Worldwide: Adjudication Series: A Comparative Perspective

Last Updated: 31 October 2019
Article by Arthur Cox
Most Read Contributor in Ireland, November 2019

Over the last weeks we have looked at the new regime for statutory adjudication in the construction sector in Ireland from a range of perspectives. In this final article we look at what's happening in other parts of the world in which (for the most part) similar regimes have been in place for longer.

There are common features that underpin statutory adjudication across most jurisdictions. For example, the key aim is ensuring cash-flow in the construction industry by providing prompt payment mechanisms backed up by a right to refer disputes to be adjudicated on speedily, usually during the life of a project. Another typical feature is the fact that an adjudicator's decision is binding in the interim (so payment ordered must be made) and can only be set aside by a court on fairly narrow grounds (though parties may ultimately litigate, arbitrate or reach alternative agreement if they continue to be in dispute). Pay-when-paid provisions are typically outlawed, and parties usually cannot contract out of the legislative framework.

So what's the picture in other jurisdictions and what are some of the main differences?

UK

Statutory adjudication was first introduced in the UK in 1998 pursuant to the Housing Grants, Construction and Regeneration Act 1996. The key difference in the UK is that a party to a construction contract has the right to refer for adjudication "a dispute" (not "payment disputes", as in Ireland) arsing under the contract. That there are many similarities between our systems is helpful: to date there are no Irish court judgments on adjudicators' decisions, but there are many from the UK Technology and Construction Court and these, properly interpreted, provide helpful guidance.

The regime in Northern Ireland is aligned with the UK. Given that we've just reached the twentieth anniversary of the introduction of adjudication in Northern Ireland, and its proximity to Ireland, we'll focus in this article on the story there so far.

Northern Ireland

In Northern Ireland statutory adjudication is provided under the Construction Contracts (Northern Ireland) Order 1997 (the "Construction Order") and the Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999 (the "Construction Scheme"). Where a construction contract does not comply with the prompt payment and /or adjudication provisions in the Construction Order, Schedule 1 of the Construction Scheme applies.

The legislation allows a party to a construction contract to refer a dispute to adjudication under a defined procedure which requires an adjudicator to reach a decision within 28 days of referral (or longer if agreed by the parties), safeguarding the adjudication mantra of "pay now argue later".

The number of adjudications in Northern Ireland has steadily increased and there have been a number of significant enforcement judgments. The grounds upon which an adjudicator's decision may be resisted are more restricted than would normally be the case in summary judgment proceedings. An adjudicator's decision typically can only be set aside on the basis that the adjudicator lacked jurisdiction to decide the matter and / or that there was a breach of the rules of natural justice. Outside of these limited points of defence, even if the adjudicator incorrectly implemented the procedure or erred on the facts or in law, the Adjudicator's decision may still be enforced.

The courts in Northern Ireland have acted to promote the success of adjudication by ensuring that expedited processes are in place to deal with enforcement actions. The Commercial Court's new Practice Direction 01/19 and Business and Property Hub play a welcome part in this.

These are some main decisions from the High Court in Northern Ireland.

Coleraine Skip Hire Ltd v Ecomesh Ltd [2008] NIQB 141 (27 October 2008)

In this first application for summary judgement to enforce an adjudicator's decision in Northern Ireland, Ecomesh applied for summary judgment in the sum of nearly £50k. Coleraine resisted on several grounds which provide a good overview of the nature of possible challenges that may be argued. (They were that some of the works were not "construction operations"; that the adjudicator issued his decision outside the permitted statutory timeframe; and that the adjudicator's amendment of his decision did not come within the "slip rule"). The court found, on the facts, that these arguments could not succeed. However, Coleraine was successful on its fourth ground, namely that the adjudicator's decision should be stayed pending the outcome of ongoing court proceedings. The judge considered that the enforcement application related to only one part of the dispute between the parties and that the sum to be paid on foot of the adjudicator's decision should be considered in the balance of the wider proceedings. This decision prompted initial concerns that adjudication might not be as successful in meeting its objectives in Northern Ireland as hoped.

DG Williamson Ltd v Northern Ireland Prison Service & NIO [2009] NIQB 8 (27 January 2009)

In this second application to enforce an adjudicator's award the respondents again argued jurisdictional points and sought a stay of the adjudicator's decision pending conclusion of overall proceedings. Again, the court did not find in favour of various jurisdictional arguments on the facts. This time, however, the judge did not stay proceedings. He was "satisfied that the starting point for a court dealing with a request for enforcement of the award of an Adjudicator is that it should work on the assumption that the award ought to be enforced..... The purpose of the legislation is to ensure speedy payment by dint of a summary process and, even where there is an error, to require the money to be paid and for the matter to be sorted out later when the contract disputes are settled finally by way of agreement, arbitration or litigation." This judgment provided a greater deal of assurance that adjudication would function effectively.

Northern Ireland Housing Executive (NIHE) v Dixons Contractors Limited [2019] NIQB 19 (22 February 2019)

This recent judgment is an unusual example of an adjudicator's decision being overturned on the basis of an error of law. In this case there was a dispute over whether Dixons were required to provide window trims as part of a contract because the contractual code of practice mentioned them but they were not in the drawings. The parties agreed that, if the adjudicator found that there was an ambiguity or inconsistency between the code and the drawings, Dixons could claim for compensation for additional work in providing the trims. The adjudicator found that there was an ambiguity – so Dixons should be paid extra. When it came before the court, there was a different conclusion. The court agreed that there was a difference between the code and drawings but that, as a matter of contractual interpretation, trims were required to be fitted as part of the contract. The court found that the adjudicator erred in his decision (and invited submissions on the appropriate relief to be granted). We are not aware of this leading to loss of confidence in the system of adjudication; rather, there is acceptance that mistakes can sometimes be made and that adjudicators (who may not be lawyers) may sometimes face legal questions.

Australia

New South Wales was the first Australian State to implement a prompt payment and adjudication scheme with the introduction of the Building and Construction Industry Security of Payment Act 1999 (the "NSW Act"). The remaining Australian States and Territories followed suit between 2002 and 2009.

Under the NSW Act, a party entitled to a progress payment (the "claimant") must serve a payment claim on the other party (the "respondent") who can then reply by providing a payment schedule identifying the amount of the payment (if any) that the respondent proposes to make. If the respondent does not supply a payment schedule within the requisite time period, the respondent becomes liable to pay the claimed amount.

When can a claimant apply for adjudication? To commence an adjudication there must be a payment claim. The claimant can apply for adjudication if the respondent: (a) provides a payment schedule specifying an amount lower than the claimed amount; (b) provides a payment schedule but fails to pay the whole or part of the amount in the schedule; or (c) fails to provide a payment schedule and fails to pay the whole or part of the claimed amount.

Adjudication under the NSW Act therefore has to be linked to a "progress payment" (which includes final payments). This is more restrictive than in Ireland and has the effect that adjudications are nearly always initiated by contractors/sub-contractors 'upstream' for monies owed to them, again consistent with the "pay now, argue later" principle. There has tended to be a more liberal approach in Ireland to the interpretation of what constitutes a "payment dispute" and a number of adjudications here have dealt with termination costs and liquidated damages.

A notable feature of adjudication under the NSW Act is the swiftness of the process. The adjudicator must determine the application as expeditiously as possible and, in any event, within ten business days (or longer if agreed by the parties) after the adjudicator has notified the parties that he or she has accepted the appointment. The adjudicator can call a conference of the parties but it should be conducted informally. In reality, and in some degree of contrast to the trend in Ireland, conferences are rarely called and adjudications are generally decided "on the papers".

The adjudicator is required to determine the amount of the progress payment (if any) to be paid by the respondent, the date on which it is payable, and the rate of interest. Circumstances in which an adjudicator's decision will be overturned are narrow and it is worth noting how strictly this has been applied. In contrast to the Northern Ireland case described above, the NSW Court of Appeal last year set aside a Supreme Court decision and confirmed that an error in interpreting a contract or understanding a payment claim not does constitute a jurisdictional error by an adjudicator and therefore is not a basis for quashing an adjudicator's decision. 1

The overriding factor is to ensure that any person carrying out construction work is entitled to prompt progress payments.2 This is evident from a number of provisions of the NSW Act, including, notably, section 20, which provides that the respondent cannot include in the adjudication response any reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant. If the respondent has failed to submit any reasons in its payment schedule, it will be precluded from defending the adjudication application on different grounds. This results in a more contractor-friendly scheme, with the primary aim of improving cash-flow taking precedence.

Amendments to the NSW legislative framework are coming into force in October 2019 with the aim of reducing maximum payment times from the head contractor to the subcontractor; requiring endorsement of payment claims to link them to the statutory regime; and removing the concept of reference dates, replacing it with a statutory entitlement to make a claim once per month. Notably, amendments also aim to allow courts to sever part of an adjudicator's decision in case of jurisdiction error, allowing the remainder to be enforced. This is consistent with what seems to be the approach in NSW to avoid interference with the adjudication process save for in very limited circumstances.

Singapore

In Singapore, the Building and Construction Industry Security of Payment Act 2004 provides for statutory adjudication, which is popular and is perceived as a fast and cheap mode of dispute resolution. Once a payment claim is served for payment under a contract, the respondent must respond either by paying the amount claimed or by answering the payment claim. A respondent who disputes the claim but fails to provide a response setting out its reasons will be prevented from raising reasons at adjudication. Therefore the consequences for a respondent of failing to provide a payment response are quite serious, and they apply whether the respondent wishes to argue against the validity of the payment claim or the adjudicator's decision itself. 3

Again, the timeline for adjudication is short. An adjudicator must determine the application within seven days (if the adjudication relates to a construction contract and the respondent has failed to make a payment response and to lodge an adjudication response, or has failed to pay the response amount where it has been accepted by the claimant). In any other case, the adjudicator has 14 days (or such period as agreed by the parties).

Where an adjudicator calls a conference, each party can be represented by no more than two representatives unless the adjudicator permits otherwise. Another feature of the Singapore legislation is that, in certain circumstances, a respondent who is "aggrieved by the determination of the adjudicator" may request a review of the adjudicator's determination by a review adjudicator or panel of review adjudicators (albeit that the amount deemed payable by the adjudicator's decision has to be paid pending this review).

Canada

Only this month – on 1 October 2019 – Ontario became the first jurisdiction in North America to introduce statutory prompt payment and adjudication by way of amendment to what is now known as the Construction Act. Many of the provincial legislatures and the federal legislature are set to follow, in what seems to be a strong recognition of the effectiveness of adjudication as a proportionate dispute resolution mechanism in the construction sector.

Under the payment system, a "proper invoice" is issued and, if it is disputed, the respondent must give a "notice of non-payment" or pay the full amount. Time periods within which this must be done vary according to contractual level (i.e. owner to contractor, contractor to sub-contractor etc). It is notable that failure to comply with the prompt payment provisions triggers remedies including, in certain circumstances, mandatory referral to adjudication. For example, if a contractor decides not to pay its subcontractor because the contractor has received a notice of non-payment from the owner, the contractor is required to refer its dispute with the owner to adjudication.

While, as in Ireland, the adjudication regime gives teeth to the prompt payment provisions, unlike Ireland, adjudication is intended to deal with disputes wider than just "payment disputes". Any party to a contract or subcontract may refer to adjudication a dispute relating to areas set out in the legislation, which lists most matters that could arise in construction projects. The adjudicator must make a determination of the dispute within 30 days of receiving documents from the parties (or such longer period as the parties agree).

Malaysia

Statutory mechanisms for prompt payment and adjudication came into effect in Malaysia on 15 April 2014 pursuant to the Construction Industry Payment and Adjudication Act 2012.

Though Malaysia's system also follows common principles there are some key differences. The legislation applies only to largescale commercial construction. Buildings of less than four storeys high that the contractor will occupy are carved out of the regime. The legislation also does not impose a mandatory right to interim payments. Payment requirements under the legislation are based on contractual payment dates. If a payment is not made by a due date, the unpaid party issues a claim for non-payment. The paying party has 10 working days to make payment or dispute the claim. Interestingly, in the absence of issuing a payment response, the respondent is taken to dispute the entire amount due. Once a notice of adjudication is served and the adjudicator is appointed, there is a relatively lengthy process in which periods of time are allocated for negotiation of the terms of the adjudicator's appointment and for parties' submissions, followed by a period of 45 working days for the adjudicator to reach a decision.

Use of statutory adjudication in Malaysia has grown rapidly and there has been a significant volume of caselaw addressing various issues that have arisen such as whether the legislation applies to contracts entered into before 15 April 2014, and whether a respondent can raise a defence in adjudication based on events that happened after the issue of a payment response or notice of adjudication. The limited circumstances in which an adjudicator's decision can be set aside are broadly similar to those we have seen applied by the UK courts. In Malaysia, they are specified in legislation as follows: if the decision was improperly procured through fraud or bribery; if there has been a denial of natural justice; if the adjudicator has not acted independently or impartially; or if the adjudicator has acted in excess of his jurisdiction.

Shared experiences

In Ireland the courts have not yet had to deal with any cases arising from statutory adjudication under the Construction Contracts Act 2013. There are, however, many decisions from courts in other jurisdictions that provide useful guidance on how similar provisions have been interpreted elsewhere.

One issue that will inevitably be shared across all jurisdictions is the authority of the court to quash a determination by an adjudicator for jurisdictional and/or non-jurisdictional error. The general trend of court decisions is to "save" the adjudicator's decision wherever possible. That said, each national court, in addition to interpreting the specific domestic legislation governing adjudication, operates within a wider context of national law. For example, in Ireland the impact of the Constitution means that principles of natural justice and fair procedure may have a greater impact on the conduct of adjudications, both in terms of whether oral hearings are required and also as regards decisions to extend timelines.

That a dispute resolution process has been introduced – and is being introduced – in so many different jurisdictions, says something about its success as a proportionate mechanic to meet the needs of the construction industry, specifically in terms of maintaining healthy cash-flow. It is not always perfect but, in many situations, it really is quite effective.

Footnotes

1. Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd [2018] NSWCA 339. See also Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4.

2. This was re-iterated by the High Court in Probuild, [2018] HCA 4, at paragraph 4.

3. Australian Timber Products Pte v A Pacific Construction & Development Pte Ltd [2013] SGHC 56.

This article contains a general summary of developments and is not a complete or definitive statement of the law. Specific legal advice should be obtained where appropriate.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Related Articles
 
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions