On October 18, 2010, the OPA released an updated timeline for the FIT
Program indicating that Transmission Availability Tests and
Distribution Availability Tests would commence on October 18, 2010
for non-capacity exempt project applications submitted between
December 1, 2009 and June 4, 2010. The results of such tests
are intended to be released in late November 2010. The
existing timeline which was released on June 1, 2010 contemplated
that the results of the tests would be released in early July
2010.
Non-capacity allocation exempt applications submitted after June 4,
2010 will be reviewed following the completion of the upcoming
Economic Connection Test. The OPA intends to post an update
on the timing of the Economic Connection Test.
Applications for capacity allocation exempt projects are reviewed
and offered contracts on an ongoing basis. Contract offers
for applications submitted after June 4, 2010 are expected to begin
in late October 2010.