Canada: The FIT 2.0 Rules And Contract Released By The Ontario Power Authority

Last Updated: September 18 2012
Article by Anna C. Naud

Most Read Contributor in Canada, September 2016

On August 10, 2012, the Ontario Power Authority ("OPA") issued the new Feed-in-Tariff Program rules ("FIT 2.0 Rules") and contract ("FIT 2.0 Contract").1 Version 2.0 of the FIT Program was implemented pursuant to Directions issued by the Minister of Energy dated April 5, 2012 and July 11, 2012 supplementing the Direction previously issued by the Minister of Energy and Infrastructure dated September 24, 2009. The final FIT 2.0 Rules and Contract replace the draft FIT 2.0 Rules and Contract released in April 2012 for comment (the "Draft 2.0 Rules and Contract").

The Ontario government is affirming, through the FIT 2.0 Rules and Contract, that it wishes the FIT Program to continue. But the changes to FIT 2.0 Rules and Contract may pose significant challenges to project developers and financing parties.

The following is a non-exhaustive list of key differences between the Draft 2.0 Rules and Contract and the FIT 2.0 Rules and Contract (some of which are explored in further detail in this article). The FIT 2.0 Rules and Contract:

1. remove the controversial termination for convenience and stop work order provisions which developers and the financial community found very problematic;

2. add additional points available to Applicants for Applications submitted before certain dates;

3. add Time Stamps as a factor considered when an Application is being reviewed;

4. clarify the "Property Owner" definition used in relation to Co-op Members;

5. provide for the assignability of Resubmitted Applications in very limited circumstances;

6. introduce the concept of a Contract Capacity Set-Aside Project which will receive a higher ranking than all other Applications;

7. change the points available in the Aboriginal Support Category to be applicable only to a small FIT project; and

8. provide an option for an Applicant that has entered into two or more FIT Contracts that qualify as a Rooftop Portfolio to extend the Milestone Date for Commercial Operation to 36 months following each Contract Date.

The FIT 2.0 Rules and Contract contain numerous amendments that developers and potential investors and participants should consider carefully. As a whole, a developer can expect greater challenges to obtain a FIT 2.0 Contract under the new Rules. The new Rules set out procurement targets, application periods, and priority ranking based on the significant involvement of groups not historically in the business of generating electricity – community, Aboriginal, and public sector groups.

The OPA will maintain an application package, including the Application for the FIT 2.0 Contract, and detailed instructions on how to apply for a FIT 2.0 Contract, on its website.

With the release of the FIT 2.0 Rules and Contract, all those active (or who want to be active) in the renewable energy space in Ontario are reviewing and strategizing the new Rules to best determine how to conform to the new Rules and how to use the Rules to their benefit.

The following is a summary of the major changes under the FIT 2.0 Rules and Contract. We would be happy to discuss the FIT 2.0 Rules and Contract in more detail with you at your convenience.

I. Major Differences between the Draft 2.0 and FIT 2.0 Rules and Contract

Controlled Scope – Procurement Targets; Application Periods

Unlike the initial open-endedness of the FIT Program, the issuance of Contracts will now be subject to periodic procurement targets set by the OPA in its discretion.

In addition, FIT applications will now be accepted only during specific application periods, rather than on an ongoing basis. The OPA will also determine the type of FIT Project that may be the subject of a particular application submitted during an application period.

As directed by the Ministry of Energy, the OPA will award 200 MW of small FIT (under 500 kW) Contracts first. The application window for this first round of small FIT 2.0 projects is anticipated to run from October 1 – November 30, 2012.

Applicants will be competing with each other and will be ranked based on points, time stamps, and availability of grid capacity. Applications will be prioritized with points awarded based on project type (community participation, Aboriginal participation, or public university, publicly-funded school, public college, hospital or publicly-owned long-term care home participation or where they are a host), municipal support, Aboriginal support, project readiness, and electricity system benefit.

Applications will first be judged on whether or not they meet the completeness requirements set out in Section 3 of the FIT 2.0 Rules. Then each Application will either pass or fail depending on whether the Application meets the eligibility requirements set out in Section 2 of the FIT 2.0 Rules. In Stage 3, each Application will be evaluated to determine whether it qualifies as a Contract Capacity Set-Aside Project and will be awarded a point score based on the prioritization process contained in Section 6 of the FIT 2.0 Rules. Applications will then be ranked by their qualifications as a Contract Capacity Set-Aside Project, as applicable, Priority Points, and by Time Stamp (or a Resubmitted Application's Pre-Existing Application Time Stamp). Finally, Applications will, in order of rank, be assessed under the Transmission Availability Test and the Distribution Availability Test (as applicable) and, if it passes and availability remains within the applicable Procurement Target, an Application will receive an Offer Notice.

New restrictions around change of control and assignment have been added to ensure that the economic interest and membership levels specified under the project type category (e.g. Aboriginal or community economic interest) do not fall below the level that resulted in the project receiving priority points during the application review process. Additional points are also now available based on the time stamp of a pre-existing application: One point is available for projects that applied on or before July 4, 2011, and one half point is available for projects that applied on or after July 5, 2011.

Project Eligibility

A number of changes have been made to eligibility requirements, some of which affect specific types of renewable fuels.

Solar Projects

  • Ground-Mounted Solar Projects may not be located on residential property or on property abutting residential property. However, for property where the lawfully permitted use is agricultural, these types of projects are permitted on the property or on an abutting property if residential use is permitted on both properties as ancillary to the agricultural use.
  • Such projects are permitted on commercial or industrial property as long as the project is not the main, primary, or only use of the property.
  • Such projects cannot, with few exceptions, be located on:
  • Specialty Crop Areas,
  • CLI Organized Lands, or
  • CLI Class 1, 2, or 3 Lands (in whole or part). If the project is located on CLI Class 1, 2 or 3 Lands, exceptions exist if the project is on an airport or aerodrome, a closed landfill, a federal military installation, a Contaminated Property, a Property which is being legally used for industrial uses and the Project would not be a Principal Use of the Property, or a Property that is owned by a Municipality (re. CLI Class 3 Lands);
  • a Residential Property that is not an Exempt Residential Property;
  • a Property that abuts a Residential Property unless such Resident Property is an Exempt Residential Property; or
  • a Property in respect of which one or more Non-Rooftop Solar Project would constitute the Principal Use.
  • Solar (PV) Projects continue to be limited to a maximum of 10 MW.
  • A Rooftop Solar Facility must reach commercial operation within 18 months of receiving a Contract, but if the Facility forms part of a Rooftop Portfolio with more than 15 MW of projects contracted from the same application window, the Applicant can have 36 months to reach commercial operation.

Waterpower Projects

  • These projects continue to be limited to a maximum of 50 MW.

There are also specific provisions for co-locating projects and limitations on developers submitting similar projects during the same application period.

In addition, a proposed project (other than a waterpower project) will need to be located within fifty kilometres of the facility's contemplated connection point.

Application Requirements

All project applicants, including those with small FIT projects, will need to submit application security under the new Rules. The size of the application security is representative of the size and development complexity of a potential project – either $20 per kW of capacity for solar PV, $10 per kW for other projects, or $1,000, whichever is greater. Lower security rates apply to projects with greater than 50% community or Aboriginal participation.

In addition, an applicant must provide representations and warranties which attest to an awareness of certain project requirements, such as environmental permitting and particular FIT Program Rules, and which confirm that certain preparatory actions have been completed in respect of the project, such as obtaining all access rights and supporting documentation (e.g. independent engineer report, a written opinion of a Land Use Planner, maps, requisite consents and statutory declarations, Environmental Site Assessments, land titles or land registry search, soil study, etc.). The effect is to place a greater degree of responsibility as well as additional costs on the applicant to ensure the viability of its proposed project.


FIT prices will be reviewed annually, with prices published in November that will take effect on January 1st of the following year.

In a significant departure from the previous FIT Program, an applicant offered a FIT 2.0 Contract will be offered the pricing (and Price Adder, as applicable) in effect when the Contract offer is made, not the price in effect when the application was filed. If the Contract Price or Price Adder (as applicable) set out in the Offer Notice is less than the Price and Adder in effect as of the date of the Application, the Applicant may by notice to the OPA elect not to enter into a FIT Contract; in such circumstance, the OPA will return the Application Security.

Following the assessment of Applications, the OPA will post on its website (1) the Offer List – listing Applications in respect of which Offer Notices are to be issued; and (2) the Amended Site List – listing Applications that are given the opportunity to make certain amendments (e.g. to revise the dimensions of the applicable Site to conform with the available provincial Crown lands, reduce the Contract Capacity, etc. and resubmit the Application) or to terminate the Application.

Domestic Content

The FIT 2.0 Contract maintains domestic content requirements, set at 50% for wind and 60% for solar (pv) facilities.

Priority Points System

Under the FIT 2.0 Rules, a new priority points system will be used to rank applications with the time stamp now acting as tie breaker. An application may only proceed if the proposed project can receive at least one point. The new system clearly assigns priority to projects that have a community, Aboriginal or municipal, education or health ("MUSH" sector) component, whether as a direct participant in the project or as supporting entity.

The FIT 2.0 Rules do not permit a project to obtain more than one type of participation project points but do permit certain combinations of project and non-project points under certain situations.

FIT Contract – Certain Key Differences

  • Supplier Termination of FIT 2.0 Contract

If the Supplier terminates the Contract in accordance with Section 2.4(a) of the Contract, then the OPA's sole and exclusive remedy shall be the payment of liquidated damages by the Supplier to the OPA unless the Supplier can provide evidence to the OPA that a limited exception under Section 2.4(c)(ii) has been met.

  • NTP Requests

For a Large FIT Facility, the Supplier must provide the OPA with a completed NTP Request no later than 6 months prior to the Milestone Date for Commercial Operation. If the Supplier does not do so, the Supplier shall provide the OPA with such information as the OPA may require in its sole and absolute discretion (which may include information regarding the Project's status and a project plan).

For a Small FIT Facility, the Supplier must provide the OPA with a completed NTP Request no later than three months prior to the Milestone Date for Commercial Operation.

  • Milestone Date for Commercial Operation

Liquidated damages will no longer be payable by a Supplier for failing to attain Commercial Operation by the Milestone Date for Commercial Operation. However, the OPA will now have the option to terminate the Contract for such failure under Section 9.2 of the Contract.

II. If a FIT application with a project 500 kW or smaller has already been submitted...

Pre-existing small FIT applicants who wish to participate in the FIT Program will need to submit a revised application between October 1, 2012 and November 30, 2012 in order to maintain their original time stamp. New and resubmitted applications will be reviewed according to the FIT 2.0 Rules. Applications can be modified to conform but the legal applicant name and location must stay the same to retain the original time stamp. The project must also be located on the same site. However, applicants will be allowed to change the legal applicant name on the application if they are adding participation of 15% or more from an Aboriginal or local community, school, college, university, hospital, or long-term care home.

New evidence and security must be submitted, along with a new application fee; the application fee and security submitted with the Pre-Existing Application will be returned.

Existing applicants who do not wish to proceed under the FIT 2.0 Rules may withdraw their application and they will have their application fees and application security returned. Any existing application that is not resubmitted within the required window will be terminated and the fees and security returned.

III. If you are an existing contract holder...

Current FIT projects will continue to be managed under the existing terms of the relevant FIT Contracts. If the project is a ground-mounted solar PV project, and a site amendment is required, the new agricultural, residential, and commercial/industrial land-use restrictions will apply to the proposed new site.

An existing FIT Contract may be terminated by the FIT Contract holder (but not by the OPA), without penalty, for any reason, until September 30, 2012. If terminated before this deadline, the security will be returned within 20 business days of the OPA receiving an executed Termination Agreement that is sent to the current FIT Contract holder following the holder's submission of a completed Supplier Notice of Termination.


1 Any capitalized term in this bulletin, not otherwise defined, has the meaning given to it in the FIT 2.0 Rules or FIT 2.0 Contract.

About BLG

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

In association with
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.