This paper is written on the assumption that the Superintendent will be working under AS4000-1997.

The Duties of the Superintendent

Clause 20 of AS4000 looks at the Superintendent fulfilling all aspects of the role and functions reasonably and in good faith, but it is not explicit in laying down exactly how that is to be achieved.

Clause 20 of AS4000 requires the Superintendent, in the exercise of his or her functions under the contract to:

  • act honestly and fairly;
  • act within the time prescribed under the contract or, where no time is prescribed, within a reasonable time; and
  • arrive at a reasonable measure or value of work, quantities or time.

Giving Directions

AS4000 allows the Superintendent to give directions orally, except where the contract otherwise provides, but the Superintendent shall confirm this as soon as practicable. This is always good practice in any case, since it puts the direction on record and prevents any dispute about what the direction actually was.

AS4000 goes on to say that if the contractor, in writing, requests the Superintendent to confirm an oral direction, the contractor shall not be bound to comply with the direction until the Superintendent confirms the direction in writing. It is amazing how often contractors fail to take this obvious precaution, probably because they only read the contract as a last resort, after disputes have already arisen.

It is important to note that directions should be issued to the contractor, not to subcontractors or workers. The chain of contractual authority should be observed at all times since, otherwise, confusion may well reign.

The Superintendent does not Supervise

There is an important distinction between exercising the functions of a Superintendent under the contract, on the one hand, and the supervision of the works on the other. It is the job of the contractor and the contractor's representatives on site to supervise the work, plan the progress of the work and ensure the quality control.

There is a common misunderstanding amongst members of the public that the Superintendent must necessarily be to blame if there is any shoddy workmanship or faulty materials. In fact, the role of the Superintendent does not require continuous attendance on site, but only occasional site visits, usually at the time of site meetings. Administering the contract and supervising the works are completely different functions.

Even if a defect were visible at the time of inspections by the Superintendent and could or even should have been picked up by the Superintendent, the Superintendent's failure to do so will not prevent the Principal from holding the contract or irresponsible to repair the defects. Of course, if the contractor seeks a variation in terms of the standard of materials or workmanship and receives an express instruction from the Superintendent approving that variation, this changes the scope of work under the contract and the contractor is entitled to proceed on that basis. The Principal cannot thereafter say that the Superintendent should not have authorised the change.

Superintendents should be wary of giving any instruction to a contractor which requires the contractor to go about his work in a particular manner, rather than what result the contractor should achieve. Superintendents should not give instructions which "method specifications" are not found in the contract documents themselves, since they thereby take responsibility for the effectiveness of the method.

In an arbitration which the writer was involved as Counsel, the Superintendent, instead of giving an instruction to remedy a defect, gave a specific instruction as to exactly how the contractor was to go about fixing the problem, over the protests of the contractor who wanted to adopt a completely different approach. The method favoured by the Superintendent failed and the Superintendent eventually relented, allowing the contractor to use its own method, which proved successful. The Arbitrator awarded the costs of the abortive attempts to fix up the problem using the method preferred by the Superintendent, as being an unreasonable attempt on the part of the Superintendent to usurp the role of the contractor in managing the work.

Even where the contractor is not putting forward its own proposal and asks the Superintendent how to go about the job, it is risky for the Superintendent to officially put forward a solution of the Superintendent's own devising. There is every prospect in that situation that if attempts fail, for whatever reason, the Superintendent's preferred option will get the blame. A contractor should be competent enough to carry out the work and if necessary, the contractor should obtain expert advice elsewhere for which the contractor would be solely responsible.

Agent for Certifier

The Superintendent has a dual role in administering the contract. In some cases, he acts merely as the agent of the Principal, the local government in the case of Superintendents employed by a local government. In so doing, he is only obliged to have regard to the interests of the local government.

For example, the Superintendent has a power to issue variations as, for instance, to omit wall paper to a particular wall and substitute plaster and paint instead. This instruction depends, solely, upon the preference of the Principal and does not require the exercise of any independent discretion.

By contrast, valuing a variation under sub-clause 36.4 does require an exercise of independent judgment on the part of the Superintendent as contemplated by clause 20. This may result in the Superintendent, acting reasonably and fairly, having to make a judgment that the price of the variation is going to be higher than the Principal would really like to pay.

You will sometimes hear people say that they regard the Superintendent as favouring the contractor, where decisions are made adverse to the interests of the Principal. Since their viewpoint is naturally biased towards the interests of their employer, with which they identify, this usually means that the Superintendent is acting honestly and fairly as required by the Contract.

Perini Corporation v Commonwealth (1969) 2 NSWR 530

This case illustrates the divided nature of the duties of an employed Superintendent. In that case, the Superintendent was the Commonwealth Director of Works. Dealing with applications for extension of time, the Director of Works considered he could not grant an extension of time which would be contrary to departmental policy, although that policy was not a term of the contract.

The New South Wales Supreme Court held that although the Director was entitled to consider departmental policy, he was obliged to exercise his discretion according to the rights and obligations of each party to the contract, as set out in the contract, and could not regard his discretion as being controlled by the policy of the Department.

The court distinguished between the powers of the Superintendent which were administrative and supervisory in their character and performed by the Director of Works as the servant and agent of the Commonwealth and his obligations as a Certifier, which required him to consider the contractual rights and duties of the contractor. His discretion as Certifier could not be fettered by the Department which employed him.

Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322

In this case, the leading judgment was given by Hodgson JA. That case involved AS2124-1992 and referred to the power of the Superintendent to grant extensions of time, variations and liquidated damages. Hodgson JA, with whom the other members of the Court agreed, concluded that when exercising certifying functions in respect of which the Superintendent must act honestly and impartially, the Superintendent was not acting as the owner's agent in a strict legal sense.

Where a Superintendent is acting as an agent in the strict legal sense of the word, a local government cannot challenge the Superintendent's action. For example, if the Superintendent issued a variation directing a building to be painted purple rather than white, the local government would not be able to say afterwards that the Council had not been consulted or even that purple was a bad colour to have chosen. Likewise, the contractor cannot assert that purple would not be a good colour to paint the building and they would be better off painting the building blue.

By contrast, a decision by the Superintendent in his capacity as Certifier, eg by the issue of a Payment Certificate, could be challenged by either party.

Safety

While the contractor has the primary responsibility for safety on the site, the Superintendent should not lose sight of the fact that there is a responsibility on his or her part and also, as the representative of the Principal. If blatant breaches of safety are perceived, a Superintendent should not close his or her eyes to that situation but should issue an appropriate instruction.

Similarly, where the work requires a job safety analysis or risk management plan, the role of the Superintendent is first of all to make sure that the contractor has such documentation and then occasionally to check to make sure this has not obviously been breached.

There will be more to say about safety when dealing with the role of the Project Manager, who has a more significant role in regard to safety.

Workmanship and Material

While the Superintendent would normally intervene with a direction to make good if the Superintendent perceives that the workmanship is faulty or materials are defective, the contractor is not excused by reason of any failure on the part of the Superintendent not to pick this up on inspections, even though a reasonably careful Superintendent should be able to do so. If the contractor provides inadequate workmanship or defective materials, the contractor remains responsible to the Principal and cannot complain that the Superintendent should have stopped the contractor or its subcontractors from doing so.

Latent Conditions

Another area where Superintendents can be in some degree of difficulty relates to latent conditions. This refers to conditions on site which could not have been anticipated by a reasonably prudent contractor who made all necessary inspections and enquiries and are not apparent from the documents provided.

These latent conditions are often problems with the subsoil strata but may consist of natural objects such as buried services and the like.

The contractor must bring the problem to the attention of the Superintendent at an early stage. Failure to do so can result in the contractor being unable to recover part or even all of the expenses involved.

Documentation

Contractors are notoriously weak on documentation. Many of them seem to have a policy of reading the contract only after a dispute arises. However, Superintendents should never fall into such slack ways.

The most commonly encountered difficulty with documentation is inconsistency between suites of supporting documents forming part of the contract. Often the drawings and specifications are found to be in conflict, particularly where there are a number of consultants issuing detailed specifications for particular parts of the work and batches of drawings relating to that work.

It is remarkable how often contractors will try to resolve those difficulties by puzzling over orders of precedence in the contract documents, instead of simply picking up the telephone or a technical query to the Superintendent.

It is not unknown for sub-contractors to simply ignore the specifications in particular areas of work because of the way they call for the work to be done is not how they usually proceed. Provision by the contractor will fail to pick this up and indeed the contractor may even connive at that course, but the Superintendent will bear that possibility in mind.

Traps for the Unwary Superintendent

Sometimes Superintendents can place too much faith in contractors. The Superintendent who issues an instruction to remedy faulty work and simply assumes that the contractor will have complied with it and may be living in a fool's paradise, which will be rudely interrupted when the work in question later fails.

Another trap into which a Superintendent can fall is to attend a meeting at which critical issues are discussed, but not to record this at the time either by Minutes taken of the meeting or by correspondence from the Superintendent to the Contractor setting out the Superintendent's understanding of the discussion. If it comes to a dispute, a contemporary written record will always be preferred to unaided recollection.

It is surprising how often project records fail to address critical issues. The writer well recalls a site diary dealing with a day in late December at which vital events occurred, but in which the only event recorded was the arrival of a substantial quantity of beer!

Site Meeting Minutes are also often defective, in that they may fail to go into discussions on key issues while recording in detail relatively mundane items. This may be because neither the party taking the Minutes nor the other party to the discussions wants to put in writing a public record of matters causing significant concern both to the Superintendent and to the Contractor.

Superintendents should diarise key date driven requirements. For example, under sub-clause 34.5 of AS4000-1997, the Superintendent must give a decision in writing within 28 days. If he fails to do so, there is a deemed assessment and direction for an extension of time as claimed.

Similarly, under sub-clause 37.2 of AS4000-1997, if the Superintendent does not issue a Progress Certificate within 14 days of receiving a progress claim, the progress claim itself is deemed to be the relevant Progress Certificate. Nothing reflects more poorly on a Superintendent than failing to give decisions in a timely fashion.

There are times when Superintendents complain that they have to take a lot of time considering and weighing up the various issues in order to arrive at an extremely careful and perfectly calculated assessment. It is better in such a situation to give a decision as best you can within the relevant timeframe and then review that decision at leisure, with a view to correcting it at a later date and bearing in mind that Payment Certificates are always provisional.

Further Information

Under AS2124 Contracts, it has been held that the Superintendent can extend time within which to issue a progress certificate by requesting further information in support of the claim. The Court in Brewarrina SC v. Beckhaus Civil Pty Ltd (2003) NSWCA 4 held that the period of time from the Superintendent's receipt of the claim to the issue of the certificate was suspended if the Superintendent asked for further information, until that further information is supplied. The Trial Judge and one of the Judges of the Court of Appeal considered that the time continued to run and that the payment claim was therefore deemed to be a certificate, the two other Judges of the Court of Appeal held otherwise and considered that the failure to supply the information reasonably required by implication prevented the time running so far as the Superintendent was concerned.

It is doubtful whether a similar outcome would occur under AS4000-1997 and indeed academic opinion is that the majority decision in Breworrina was incorrect. The better course in the writer's opinion and that of the learned authors of Dorter & Sharkey on "Building and Construction Contracts in Australia" is that the Superintendent should make the best estimate he can, on the basis of such information as was supplied and, if that is not possible, to issue a nil certificate, bearing in mind that a further certificate can be issued at a later stage when better information comes in.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Kott Gunning is a proud member of

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Related Topics
 
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions