Introduction

A satisfactorily concluded dispute resolution mechanism, at least to an award creditor, is the successful enforcement of the decision of the arbitral tribunal. Where a judgment or arbitral award is made and the successful party cannot enforce the award, the creditor has only succeeded in obtaining a pyrrhic judgment or award and can only be tagged a "judgment creditor" or "award creditor" but without the much-needed value of the award or judgment.

Unfortunately, award debtors routinely employ every conceivable strategy and argument to circumvent the enforcement of the award against them. One strategy being an argument that the time within which to enforce the award or judgment has lapsed and the award unenforceable.

The issue of limitation of time for enforcement of arbitral awards has long plagued award creditors and there is indeed a need to critically evaluate the statutory provisions and judicial decisions to ascertain ways to avoid the unsavoury outcome of the statutes of limitation.

Time limit on recognition and enforcement of arbitral awards

There are two types of time limitation in enforcement proceedings in Nigeria - contractual time limitation and statutory time limitation.

Contractual time limits are usually those set by the parties in their arbitration agreement stating the time limit for commencing arbitral proceedings or enforcing arbitral awards (where a party does not voluntarily comply). Such contractual arrangements are however subject to statutory provisions on time limitations.

Statutory time limitation operates by virtue of statutory provisions limiting the time for the enforcement of arbitral awards. A number of statutes define the limitation period applicable to the enforcement of arbitral awards. These include –

  • Reciprocal Enforcement of Judgments Act, Chapter 175 Laws of the Federation of Nigeria 1958 (REJA) which provides that a judgment creditor is to apply to the High Court within twelve months after the date of the judgment, or such longer period as may be allowed by the High Court to have the judgment registered.1
  • The Foreign Judgments (Reciprocal Enforcement) Act2 (FJREA) applies to foreign arbitral awards which have to be registered in order to be enforceable. The limitation period under the FJREA for the registration is "six years" after the date of the judgment or where the judgment is appealed against, 6 years after the date of the last judgment on appeal.3 
  • The Limitation Law of Lagos State4 provides in section 8(1)(d) thereof, that an application for enforcement of arbitral awards must be filed within six years from the date the cause of action accrued so far as the arbitration agreement is not under seal or the arbitration is under an enactment other than the Arbitration and Conciliation Act.
  • Lagos State Arbitration Law provides in section 35(5) that, for the purpose of limitation, the time between the commencement of the arbitration and the date of the award are not to be reckoned, and thus, time freezes while the proceedings are pending.

When then does time begin to run for the purpose of enforcing an arbitral award? When does the award creditor lose his right to enforce an arbitral award in view of the various statutory provisions on limitation?

The Supreme Court in a reconvened full panel of seven justices5 in the leading judgment read by Ogundare JSC in City Engineering Nig. Ltd v. Federal Housing Authority6, began the judgment with the following words:

"The principal question that calls for determination in this appeal is: When does the statutory period of limitation start to run for the purpose of the enforcement of an arbitration award; is it at the date of the accrual of the original cause to action or is it at the date of the arbitral award?" 

In construing the six year period provided by the Limitation Law of Lagos State, the honourable Justice of the Supreme Court ended with:

"The statutory period of limitation of six years began to run from 12/12/807 and appellant's application to enforce the award was statute-barred when it was brought in 1988. The appellant has itself to blame for the catastrophe that has befallen it. Notwithstanding that there was some delay in the arbitration proceedings arising from various applications made by both sides, the arbitrator gave his award in November 1985,8 a date still within the statutory period of limitation. For unexplained reasons, the appellant waited another three years before applying to enforce the award in its favour, by which time limitation period had set in."

The decision of the Supreme Court in the City Engineering case appears not to be arbitration friendly and is a long distance away from the English position which commences the calculation of time from the date of the award.9 This is because delays occasioned as a result of lengthy arbitral proceedings and subsequent appeals against a refusal of the court to set aside an award may deny the successful party the ability to enforce the award. The appeal process in Nigeria, from the court of first instance to the Supreme Court, (except for some political, constitutional or designated fast track cases) takes an average of 8-12 years. Going by the unanimous decision of the full panel of the Supreme Court in the City Engineering case, what hope then is available to an award creditor who obtains a successful award after six years of the accrual of the cause of action?

Solutions to the 6-year time limit to enforce

The true position in the Limitation Laws

It appears that the decision in the City Engineering case refers to "arbitration" generally, and not necessarily arbitration under the Arbitration and Conciliation Act. This is so, going by the way the issue in the appeal was framed for determination by the Supreme Court.

In the course of the judgment, the court was however conscious of the conditions placed by section 8(1)(d) of the Limitation Law of Lagos State, which excludes arbitration agreements made under seal and arbitral agreement governed by the Arbitration and Conciliation Act.

To avoid the limitation scenario in the City Engineering case, parties are expected to meet any of the following conditions as provided under the Limitation Law of Lagos State:

  1. Ensure that their arbitration agreements are made under seal. When this is done, the six-year limitation period from the accrual of cause of action shall not apply.
  1. Agree that the law applicable to their arbitration is the Arbitration and Conciliation Act.

On (a) above, where the agreement is under seal, the applicable limitation period shall be twelve years from the date of the accrual of the cause of action by virtue of section 12(1)(b) of the Limitation Law. Under the FJREA, the limitation time for registration of foreign arbitral awards in Nigeria would have been six years after the publication of the award. However, due to the fact that the Minister of Justice has not made a proclamation extending Part 1 of the Act to relevant foreign countries, the time is limited to 12 months,10 just as is applicable to arbitral awards obtained in England, Northern Ireland or Scotland under the REJA.11

On (b) above, it is not clear what limitation period would apply to an arbitration governed by the Arbitration and Conciliation Act, as the Limitation Law of Lagos State is silent on this. However, it can be argued that "judgment" used in section 12(2) of the Limitation Law12 includes an arbitral award made under the Arbitration and Conciliation Act.13 In which case, the limitation period for arbitral awards made under the ACA are enforceable within 12 years from the date on which the award becomes enforceable.

Frozen time – Lagos State Arbitration Law

Noting that under section 8(1)(d) of the Limitation Law of Lagos State, arbitral awards made pursuant to "arbitration under other enactments other than the ACA" are susceptible to the 6 year period of limitation from the accrual of the action, the Lagos State Arbitration Law provides that the period between the commencement of the arbitration and the date of the award shall be excluded in computing the limitation period for enforcement of arbitral awards.14 The limitation period as stipulated in the Lagos State Arbitration Law is applicable to all arbitration within Lagos State except where the parties have agreed to be governed by another arbitration law.15

The fact that arbitration under the Lagos State Arbitration Law is not one that is under the Arbitration and Conciliation Act, does not make the Lagos State Arbitration Law to be in conflict with section 8 of the Limitation Law. This is because by section 4(a) of the Limitation Law, the limitation period in the Limitation Law will not apply to an action for which a period of limitation for enforcement is fixed by any other enactment. This means that where an arbitration is governed by any statute that stipulates the limitation period for enforcement of an award, the period of limitation in the Limitation Law will not apply.

Argument of frozen time

There is now a semblance of hope and a movement away from the stringent position taken by the Supreme Court in City Engineering v. FHA.

In Sifax Nigeria Limited v. Migfo Nig. Ltd,16 the Court of Appeal stated categorically that "computation of time during the pendency of an action shall remain frozen from the filing of the action until it is determined or abates." In effect, the period between the commencement of the arbitration and the date of the award shall be excluded in determining the 6 year limitation period under section 8(1)(d) of the Limitation Law.

Though the decision of the Court of Appeal was appealed to the Supreme Court, the apex court17 on 16 February 2018, aligned itself with the decision of the Court of Appeal and is indeed in tune with the reason proffered by Oseji JCA of the Court of Appeal who said:

"...contention that time should not run during the pendency of an action in court for the purpose of Limitation Law would, in my modest opinion, unwittingly permit the Legislature, to take over control of the time-table of litigation indirectly or by subtle means, to wrongly/technically dictate the pace cases are heard in court under the cloak of limitation enactment. This will create the alarming scenario in which pending cases caught by the effluxion of time and objection to their determination on the merit on account of lapse of time so upheld would meet undeserved grief. Or it may create the dangerous repercussion of stampeding the court to operate on full throttle to grapple with time in the course of which justice may be sacrificed on the altar of neck-breaking speed or indecent haste which will drain the adjudication of the dispute of the patience, fairness, diligence, or balanced/even handed justice which it is wont to have, which will be a sad day for the administration of justice."

 

The decision in Sifax v. Migfo subtly gives credence to Section 35(5) of the Lagos State Arbitration Law. It means inevitably, that had the decision in Sifax Nigeria Limited v. Migfo been in existence and had the Supreme Court sanctioned it before determining the appeal in City Engineering v. FHA, the court might have held that the appellant was within time to enforce the arbitral award.18 This is particularly so, as the cause of action arose in 1980, the same year the action was instituted. Time would have been frozen between 1980 and 1985 when the arbitration was concluded, and time would only have been reactivated after 1985.

With the decision of the Supreme Court in Sifax v. Migfo, it appears that the decision of the apex court in City Engineering v. FHA may cease to be the law. However, it is anticipated that when an issue of limitation of action for the enforcement of arbitral award comes before the Supreme Court, it will seize the opportunity to make formal pronouncement to deviate from its earlier decision in the City Engineering case.

Instituting a preservative action

Where the arbitration is not under seal, not under the Arbitration and Conciliation Act, not under the Lagos State Arbitration Law, and there is no assurance that the Sifax v. Migfo scenario can come in aid in arbitration (in the absence of a formal deviation by the Supreme Court from its decision in City Engineering decision), the claimant may file an action in court in defiance of the arbitration agreement. The claimant may then seek an order to stay proceedings pending arbitration, thus preserving his right of action.

There is a possibility that this strategy may be opposed on the grounds that it is an abuse of process, particularly where the defendant does not request for the stay of proceedings pending arbitration. However, the Arbitration and Conciliation Act does not stipulate that the party who may apply for stay of proceedings pending arbitration must be the defendant. It rather states in section 5 that "any party to the arbitration agreement may...apply to the court to stay the proceedings"19

Commencing enforcement within 12 months after award

Where a foreign arbitral award is not under seal, the award may be registered as a domestic judgment under the Foreign Judgment (Reciprocal Enforcement) Act (FJREA) 1990 or the Reciprocal Enforcement Of Judgments Ordinance, Cap 175 Laws Of The Federation Of Nigeria And Lagos, 1958 (REJA) within 12 months after the publication of the award. Judgments from commonwealth countries are enforceable in Nigeria pursuant to the provisions of REJA. There is no need for reciprocal agreement between Nigeria and the commonwealth country where the award sought to be enforced comes from.20

For non-commonwealth countries, the FJREA will apply, as the FJREA was enacted to "make provision for the enforcement in Nigeria of judgments given in foreign countries which accord reciprocal treatment to judgment(s) given in Nigeria, for facilitating the enforcement in foreign countries of judgments given in Nigeria..." The period for registration of final, conclusive and enforceable award21 is also twelve months as in REJA.22

Applying for recognition first in another jurisdiction

The focus of the various enabling laws on enforcement of foreign awards or judgments are the awards or judgments of a foreign court or foreign arbitral tribunal. It is therefore arguable that where a judgment creditor perceives that the limitation period for registration of the award has lapsed in Nigeria, he could take the award for recognition in another jurisdiction where the action is not statute barred (e.g. England) and obtain the judgment of that court. He could then apply to a Nigerian court with the judgment from the foreign court for registration in Nigeria. It is unlikely that this approach will not be met with stiff opposition that will require a definite position of the court on whether an award can be subjected to recognition in more than one jurisdiction. It could also raise the question of the nebulous public policy.

Once a foreign arbitral award is recognized and enforced by the court, the award is treated as a judgment of the registering court and enforced in a similar manner. Arguably, the limitation period for the enforcement of the judgment now recognised for enforcement is twelve years from the day the judgment of the registering court becomes enforceable.23

Conclusion

Enforcement of arbitral award can sometimes be like a nightmare to award creditors. Hopefully, employing any of the strategies proposed above in the right context will serve as succour to award creditors; and award debtors will not have the confidence of stultifying hearing or delaying proceedings with the belief that time will be a grave factor from date of accrual of action.

It is also hoped that where it becomes clear that time is no longer a grave factor, award creditors will look toward settling the award, particularly where interest accrues continually with the attendant delayed post-award proceedings.

Footnotes

LLM; MCIArb; ACTI; Senior Associate at AELEX

1 Section 3 of REJA. This is applicable to judgment and arbitral awards obtained from England, Ireland or Scotland

2 February 1961

3 Section 4 of the FJREA. This is what the statutes says. But what the court says about this provision shall be considered below.

4 Similar to Section 7(1)(d) of the Limitation Act, Cap 522, L.F.N. (Abuja) 1990

5 The Supreme Court of five Justices had earlier heard the appeal. But when it realised that it had given two conflicting decisions on limitation, it abolished the hearing and reconvened with seven Justices to unify its decision. In Murmansk State Steamship Line v. Kano Oil Millers (1874) 12 SC 1; (1974) NSCC590, the Supreme Court  had held that the statutory period of limitation should run from the date of the breach of the charter party in 1964, when the cause of arose and not from the date when the award was made in 1966. Also in Obembe v. Wemabod Estates Ltd (1977) 5 SC 115. But in Kano State Urban Development board v. Fanz Construction Co Ltd (1990) 4 NWLR (Pt. 142)1, the Supreme Court held that an award by an arbitrator constitutes an independent cause of action.  

6 (1997) 9 NWLR (Part 520) 224

7 That is when the cause of action accrued.

8 Arbitration proceedings began in 1980, the same year the cause of action accrued and concluded with its award in 1985.

9 In Turner v Midland Rly Co (1911)1KB 832 it was held that the six year period of time limitation for enforcement of the arbitral award commences from the date of the award and not when the claim arose because the award itself gives rise to another cause of action. Same also in Agromet Moto import Ltd v.  Maulden Engineering  Co (Beds ) Ltd (1985)2 All ER 436.

10   Marine and General Assurance v. Overseas Union & 7 Ors. (2006) 4 NWLR (Pt. 971) 641, where the Supreme Court said "However, section 3(1) of this Act had subjected the coming into force of the provisions of Part 1 of the Act which contains section 4(1) of the Act extending the period of registration to six years, to an Order to be made by the Minister of Justice directing the extension of Part 1 of the Act to relevant foreign countries. Section 9 of the new 1990 Act had also unequivocally preserved the effect of the 1958 Reciprocal Enforcement of Judgments Ordinance pending the promulgation of the Order envisaged under section 3(1) of the 1990 Act by the Minister of Justice."

11 Macaulay v. R.Z.B. of Austria (2003) 18 NWLR (Pt.852) 282 at 297-298; Marine and General Assurance v. Overseas Union & 7 Ors. (supra)

12 Similar to section 11(2) of the Limitation Act of Abuja

13 This argument could be deduced from the judgment of the Supreme Court in the City Engineering v. FHA case, particularly with reference to section 8(1)(d) of the Limitation Law on pages 234-235 of the report. Ogundare JSC may have mixed up the intent of section 8(1)(d) when he said on page 235 "it is generally accepted for the purpose of these proceedings that the arbitration agreement of 17/12/74 was not under seal nor was it under any enactment other than the Arbitration Law." The underlined would have read "and was under an enactment other than the Arbitration Law."

14 Section 35 (5) of the Lagos State Arbitration Law, 2009.

15 ibid. section 2

16 (2015) LPELR 24655 (CA)

17  Sifax v. Migfo SC.471/2005

18 This is assuming that the arbitrator had the requisite jurisdiction to entertain the action beyond the 3 month agreed period for the arbitration.

19 Article 8(1) UNCITRAL Model Law of International Arbitration provides that "...if a party so requests..."

20 Marine and General Assurance v. Overseas Union & 7 Ors. (supra)

21  Section 2 of FJREA defines "judgments" to include awards in arbitration and authorizes Nigerian courts (with jurisdiction to hear the dispute) the power to register and enforce foreign judgments of countries which accord reciprocal treatment to Nigerian judgements.

22 Ibid.

23 Section 12(2) of the Limitation Law of Lagos State

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions