The new Common Provisions Act affects land access, environmental approvals, overlapping tenements and the lease application process for Queensland mining projects.

The Mineral and Energy Resources (Common Provisions) Act 2014 (Qld) (CP Act) was passed on 9 September 2014 and is to commence on a date to be fixed by proclamation.

In this article, we値l summarise some of the key matters that industry will need to start doing now to get ready for the commencement of the CP Act, and what needs to be done once the Act has commenced.

Private land access

On-tenure private land access (all tenements other than mining leases, mining claims and prospecting permits)

The regime for entry on to private land under the CP Act is broadly consistent with the previous regime in the resource Acts.

However, the following are key additions to the regime in the CP Act that should be noted by industry:

  • there is a further obligation for a tenement holder to give periodic notices after the initial notice of entry has been given;
  • each owner and occupier of the land may, by agreement, opt out of a CCA or deferral agreement; and
  • a tenement holder who enters into a CCA or opt-out agreement will be required to give written notice of this to the registrar of titles to be reflected on title within 28 days of entering into the agreement. The registrar of titles will then be obliged to amend the title register so that a search will show the existence of the agreement (although we understand a copy of the agreement itself will not be searchable). The tenement holder will also have to notify the registrar of titles if the agreement ends, or if the land is subdivided such that the agreement no longer applies to a new lot.

The provision requiring registration of agreements will act retrospectively, meaning that any agreements existing when the CP Act commences will need to be notified to the registrar of titles within six months of the commencement. Accordingly it would be prudent to ensure that your company has easy access to all CCAs that it has entered into so you can do this within the required timeframes.

Off-tenure private land access (all tenements other than mining leases, mineral development licences, mining claims and prospecting permits)

The current off-tenure land access framework under the Petroleum Act 1923 and Petroleum and Gas (Production and Safety Act) 2004 (PAG Act) will now also apply to mineral and coal exploration permits (not mineral development licences).

Access agreements will be needed in order for a tenement holder to cross access land (or to carry out activities reasonably necessary to allow the crossing of the land). The access agreement will be needed with:

  • each occupier of the land, if the impact of the exercise of the access rights is unlikely to be permanent; and
  • each owner and occupier of the land, if the impact of the exercise of the access rights is likely to be permanent.

Restricted land

Proposed changes to the restricted land regime will only be relevant to resource authorities applied for and granted after the CP Act commences. For those resource authorities, this means a change in what constitutes restricted land (both in radius and characteristics).

Generally, the consent of the relevant restricted land owner or occupier will be required to carry out activities in the area of restricted land. However, for a mining lease, consent of the relevant owner or occupier is not necessarily required.

For a mining lease, if the Minister considers that the activities carried out on the restricted land cannot co-exist with the authorised activities under the lease, the lease holder needs to have entered into a compensation agreement under the amended section 279 of the Mineral Resources Act 1989 (Qld) (MRA) with the relevant owner or occupier relating to the restricted land.

One aspect that is not clear from the wording of the CP Act is whether, if the Land Court determines compensation including in relation to restricted land, consent is still required before activities can be done on that land. We understood that the Government's intention was that consent not be required in these circumstances but the drafting of the CP Act does not clearly reflect this. This should, in our view, be corrected to ensure that the CP Act works as intended.

For any resource authorities applied for before the CP Act commences, the previous restricted land provisions in the resources Acts will apply.

However, for mining leases granted before the commencement of the CP Act that were not granted over areas of restricted land because the consent of the landowner was not obtained, the lease holder may apply under section 275 of the MRA (additional surface area application) to add those areas of restricted land to the mining lease. If that application is granted, the new restricted land provisions apply to the relevant owner or occupier for the restricted land.

There is what appears to be an unintended omission for mining leases applied for before the commencement of the CP Act, and granted after the commencement, over areas excluding restricted land. For these leases, there is no transitional provision allowing the lease holder to apply under section 275 of the MRA to add the restricted land in to the lease (under the new provisions). This means that the lease holder would need to make an entirely new mining lease application over the areas of restricted land under the new provisions.

Mining lease and environmental authority objections

Coordinated projects (under either EIS process or new impact assessment report (IAR) process)

The CP Act also makes amendments to the EP Act to confirm that:

  • a submitter cannot request that any part of a submission to an EIS that relates to a Coordinator-General's condition be taken to be an objection to the environmental authority application; and
  • the grounds for an objection to an environmental authority cannot relate to a Coordinator-General's condition.

The CP Act amends the State Development and Public Works Organisation Act 1971 (Qld) to provide that a submitter under the Environmental Protection Act 1994 (Qld) (EP Act) to an environmental authority (EA) application may not request that its submission be taken to be an objection to the environmental authority application, if the Coordinator-General's report for the project states:

  • conditions for the proposed EA; and
  • the Coordinator-General is satisfied the conditions adequately address the environmental effects of the mining activity.

This will mean that there cannot be any objection or Land Court hearing in relation to the EA application. This advantage will be able to be used by some coordinated projects that are going through an existing approvals pathway, so the project managers for every such project should be closely checking the transitional provisions for the applicability of the new regime to their project.

Because of these changes, the Coordinator-General's process (whether EIS or IAR process) is likely to become a very attractive option as compared to the EP Act process.

Projects requiring site-specific EA application (not coordinated projects)

For mining lease applications that are not coordinated projects, but still require a site-specific EA application, the public notification of the EA application will only occur under the EP Act (if at all).

Anyone who makes a properly made submission on the Environmental Impact Statement (EIS) or EA application (if public notification occurs) will retain the right to request that their submission be taken as an objection to the EA.

Objections to a mining lease application

There will no longer be a concept of a Certificate of Application (COA) or a Certificate of Public Notice for a mining lease application. In addition, the application will no longer need to be publicly notified.

Instead, the Chief Executive will issue a mining lease notice for a mining lease application, which must be given to certain persons, including the owners of land underlying the application.

Only an "affected person" can object to the grant of a mining lease application. In this context, an affected person means:

  • owner of land the subject of the proposed mining lease ;
  • owner of land necessary for access to the land the subject of the mining lease ;
  • an owner of adjoining land; and
  • the relevant local government.

Further, each affected person may only object on certain limited grounds specific to the land that is impacted.

The transitional provisions for the new mining lease application objections regime are:

  • for an application with a COA issued before the commencement of the CP Act, the MRA, as in force immediately before the commencement of the CP Act, continues to apply to the COA;
  • for an application with a Certificate of Public Notice issued before the commencement of the CP Act, the MRA, as in force immediately before the commencement of the CP Act, continues to apply to it; and
  • for applications where objections were lodged before the commencement of the CP Act, the MRA, as in force immediately before the commencement of the CP Act, continues to apply to the objections.

In all other circumstances, the new provisions in the CP Act will apply.

Overlapping coal and CSG tenement regime

There is also a new overlapping coal and CSG tenures regime in the CP Act. There are some key provisions in the Act that require industry to take certain steps almost immediately after the commencement of the CP Act.

Existing mining lease applications

Where, at the commencement of the CP Act, a mining lease application has been made over an ATP, but not decided, the new regime will apply.

This will require the applicant to issue an "advance notice" to the ATP holder within 10 business days of the commencement, and seek to negotiate a joint development plan with the ATP holder. The advance notice is required to contain a large amount of information, including a proposed joint development plan.

If the parties are unable to agree on a relevant matter for a joint development plan, within six months after the provision of the advance notice, the applicant must apply for arbitration of the dispute.

This means that existing applicants to whom the new regime applies will need to prepare an advance notice and proposed joint development plan in readiness for issuing those to the ATP holder at the commencement of the CP Act.

Existing petroleum lease applications

Where, at the commencement of the CP Act, a petroleum lease application has been made over an EPC/MDL, but not decided, the new regime will apply.

This will require the applicant to issue a petroleum production notice to the EPC/MDL holder notice within 10 business days of the commencement.

Concurrent applications

Where, at the commencement of the CP Act, there are concurrent petroleum lease and mining lease applications, the petroleum lease applicant appears to be able to issue a concurrent notice to the mining lease applicant.

If the petroleum lease applicant does this, the intention of the relevant provisions seems to be that the petroleum lease applicant is then treated as a petroleum lease holder (instead of an ATP holder) for the purposes of applying the new regime (although the drafting of these provisions in the CP Act does not expressly state that this provision applies to a petroleum lease applied for before the commencement of the CP Act).

This would mean that the mining commencement date for the mining lease application must be 11 years after the date on which the advance notice was given (instead of 18 months), otherwise compensation is payable by the mining lease holder for accelerating those timeframes.

You might also be interested in...

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.