New home building spurs construction expansion
The long-hoped-for recovery in Australia's residential construction sector may finally be underway, with low interest rates driving the fastest expansion in new home building since 2005 (08 January 2014). More...

QLD Schools PPP to deliver better value
Plenary Schools will deliver 10 new schools in South-East Queensland under a Public Private Partnership (PPP) (17 December 2013). More...

Brisbane Airport to redevelop international terminal
Local architects Richards and Spence, and Arkhefield have been chosen for the project. Work has commenced on the next important phase of the $1.3 billion new parallel runway and more than 50 projects are underway in the broader airport precinct (09 January 2014). More...

Gold Coast International Marine Precinct approved
Harbour Island's proposed $390 million Gold Coast International Marine Precinct has been approved by the Queensland Coordinator General subject to meeting environmental and operational conditions (09 January 2014). More...

Updated Australian standards released
Standards Australia has released a new version of AS 165 – 2013 Fixed platforms, walkways, stairways and ladders – design, construction and installation. The new standard will reduce ambiguity and offer guidelines for manufacturers, providing greater safety for those accessing these structures (09 January 2014). More...

Pacific Highway: Oxley Highway to Kundabung a Step Closer
Lend Lease has won the contract as the preferred tenderer to design and build the Oxley Highway to Kundabung upgrade of the Pacific Highway (08 January 2014). More...

Work starts on new section of Pacific Highway upgrade
Major work has started on the $780 million 22 kilometre upgrade of the Pacific Highway from Nambucca Heads to Urunga. Works including utility relocations and the establishment of a site compound commenced late last year, with Lend Lease securing the contract to design and construct the upgrade (15 January 2014). More...

More time for BASIX submissions
They must have hit a nerve with the BASIX (Building Sustainability Index) Target Review with the New South Wales Government announcing an extension until 14 February for submissions on the proposed changes, due to the high level of interest from stakeholders (15 January 2014). More...

New homes and infrastructure for south-west Sydney
The housing boom in NSW is continuing with a further 3,200 new homes to be delivered in Sydney's south-west as part of the NSW Government's commitment to boost housing supply with the announcement of the rezoning of the Catherine Field site (28 December 2014). More...

Maules Creek Approval Upheld
Whitehaven Coal Limited has welcomed the judgment in the Federal Court of Australia that the Federal Minister for the Environment did not err in law in granting approval for Whitehaven's Maules Creek project in early 2013. Justice Cowdroy dismissed NICE's legal challenge to the validity of the Federal Minister's approval for the project granted under the EPBC Act and not a merits based appeal against the project (December 2013). More...

NSW roads maintenance funding at historic highs
Minister for Roads and Ports Duncan Gay today announced record levels of funding for roads and bridges maintenance in NSW, including council owned infrastructure. The record roads and bridges maintenance allocation in 2013-14 includes nearly $432 million in Block Grants, REPAIR funding and forecasted natural disaster payments to councils (13 January 2014). More...

Infrastructure fund gets an added boost
The NSW Government's dedicated infrastructure fund, Restart NSW, has received a boost of nearly a quarter of a billion dollars, Treasurer Mike Baird announced. Almost a third of the proceeds of Restart are reserved for projects in regional NSW (2 January 2014). More...

Super Tribunal to start on 1 January 2014
Acting Minister for Justice announces that the NSW Civil and Administrative Tribunal (NCAT) will start on 1 January 2014. The government has integrated 22 of the State's tribunals and bodies into a new overarching tribunal that will provide a simple, quick and effective process for resolving disputes, supervising occupations and reviewing executive action (1 January 2014). More...

Victoria Scraps Commercial Building Defect Insurance
Commercial builders in Victoria will no longer need defects insurance under new rules which will also see the scrapping a requirement for metal roofs to be constructed by plumbers and will increase height thresholds above which walls can be constructed near property boundaries without permits (16 January 2014). More...

Victorian Government announces reforms for Building and Construction
The Victorian Coalition Government has announced 36 red tape cutting reforms to boost productivity and reduce costs for Victorian businesses. Of the 36 reforms roof plumbing, building complaints, wall height, builders' defects in commercial buildings, wall setback, testing of geosynthetic products, caravan annex construction and building permit signing reforms have relevance to builders and plumbers (8 January 2014). More...

Works start on $49m South East road upgrade
Works have started on the $49 million Narre Warren-Cranbourne Road upgrade to reduce congestion along one of south-east Melbourne's most important travel corridors, Minister for Roads Terry Mulder announced today (07 January 2014). More...

Avalon Airport Rail Link reaches environmental planning milestone
The Avalon Airport Rail Link has now reached the formal environmental planning stage, Minister for Public Transport Terry Mulder said today (4 January 2014). More...

Published – articles, papers, reports

Building Activity, Australia, Sep 2013
Author: Australian Bureau of Statistics
The trend estimate of the value of total building work done rose 0.9 percent in the September 2013 quarter. The seasonally adjusted estimate of the value of total building work done rose 1.6 per cent to $21,124.3m, trend estimate of the value of new residential building work done rose 0.4% , value of work done on new houses fell 1.7 per cent, while new other residential building rose 3.7 per cent. The trend estimate of the value of non-residential building work done rose 1.5 per cent (16 January 2014). More...

Stranded down under? Environment-related factors changing China's demand for coal and what this means for Australian coal assets
Author: Ben Caldecott, James Tilbury, Yuge Ma
Smith School of Enterprise and the Environment: 16 December 2013
The report looks at how China's changing demand for coal could impact coal-related assets in Australia, which is a large and growing coal exporter to China. More...

State of Play Report 2013: Australia's Key Economic Infrastructure Sectors
Author: Infrastructure Australia
This paper discusses Australia's key economic infrastructure sectors. It provides some insight into the level of confidence that the nationally significant infrastructure within the energy, transport, communications and water sectors is meeting the needs of Australian industry, households and individuals (19 January 2014). More...

Urban Transport Strategy 2013
Author: Infrastructure Australia
In conjunction with national infrastructure audits, such a strategy would aim to improve proposals for inclusion on the national infrastructure priority list. However, it would not merely deal with projects. This paper raises some issues regarding such a strategy and offers suggestions as to key principles (December 2013). More...

In practice and courts

NCC 2014 – an overview
This overview contains a snapshot of some important changes contained in NCC 2014. A List of NCC 2014 amendments will also be made available via the ABCB website early this year. More...

Infrastructure Australia: submission to the Productivity Commission Inquiry into Public Infrastructure
In structuring this submission to provide the Commission with comments that will usefully assist it in fulfilling the inquiry's Terms of Reference this submission considers: Infrastructure funding and financing; Long-term planning and project selection; The cost of infrastructure projects. More...

NSW: BPB Report on Building Certification and Regulation -Public Comment Sought
The Building Professionals Board (BPB) is seeking public comment on a building certification and regulation report which has just been publicly released. Submissions close on Monday 24March 2014. More...

NSW: BASIX Target review - extension to exhibition period
The NSW Government is proposing changes to the BASIX targets to reflect trends in construction design and new technology innovation and align more closely with the national building standards contained in the Building Code of Australia. The proposed changes to BASIX will now be on exhibition from 13 December 2013 until 14 February 2014 (January 2014). More...

NSW: Commencement of NCAT
The NSW Civil and Administrative Tribunal (NCAT), which consolidates 22 of the state's tribunals and bodies, commenced on 1 January 2014. Applications lodged with a tribunal prior to 1 January 2014, and which have not yet been heard, will not need to be re-lodged. More...


Director of the Fair Work Building Industry Inspectorate v McDonald [2013] FCA 1431
INDUSTRIAL LAW – admitted contraventions of s 38 Building and Construction Industry Improvement Act 2005 (Cth) – statement of agreed facts – appropriate penalties to be imposed – factors to consider. Building and Construction Industry Improvement Act 2005 (Cth) s 4, 4(1), s 5, s 36(1), s 36(1)(d), s 37, s 38, s 48(2), s 49, s 49(2)(a), s 69, s 69(1), s 69(1)(b), s 69(1)(c)(iii), s 69(3)(b). More...

Mine Subsidence Board v Jemena Ltd and Jemena Gas Networks (NSW) Ltd [2013] NSWCA 465
ENERGY AND RESOURCES - mining - interpretation of Mine Subsidence Compensation Act 1961, ss 12A(1)(b), 15(5)(b) - respondents claim compensation from Mine Subsidence Compensation Fund under s 12A(1)(b) for expense incurred to prevent or mitigate damage to pipeline from subsidence - pipeline erected in "mine subsidence district" without approval in contravention of Act - s 15(5)(b) provides that "no claim shall be entertained or payment made" by the Board "in respect of damage caused by subsidence" to unapproved improvements unless certificate issued by Board - whether claim under s 12A(1)(b) a claim "in respect of damage caused by subsidence". More...

J & D Rigging Pty Ltd v Agripower Australia Ltd & Ors [2013] QCA 406
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the first respondent purchased mining plant and equipment which was affixed to land subject to a mining lease – where the first respondent engaged the appellant to dismantle and remove the plant – where the first respondent did not pay the appellant after being served with a payment claim – where the appellant was successful at adjudication – where the primary judge found that the dismantling of the plant was not ?construction work? under a ?construction contract? within the meaning of s 10 of the Building and Construction Industry Payments Act 2004 (Qld) and consequently the adjudication decision was void for want of jurisdiction – where the primary judge found that ?land? does not include mining leases and the plant did not ?form part of land? within the meaning of s 10 – whether the phrase ?forming, or to form, part of land? in s 10 imports the common law doctrine of fixtures. More...

BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2013] QCA 394
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the appellant (BMA) entered into a contract with the first respondent (BGC) for the construction of a dam – where BGC served a payment claim on BMA pursuant to the Building and Construction Industry Payments Act 2004 (Qld) (the Act) which included claims for alleged latent conditions and termination costs – where the payment claim was referred to adjudication and BGC was awarded a progress payment which included sums on account of latent conditions and termination costs – where BMA sought a declaration that the adjudication decision was void as a result of three jurisdictional errors – where the primary judge held that the adjudicator had made a jurisdictional error in the determination of the termination costs claim – where, on 13 November 2012, the primary judge declared the decision of the adjudicator void – where, on 22 March 2013, the primary judge revoked the declaration and dismissed BMA's application upon BGC undertaking to repay to BMA the portion of the adjudicated amount affected by jurisdictional error – where BMA submits that the primary judge's conclusion that a decision affected by jurisdictional error was not necessarily invalid for all purposes and has some residual effect was an error of law – whether the primary judge erred in finding that the adjudication decision, which he held to be affected by jurisdictional error, retained effect until he exercised his discretion to grant a declaration or make an order quashing or setting aside the decision – whether the primary judge erred in law in withholding the relief sought by BMA – whether the matter should be remitted to the adjudicator for determination according to law. CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where cl 26.3(b) of the contract requires BGC to give written notice to BMA of the encountering of latent conditions – where, within 10 business days of notification, the parties must ?negotiate in good faith any changes to the Price and/or time for completion of the Services as a result of Latent Conditions? and, in the absence of agreement, must refer the matter to an independent expert for determination – where the primary judge held that cl 26.3 was predicated on the existence of latent conditions and any dispute as to their existence was to be resolved by the general dispute resolution provision, cl 37 – where, contrary to BMA's contentions, the primary judge held that the fact that the machinery for assessment of value under the clause had not been advanced did not alter BGC's entitlement under the contract to be paid in respect of a latent condition – where the primary judge held that the award by the adjudicator in respect of latent conditions did not constitute a jurisdictional error – where BMA contends that cl 26.3 was intended to deal with all aspects of a dispute concerning latent conditions, including the determination of the existence of a latent condition – whether cl 26.3 operates subject to the determination of the existence of latent conditions under cl 37 – whether the adjudicator committed a jurisdictional error in awarding BGC a progress payment which included a sum in respect of latent conditions

INTEREST – RATE OF INTEREST AND COMPOUND INTEREST – RATE IN OTHER CASES – where BMA sought interest on the sums repayable to it at the rate prescribed in practice directions for default judgments – where the primary judge accepted BGC's contentions that the appropriate rate was that payable on term deposits with financial institutions – where BGC's evidence of commercial rates of interest awarded on investments was uncontested – whether the primary judge erred in accepting and acting on evidence of commercial interest rates when awarding interest on the sum repayable to BMA. More...

Heavy Plant Leasing Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd & Ors [2013] QCA 386
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the first respondent was a sub-contractor for the provision of earthworks and the appellant was a sub-contractor to the first respondent – where the first respondent sent two documents, dated 6 and 8 March, to the appellant in response to the appellant's payment claim – where, despite failing to provide a statement as to ?why the scheduled amount [was] less? in respect of ?variations?, there was no suggestion in the 6 March document that it was provisional – where the adjudicator concluded that the 6 March document was the payment schedule for the purposes of the adjudication and disregarded the 8 March document – where the primary judge found that there was no proper basis for the adjudicator to find that the 6 March document constituted a payment schedule and that, in refusing to consider the contents of the 8 March document, the adjudicator committed a jurisdictional error – where the appellant contends that the 6 March document constituted a payment schedule as it met the requirements of s 18 of the Building and Construction Industry Payments Act 2004 (Qld) (the Act) – where the appellant submits that it was irrelevant that the 6 March document was not described internally as a ?payment schedule? and that the subsequent provision of more detailed reasons did not invalidate the 6 March document as a payment schedule – where the appellant contends that the primary judge erred in considering ?all of the circumstances of the case?, including the content of the 8 March document and the first respondent's subjective intention, in determining whether the 6 March document was a payment schedule – whether the primary judge erred in failing to analyse whether the 6 March document was a ?payment schedule? by reference to the statutory requirements in s 18 of the Act and not otherwise – whether the primary judge erred in considering the subjective intention of the first respondent and whether the 6 March document ?purported? to be a payment schedule – whether the primary judge erred in finding that the 6 March document was not a payment schedule for the purposes of the Act – whether any deficiency in the 6 March document was remedied by incorporating parts of the 8 March document – whether, if the 6 March document did not constitute a valid payment schedule, the adjudicator committed a jurisdictional error rendering his determination ineffective – whether the matter should be remitted to the adjudicator for determination according to law. CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – SUBCONTRACTORS' CHARGES ACT (QLD) – where the appellant served the first respondent with three notices of claim of charge – where the first respondent demanded that the notices be withdrawn on the basis of non-compliance with the Subcontractors' Charges Act 1974 (Qld) (the Charges Act) – where the appellant wrote to the first respondent on 20 February 2013 accepting that its notices of claim of charge were invalid and of no effect – where the letter of 20 February 2013 was not in the approved Form 5 – where the primary judge found that the failure to give notice of withdrawal of a notice of claim of charge in the approved form did not render a clear and unequivocal statement that a notice of claim of charge was invalid ineffective – where the primary judge held that, if a notice in the approved form was a necessary prerequisite to withdrawal, there had been sufficient compliance with s 11(8) of the Charges Act – where the first respondent submits that the failure to use Form 5 meant that there could not have been substantial compliance with s 11(8) of the Charges Act – where the first respondent contends that the adjudication decision was void as, at the time the payment claim was served by the appellant, there was a valid and subsisting charge pursuant to the Charges Act and s 4 of the Act prohibits the service of a payment claim in such circumstances – whether the letter of 20 February constituted an effective withdrawal of the notices of claim of charge. More...

Gratrax Pty Ltd v D & C Pty Ltd [2013] QCA 385
TORTS – NEGLIGENCE – ESSENTIALS OF ACTION FOR NEGLIGENCE – DAMAGE – CAUSATION – GENERALLY – where the appellant retained the respondent to design a road – where the respondent's design specified the wrong class of materials to be used in connection with the construction of the road – where the trial judge found the respondent failed to exercise proper care and skill – where the appellant was required to undertake testing and approval of the material and pavement prior to commencing work – where the appellant proceeded to lay the pavement without obtaining the appropriate testing, inspection and approval – where the trial judge concluded that the factual causation test in s 11(1)(a) of the Civil Liability Act 2003 (Qld) (=the Act') was satisfied but that the appellant's actions in prematurely laying the pavement meant that the scope of liability test in s 11(1)(b) of the Act was not satisfied – where the respondent was found to be liable only for the additional costs the appellant would have sustained as a result of the respondent's negligence if it had not prematurely commenced construction – whether the trial judge erred in approaching the question of causation – whether the appellant's intervening act or decision was a more immediate cause of its loss than the respondent's breach. TORTS – NEGLIGENCE – CONTRIBUTORY NEGLIGENCE – GENERALLY – where, although it was not necessary to make such a finding, the trial judge found that the appellant failed to take reasonable care in prematurely commencing work – where the trial judge did not otherwise make any apportionment to account for the appellant's contributory negligence – whether the trial judge erred in failing to carry out the assessment of damages to take account of the appellant's contributory negligence. More..

Butler & Ors v The State of Queensland [2013] QSC 354
TORTS – STATUTES, REGULATIONS, ETC – APPLICABILITY AND EFFECT IN ACTIONS FOR NEGLIGENCE – GENERALLY – where a subsidence event occurred in 2008 in Collingwood Park, an area within the confines of a mining lease granted in 1967 – where the plaintiffs claim damages for loss arising from breaches of duty in the granting of a mining lease and the supervision and monitoring of mining work undertaken – where the relevant statutory regime provided for the grant of approval to mine and power to impose special conditions with the responsibility to monitor and supervise compliance – where it was found the 2008 subsidence event was materially contributed to by the size and shape of the pillars and the higher extraction ration – whether the defendant owed the plaintiffs a duty of care in the grant of the mining lease, and for the imposing of conditions on the grant, and the monitoring, supervision and enforcement of compliance. TORTS – ESSENTIALS OF ACTION FOR NEGLIGENCE – DUTY OF CARE – IN GENERAL – where the plaintiffs claim the defendant owed a separate duty of care in responding to an earlier subsidence event in 1988 to obviate or minimise the risk of injury – where there was no allegation the defendant was in breach of a duty of care in relation to that subsidence event - whether the defendant owed the plaintiffs a duty of care to take remedial steps. TORTS – ESSENTIALS OF ACTION FOR NEGLIGENCE – DAMAGE – GENERAL – where the plaintiffs claim the defendants conduct in failing to monitor, supervise and enforce compliance with the mining lease was a breach of its duty of care and caused or materially contributed to the plaintiffs' loss and damage – where the question is whether there was any diminution in market value, and was any such diminution caused by the subsidence – where the valuation experts disagreed as to the correct methodology for an assessment of damage – whether the plaintiffs established on the balance of probabilities the defendant's breach caused or materially contributed to each plaintiff's loss and damage. More...

Faulks v New World Constructions Pty Ltd [2013] QCAT 658
Failure to complete a stage in construction — Works wrongly suspended — Application for relief from payment of stage because of defective and incomplete work and claim for general damages for distress, inconvenience and discomfort — Contract terminated as Respondent's QBSA licence suspended — Entire contract — Counter application for payment of stage — Availability of recovery on quantum meruit — Whether the claim for general damages by innocent party enlivens claim by defaulting party for recovery on quantum meruit. Chalet Homes Pty Ltd v Kelly [1978] Qd R 389 Robinson v Harman [1848] Eng R 135 Bellgrove v Eldridge (1954) 90 CLR 613 Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178 Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184 Falko v Jones McKewen & Co. Pty Ltd [1977] BR 447 Coshott v Fewings Joinery Pty Ltd BC 960 2970 NSWCA 15 July 1996 (unreported) Baltic Shipping Company v Dillon (1993) 176 CLR 344 Hutchinson v Harris (1978) 10 BLR 24, 37-238 Batty v Metropolitan Realisations Ltd (CA) (1978) 1 QB 554 Burke v Lunn [1976] VR 268 Bonchristiano v Lohmann [1998] 4 VR 82. More...

Andara Homes Pty Ltd v Matish Pty Ltd; Andara Homes Pty Ltd v Magistrates Court of the Australian Capital Territory and Matish Pty Ltd [2013] ACTSC 265
BUILDING AND CONSTRUCTION – adjudication under the Building and Construction Industry (Security of Payment) Act 2009 (ACT) – order in the nature of certiorari sought –jurisdictional error – alleged that mandatory procedures set out in the Act were not complied with –Building and Construction Industry (Security of Payment) Act 2009, s 22. CORPORATIONS – statutory demand – offsetting claim – whether genuine – demand set aside – no issue of principle - Building and Construction Industry (Security of Payment) Act 2009 (ACT) ss 22, 23, 28; Corporations Act 2001 (Cth) s 459G. More...

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.