWh.

In its consultation paper at the time, Nersa said that the tariffs had been reduced based on 2011 market conditions, reflecting a reduction in the nominal cost of debt and inflation, and a strengthened Rand-to-US-dollar exchange rate, since the 2009 tariffs were set.

A senior Department of Energy official confirmed in mid- June that the government intended to pursue a competitive bidding process for South Africa's first wave of renewable energy projects under the Refit program.

Ompi Aphane, the deputy director-general for electricity, nuclear and clean energy, said, "We're definitely going to have price competition on the different technologies." His comments raised questions about the future of the Refit tariffs adopted by Nersa two years ago.

There seemed to be some misalignment between the processes of Nersa and the government, with the government proposing that Refit prices, instead of applying across the board according to levels determined by Nersa, will serve as an upper guide in a competitive bidding process.

Aphane said the Refit rates would act as a "ceiling" beyond which bids would not be considered. To meet other objectives, such as localization, bidders would first be required to pass a set of minimum requirements. "Those that make the thresholds then go into the next comparison, which is price."


Though there had been discussions in the sector about the possibility of a revision in Refit tariffs, particularly in light of improvements in technology pricing and as a result of a change in exchange rate assumptions used, Nersa's announcement came as a shock to the industry, in light of its timing a week or so before the procurement process was widely expected to commence.

Nersa's move appeared to surprise even the Department of Energy, which initially said that the higher tariffs should apply for the first round of Refit bids to go out to tender because their projects had to be ready by 2013 and would therefore cost more.

The proposed tariff changes and the mooted adoption of a competitive bidding model raised alarm in the sector, while the magnitude of tariff drops worried some technology segments.

South Africa Wind Energy Association board member Ian Macdonald has said that recent developments were "disappointing," particularly owing to the fact that, until April, the one constant in the much delayed renewables process had been the tariff. The 2009 Refit stimulated material investor interest. It is estimated that wind energy developers had already risked over ZAR 400 million developing projects to participate in the Refit program on the premise of the tariffs promulgated in 2009.

Many in the renewables sector have argued that the Refit model, which offers a guaranteed purchase price, had emerged as "best practice" globally for supporting the development of the fledgling renewables sector.

More than 60 countries had pursued the model and developers argued that it has delivered better results when compared with those countries that opted for competitive bidding. The key danger, they argued, is that inexperienced and overly-optimistic developers bid low in order to secure the tender, but are then unable to raise the project finance required to construct projects.

The wind trade association pointed to a detailed 2008 analysis by the European Commission that concluded that "well-adapted feed-in tariff regimes are generally the most efficient and effective support schemes for promoting renewable electricity."

In contrast to most of the renewables developers, there were some developers, particularly in the solar sector, who supported the tariff reductions, with Olivier d'Huart of PV manufacturer Amonix saying that the revised solar tariffs were internationally competitive and that the 2009 tariffs were "over generous."

Renewables Program Launched

The long-awaited procurement process for South Africa's first renewable energy projects commenced on August 3, 2011 with the publication of the South African renewable energy IPP request for proposals.

The request for proposals seeks to procure 3,725 megawatts of renewable generation by 2016 in the first round of procurement. This is a significant increase from the 1,025 megawatts of capacity that market commentators had been expecting.

There is a defined allocation between various renewable technologies, and the request for proposals sets a tariff cap for each technology. A bid will be considered non-compliant and be automatically rejected if the price cap is exceeded. The table below summarizes this allocation as well as the relevant tariff caps.

A key feature is the significant increase in allocation of capacity to solar PV.

The evaluation criteria in the request for proposals contemplate a two-step tender process. Projects will first compete on a number of "qualification" criteria and gatekeeper issues such as status of land rights, environmental permitting and various technological and financing criteria.

Those projects that get through the first round will then move to round two where they will compete against each other on certain stipulated evaluation criteria. The two main criteria are price and economic development.

Each technology has its own economic development matrix, but common to all are questions of job creation, local content (with special emphasis on local manufacturing), rural community development, skills development and education, enterprise development, socio-economic development and participation by the historically disadvantaged. The points allocation between price and economic development is 70/30.

There are five bidding "windows" — November 4, 2011, March 5, 2012, August 20, 2012, March 4, 2013 and August 13, 2013. If the maximum allocable megawatts for any particular technology have been allocated during any particular window, then the subsequent windows will not be opened for that technology.

The request for proposals includes a drafts of a power purchase agreement, implementation agreement, direct agreement and connection agreement. Unusually these agreements are non-negotiable and no bidder mark ups will be allowed.

Bidders whose responses rank the highest will be appointed preferred bidders, with as many being appointed as may be necessary in order to provide the maximum allocation of megawatts for each technology. These bidders would then need to conclude a power purchase agreement with Eskom, finalize connection agreements and sign an implementation agreement with the Department of Energy. Projects bidding in the first window are expected to reach financial close by June next year.

Eskom has been specifically excluded from bidding any of its renewables projects, and the state-owned utility's role has been confined to that of buyer and to connecting the projects to its grid.

Market Response

Market reaction has generally been positive. "We're impressed with the request for proposals," said Standard Bank's Eardley- Taylor. "Although it has been along time coming, it is a solid eight out of 10."

Potential developers have indicated that the tariff caps did not appear to be unrealistic, but some were concerned about the number of requirements being added that were unrelated to the core business of power generation.

The Department of Energy has confirmed that more than 400 companies paid the R15,000 application fee to receive the bid documents, although about 270 of those could be considered to be potential IPP developers with the balance being made up of potential financiers and equipment suppliers.

The government is understood to be very pleased with the response, particularly against the backdrop of the initial disquiet expressed by potential developers when it was confirmed that the renewable energy feed-in tariffs had been abandoned in favor of a competitive bidding process.

Director General Nelisiwe Magubane said the response had been "better tan expected" and that further applications were likely from foreign and domestic companies. She added that the response also bodes well for delivery on the objective of building a "sustainable" renewables industry, which could lead to development of some 18,000 megawatts of renewable energy by 2030.

It has taken a while and there have been twists and turns along the way, but the renewables program in South Africa is up and running.

With the first round of the procurement process expected to generate between $10 billion and $12 billion in foreign and domestic investment in the renewables sector in South Africa, it appears the winds of change in the energy sector in South Africa are more than just hot air.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.