Canada: Need And Resistance: A Review Of The Status Of Major Canadian Pipeline Projects In 2014

Pipeline capacity continues to lag North American production gains. Increased pipeline access to refineries in the U.S. and Eastern Canada and, particularly to the coasts and new international markets beyond, remains critical for the Canadian energy sector even with oil prices perilously low. Alberta's Premier recently reported that lack of access to oil markets cost the federal and Alberta government about $6 billion last year alone. Access is needed to (i) reduce the impacts of the discount that Western Canada Select heavy crude sells for; and (ii) mitigate against the impacts of the increased reliance of U.S. markets on its own domestic production, particularly Marcellus and Utica shale gas and Bakken shale oil. We have seen this reality play out over the last number of years on TransCanada's Canadian Mainline, where even the Ontario and Quebec markets are placing ever-increasing reliance on shorthaul capacity from the Dawn Hub in favour of historic reliance on longhaul capacity from the WCSB.

In this climate of much needed access, pipeline projects necessary to access  refineries and new markets are continuing to face fierce resistance. Opposition from First Nations and environmental groups continued throughout 2014; heading into 2015, the new source of resistance is political, and comes from our very own provinces and municipalities. While their jurisdictional and constitutional footing to make demands or impose certain conditions on particular pipeline projects is questionable, their influence is unmistakable and their concerns will have to be addressed. After all, public expressions of a lack of confidence in Canada's federal energy regulator from provincial governments do little to instill confidence in Canadian energy sector investors. 

Developments over the course of 2014 on various major approved and proposed pipeline projects are outlined below. While slumping oil prices may have an impact on whether some of these pipelines are ultimately built, given the long lead-times required to navigate regulatory and appeal processes, and to construct major pipelines, we do not expect current oil prices to significantly influence the proponents' continued pursuit of the projects discussed below. 

Energy East

TransCanada filed its application for approval of its Energy East Pipeline Project with the National Energy Board on October 30, 2014, some three business quarters later than anticipated. The holdup? Presumably learnings from the Enbridge Northern Gateway project gave rise to serious introspection on the adequacy of TransCanada's consultation program. Additionally, TransCanada would certainly have been motivated to keep the Energy East project as far away from its Mainline Toll Settlement proceeding as possible given that a segment of the natural gas pipeline to be repurposed as part of Energy East is being used at capacity and has been the subject of demands for new capacity given its location within the "Eastern Triangle", where Ontario and Quebec distribution companies had been fighting tooth and nail with TransCanada for greater access to the Dawn Hub and the Marcellus and Utica gas beyond. This is why Quebec's largest gas utility has been splashing full-page ads opposing Energy East in national newspapers.

The Energy East Pipeline is TransCanada's $12 billion project comprised of a proposed 4,600- kilometre pipeline to carry 1.1-million barrels of crude oil per day from Alberta and Saskatchewan to refineries in Eastern Canada (Montreal, Levis and St. John). The project entails converting 3000 kilometres of an existing natural gas pipeline to oil service between Saskatchewan and Ontario, and building 1600 new pipeline segments in Alberta, Saskatchewan, Manitoba, Eastern Ontario, Quebec and New Brunswick to connect with the converted pipe (plus 250 kilometres of new natural gas capacity to replace the fully utilized segment discussed above). There are also numerous associated facilities, including two export marine terminals.

Just a month after filing its application, amidst public and political outcry, TransCanada has put its plans for a controversial marine terminal in Cacouna, Quebec on hold. The announcement came on the heels of a report by a federal government wildlife committee concluding that beluga whales in the area are endangered. It also came just a week after the Premiers of Ontario and Quebec announced that Energy East would have to meet seven conditions before they would approve the project in their respective provinces. Of course, the provinces' approval of the project is not strictly necessary, but that's a discussion for another day. Of the seven conditions, most notable are demands that natural gas capacity be sufficient to meet the needs of the respective provinces (i.e. the Mainline end game), and that the project be subject to a comprehensive environmental assessment taking into account greenhouse gases. This last "condition" will likely be the subject of most controversy and it is not clear that the Ontario and Quebec Premiers had the same scope of assessment in mind. Quebec appears to be seeking an environmental assessment that includes consideration of upstream greenhouse gas emissions from production outside the province. The National Energy Board has consistently refused to require the inclusion of upstream gas emissions in its assessment of other pipeline projects. In fact, the failure to include upstream emissions in its environmental assessments is one of the issues before the Federal Court of Appeal in the numerous appeals and judicial reviews of the approval of Northern Gateway.

The regulatory review before the National Energy Board is anticipated to take 18 months. Should Energy East be approved, TransCanada anticipates that the pipeline could be in service for deliveries in Quebec and New Brunswick by late 2018. In 2015, watch for political maneuvering as Alberta Premier Jim Prentice engages in productive conversations with other provincial leaders to extoll the overwhelming economic benefits of Energy East while appreciating the need for a common and meaningful approach to environmental issues. Notwithstanding its PR false start, we anticipate that Energy East will be approved and built within a reasonable timeframe. The need to move Canadian oil through Canadian refineries and then on to tidal waters converges with 3000 kilometres of existing right of way and mostly unutilized Mainline capacity.

Trans Mountain Expansion

On the other side of the country, all is not well in Burnaby B.C., where protesters successfully impeded Trans Mountain's ability to complete aspects of additional geotechnical studies to support its proposed revised routing through Burnaby Mountain to avoid the streets of Burnaby between the Burnaby Storage Terminal and the Westeridge Marine Terminal.

Kinder Morgan filed its application for approval of the $5.4 billion Trans Mountain Expansion Project with the National Energy Board on December 16, 2013. The project contemplates the twinning of the existing 1150 kilometre Trans Mountain pipeline from Edmonton, Alberta to Burnaby. to increase the capacity of the system from 300,000 barrels per day, to 890,000 barrels per day. The existing line would carry refined products, synthetic crude oils, light crude oils with capability for heavy crude oils, while the new line would carry heavier oils. Significantly, the expansion project also includes the expansion of the Westridge Marine Terminal in Burnaby to be expanded with three new berths that would increase the number of tankers to be loaded and to travel down the Burrard inlet from 5 to 34 per month.

On April 2, 2014, the National Energy Board announced that it would hold a public hearing with a legislated 15 month timeframe. There are 1650 registered participants in the process, 400 of which have been granted full intervenor status to participate in the public hearing (the most to ever participate in the hearing process). In August of 2014, the National Energy Board extended the process by seven months to consider supplemental materials related to Kinder Morgan's proposed revised controversial routing through Burnaby Mountain. This pushes the National Energy Board's recommendation to the Federal Cabinet out to January 2016.

TransMountain's supplemental work to assess the feasibility of the Burnaby Mountain alternative has been mired by roadblocks both figurative and literal. There have been court proceedings and applications before the National Energy Board to address the Municipality of Burnaby's attempts to forestall work expressly permitted under the federal regulator's enabling legislation. First the City refused to issue permits to conduct work in the Burnaby Mountain Conservation Area, then it began issuing various bylaw infractions to Kinder Morgan including an Order to Cease. In response, Kinder Morgan filed a motion with the National Energy Board seeking an order directing the City of Burnaby to permit access to the required lands, which motion resulted in an important decision from the federal regulator addressing constitutional issues that may well have to be addressed again given the increasing trend of municipalities and provinces to make demands and assert conditions precedent to federal pipeline project proponents.

The City of Burnaby too sought legal intervention, filing an application with the B.C. Supreme Court seeking an injunction preventing Kinder Morgan from undertaking any further work in the Burnaby Mountain Conservation Area in contravention of its municipal bylaws. This application was denied on September 17, 2014 and leave to appeal to the B.C. Court of Appeal has been sought. On October 23 2014, on jurisdictional and constitutional grounds, the National Energy Board granted Kinder Morgan's motion directing the City of Burnaby to permit access to Trans Mountain representatives to conduct the necessary studies and forbidding Burnaby from denying or obstructing access. With the law having landed on its side, Trans Mountain workers attempted to resume work on Burnaby Mountain only to be met with protesters and blockades necessitating another application to the B.C. Supreme Court for injunctive relief. Since issuing an injunction in favour of Trans Mountain, it is reported that over 60 protesters have been charged with civil disobedience pursuant to the injunction.

On December 1, 2014, Trans Mountain filed its supplemental information in respect of routing options between the Burnaby Storage Terminal and the Westeridge Marine Terminal. Trans Mountain determined horizontal directional drilling through Burnaby Mountain is not feasible. Its preferred alternative is tunelling through Burnaby Mountain, but it is also putting forward a revised corridor through Burnaby Streets as a viable alternative for the regulator's consideration. Trans Mountain had advised the regulator that it was revising its preferred route through Burnaby streets to tunneling through the mountain because of significant public outcry from Burnaby residents who did not want a pipeline in their streets. Of course, it turns out they were equally, if not more, opposed to tunneling through Burnaby Mountain and the conservation area in which it lies. In fact, their Mayor has said in no uncertain terms that no route through Burnaby will be acceptable to the City.

Assuming issuance of the Certificate of Public Convenience and Necessity, Kinder Morgan projects that the Trans Mountain Expansion could be in service in 2018. It will not be approved in 2015.

Northern Gateway

The Northern Gateway project consists of two pipelines that would run 1,178 kilometres from Bruderheim, Alberta to a marine terminal in Kitimat, B.C. One pipeline would take 525,000 bpd of Alberta oil west to the coast for export; the other, would bring 193,000 bpd of much-needed condensate back east to thin Alberta's land-locked bitumen. The Joint Review Panel issued its report to the Federal Cabinet on December 19, 2013, recommending approval of the project subject 209 conditions. By Order in Council dated June 17, 2014, the Federal Cabinet accepted the Joint Review Panel's recommendation and ordered that the National Energy Board issue Certificates of Public Convenience and Necessity subject to the 209 conditions.

With the required approvals in hand, is Enbridge on track for its 2018 start-up date? In a word – no. Northern Gateway's President has been reported as saying that any possibility of a 2018 start-up date is "quickly evaporating". He admits that the process of re-engagement with First Nations will take time and Northern Gateway is focused on gaining the support it needs to go ahead. The Joint Review Panel was openly critical of Enbridge's consultation with First Nations and a number of conditions relating to continued consultation with First Nations prior to construction and throughout the life of the Northern Gateway project are among the 209 conditions.

In answer to how Enbridge's re-engagement with First Nations is unfolding, one need only look as far as the registry at the Federal Court of Appeal. Approval of the Northern Gateway project is the subject of 18 proceedings before the Federal Court of Appeal filed by nine different Applicants. There are five judicial reviews in respect of the Joint Review Panel's Report; nine judicial reviews of the Cabinet's Order in Council directing the issuance of the Certificates of Public Convenience and Necessity; and four Appeals of the Certificates ultimately issued by the National Energy Board. Eleven of these proceedings were commenced by First Nations and Bands challenging, among other things, the adequacy of consultation and whether the Crown met its duty to consult with and accommodate First Nations interests. The other Applicants are largely environmental groups challenging the adequacy of the environmental assessment, including the findings that the significant impacts on woodland caribou and grizzly bears are justified in the circumstances, and the Joint Review Panel's refusal to take into account the upstream environmental effects of oil sands production.

In 2015, watch for decisions of the Federal Court of Appeal on the above judicial reviews and appeals, which will not come until the latter part of the year. If unsuccessful, expect to see applications for leave to appeal to the Supreme Court of Canada.

Line 9 Reversal

On March 2 2014, the National Energy Board approved Enbridge's application to reverse the segment of its existing 639 kilometre Line 9B between North Westover, Ontario and Montreal, Quebec, in addition to expanding the entire Line 9 capacity from Sarnia, Ontario to Montreal (from 240,000 barels per day to 300,000 barels per day), and permitted the transportation of heavy crude. Enbridge had already obtained approval to reverse the pipeline's flow for the Line 9A section running between Sarnia and North Westover, in southwestern Ontario. With Western Canadian oil now priced lower than foreign sourced oil being shipped Westbound from Montreal, the Line 9 reversal will allow Quebec refineries to remain viable.

While one might have reasonably expected an application to return a pipeline to the purpose it was originally built for 1976, and which has been operated without major incident for 35 years, to be relatively uncontroversial, that was not the case. The current state of public pipeline sentiment in Canada is such that proceedings before the National Energy Board escalated to a state where the regulator had to cancel the final portion of oral argument and resort to written submissions due to fear for the safety of attendees.

During the hearing, the regulator predominantly heard concerns respecting pipeline integrity and spill prevention and response given that Line 9 travels through the some of the most populated parts of Canada including Montreal and the suburbs of Toronto. Heightened concerns were not unexpected given that the hearing came on the heels of major incidents including the Lac-Megantic train derailment and Enbridge's own Line 6 spill into a tributary of the Kalamazoo River in Michigan. Notwithstanding that the project contemplated no new permanent land rights, the regulator also heard concerns respecting the adequacy of consultations with First Nations.

Before being granted leave to open, Enbridge is required to demonstrate that it has met all of the conditions set out by the regulator. On October 9, 2014, the National Energy Board determined that Enbridge failed to meet condition 16 because it had not installed shut-off valves around some major waterways. The regulator noted that Enbridge only has shut-off valves on both sides of six of 104 major water crossings and directed it to file a revised submission for condition 16, at least 90 days prior to applying for the final leave to open of the Project. This may not be an insignificant set-back for Enbridge and will push the in-service date of the reversed Line 9 into 2015.

Keystone XL

Finally, an oldie but goodie; Keystone XL, which has remained on life support for five long years amidst hyperbolic political posturing in both U.S. houses and on both sides of the aisle. Any reader can be forgiven for having forgotten the particulars of this long ago proposed pipeline project, the Canadian portion of which obtained National Energy Board approval in 2010, and which has languished awaiting a coveted Presidential Permit. To recap, Keystone XL is a proposed 1897 kilometre crude oil pipeline beginning in Hardisty, Alberta and extending south to Steele City, Nebraska, with a capacity to transport up to 830,000 barrels of WCSB and Bakken oil per day to Gulf Coast and Midwest refineries.

In May of 2012, TransCanada filed a new application for a Presidential Permit with the U.S. Department of State. After controversy in respect of routing through Nebraska's environmentally sensitive Sands Hills region, the Governor of Nebraska approved a revised route in January of 2013. In March of 2013 a Draft Supplementary Environmental Impact Statement reaffirming no significant environmental impacts. On April 18, 2014 Obama's adminstration announced that its review of the project would be extended indefinitely, pending the result of a legal challenge to a Nebraska pipeline siting law that could result in route amendments. Argument was heard by the Nebraska Supreme Court on September 5, 2014 on issues including whether the landowners had standing to bring the action and whether the Legislature violated the Nebraska Constitution when it passed the law that allowed the Governor to approve the pipeline, the routing of which would typically be approved by the Nebraska Public Services Commission.

November 2014 saw a bill approving Keystone XL pass in the House of Representatives for the ninth time. The bill went on to be defeated in the Senate by one vote. While Republicans regained the majority of the Senate in recent midterm elections, the newly elected Senators had not been sworn-in yet. The bill will surely be reintroduced in the very near future, the Senate Republican Leader having declared it to be a priority item on the Senate agenda for 2015.  Even if the bill had passed, President Obama was expected to veto it and may yet veto it should the opportunity present itself.

In 2015, watch for the imminent decision of the Nebraska Supreme Court concerning the constitutionality of the pipeline siting law as Obama's administration has repeatedly indicated that it will not act prior to a ruling on routing through that state. It will also be interesting to watch whether the Republican held Senate will be able to muster up the 67 votes necessary to override the presidential veto.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions