The new standard construction contract, NZS3910:2013, although the product of what was billed by the Standards Committee as a "limited technical review", contains a number of significant changes and new features.

On balance, we like it - but there is a lot for users to digest. Principals, in particular, will need to modify their standard amendments to reflect the changes.

Key changes

These include:

  • a new structure with the form of Contract Agreement now at the front of the document (formerly included as the Second Schedule)
  • new guidelines which no longer have contractual status
  • new provisions governing cost reimbursement contracts
  • a prohibition on assignment of the contract by either the Principal or the Contractor without the consent of the other party (such consent not to be unreasonably withheld or delayed)
  • new provisions setting out when the Principal cannot call on a Contractor's Bond, a positive obligation on the Principal to release a Contractor's Bond within five working days after the Principal receives the Practical Completion Certificate, and a requirement for the Contractor to procure a replacement Bond where the Bond has an expiry date that will occur before the Principal is obliged to release the Bond
  • more comprehensive clauses dealing with programmes, including the option for a Comprehensive Programme
  • specific provisions in the general conditions setting out the requirements for Safety, Quality and Traffic Management, including contract specific safety, quality and traffic plans
  • new advance notification obligations
  • updated provisions governing insurances and new insurance forms (retained as schedules)
  • substitution of "Defects Liability Period" with "Defects Notification Period" and "Defects Liability Certificate" with "Final Completion Certificate", including a requirement on the Contractor to remedy defects within five working days unless otherwise agreed by the Engineer
  • clearer provisions for notifying and valuing Variations
  • an express entitlement to the Contractor for time and money for delay to completion caused by the Principal or any Person for whom the Principal is responsible
  • the introduction of Provisional Items (being different from Provisional Sums)
  • more streamlined processes for issuing payment schedules
  • a more comprehensive "checklist" Specific Conditions of Contract schedule (Schedule 1) which contains provision for capturing information on the Contract which might otherwise be documented in other contract documents, including insurances and the valuing of Variations
  • the inclusion of standard forms of Contractor and Subcontractor warranty, Agreement for off-site Materials, Practical Completion Certificate and Final Completion Certificate
  • acceptance of notices by email, and
  • revised Conditions of Tendering.

Many of these changes will be welcomed by the construction industry. We discuss some of them in more detail below. In addition, a number of technical amendments have been made to clarify the meaning of the standard form or to simplify its procedures.

Structure and new forms

Putting the Contract Agreement first is consistent with the order in which Contract Documents are usually assembled in practice.

The more comprehensive Specific Conditions of Contract schedule (Schedule 1) will assist parties to record the key commercial terms in one contract document.

The inclusion of standard forms of Contractor and Subcontractor warranty, Agreement for off-site Materials, Practical Completion Certificate and Final Completion Certificate is also sensible given that such forms are already widely used.

Cost reimbursement contracts

The new cost reimbursement provisions set out a method of calculating the Contract Price being either:

  • the Net Cost of the items used in the Contract Works plus allowances for On-site Overheads and Off-site Overheads and Profit, or
  • rates, where the Contract contains rates. Allowances for On-site Overheads and Off-site Overheads and Profit will only be added to the rates if the rates have not already made allowance for these amounts.

All costs claimed by the Contractor for reimbursement must be verifiable by the Contractor's records. Where an indicative estimate of the Contract Price is included in the Specific Conditions, each of the Contractor's payment claims must include a reconciliation of the claim against the estimate and an explanation where there has been any variance from, or to, the estimate.

Providing a standard approach to calculating the Contract Price under a cost reimbursement contract is a good step as the previous version of NZS3910 left it to the parties to describe the process in the Contract. But, while this addition will promote more consistent approaches to cost reimbursement contracts, parties should take care to select the right contracting method where rates are used, as a measure and value approach may be more appropriate.

Comprehensive Programme

The ability to require the Contractor to provide a Comprehensive Programme - including details such as work sequencing, a critical path analysis showing activity durations and dependencies and key dates relating to site access together with the provision of Principal supplied materials and services and the works of Separate Contractors - reflects current best practice. Both hard and soft copies of the Comprehensive Programme must be provided.

A Comprehensive Programme will allow the parties and the Engineer to better monitor and evaluate the impact of Variations and interface issues with Separate Contractors and may be useful to the Engineer in assessing delay and/or extension of time claims.

Safety, Quality and Traffic Management Plans

Although the previous version of NZS3910 included in an option to require the Contractor to provide specific safety plans, quality plans and/or traffic management plans as necessary, it was left to the Principal or Engineer to document elsewhere in the Contract what the Contractor must provide by way of these plans.

The inclusion of the specific requirements for each type of plan in the new form will promote a more consistent standard on how these project management tools are to be effectively implemented.

Advance notification

The new form also includes an obligation on both the Contractor and the Engineer to notify the other when either of them becomes aware of any matter which is likely materially to alter the Contract Price, delay completion of the Contract Works or result in a breach of a statutory duty in connection with the Contract Works.

The Contractor or Engineer is then entitled to require the other to meet in order to explore proposals for avoiding or reducing the impact of the notified matter. Where the Contractor fails to give advance notification, its failure may affect the valuation of any Variation arising out of the matter. This obligation will encourage the Contractor to communicate matters early, which can only be good for the project.

Defects Notification Period and Final Completion Certificate

Replacing "Defects Liability Period" with "Defects Notification Period" and "Defects Liability Certificate" with "Final Completion Certificate" (as used in other standard forms, such as FIDIC), is sensible. The new terms will help dispel a common misconception that the "Defects Liability Period" limits the liability of the Contractor to remedy defects and that liability ceases upon the issue of the "Defects Liability Certificate".


The new insurance provisions and the revised information for insurance forms contained in the Schedules are far more comprehensive. They:

  • require the parties to elect the specific events which are to be covered by the insurances
  • set out which party will be liable for insurance deductibles or excesses (depending on the party arranging the insurance and whether the claim arose from an act or omission of the Contractor), and
  • provide that forces of nature which are identified as covered in the Specific Conditions will not be treated as an "excepted risk". (This removes an anomaly in the previous version of NZS3910 which permitted the Contractor to exclude from its insurance cover any "excepted risks". Principals typically take the risk of loss or damage to the Contract Works caused by the "excepted risks".)


The changes to the Variation provisions, particularly the valuation of Variations, should make the processes clearer and easier to apply. However, there is still no formal process for the Principal or Engineer to request the Contractor to quote a price for a Variation before it is instructed.


Similarly, the system for issuing payment schedules under the Contract has been simplified to avoid the need for a separate provisional payment schedule and a progress payment schedule each time a payment claim is submitted.

Changes include:

  • the progress payment schedule issued by the Engineer, while initially provisional, will apply unless the Principal notifies the Engineer of any amendments or deductions
  • provision in the Specific Conditions for the parties to elect whether Progress Payment Schedules are to be issued as GST invoices or whether a separate GST invoice corresponding to a Progress Payment Schedule must be issued
  • reduction from two months to one month of the deadline for submitting a Final Payment Claim after the issue of the Final Completion Certificate
  • a new requirement that the Engineer issue the Final Payment Schedule no later than 35 working days following receipt of the Final Payment Claim and a Provisional Final Payment Schedule no later than 20 working days following receipt of the Final Payment Claim. Previously there were no time limits
  • an explicit provision that the Final Payment Claim will be the Contractor's final payment claim under the Contract, and
  • a change to the default interest rate payable by the Principal for payment default to one and a half times the monthly small-to-medium-sized enterprise overdraft rate published by the Reserve Bank (from one and a quarter times the rate payable by the Contractor for overdraft facilities).

Provisional Items

Provisional Items allow the parties to include individual elements of work for which a rate has been agreed in the Schedule of Prices against nominal quantities. Provisional Items will only be carried out on the instruction of the Engineer and the Contractor will be paid at the agreed rate. Provisional Items differ from Provisional Sums in that the latter are instructed and valued as Variations.

Conditions of Tendering

A number of changes have been made to the Conditions of Tendering forming part of NZS3910. For example, provision has been included to enable the Principal to include tender evaluation criteria. However, we note that the Conditions of Tendering still do not provide protection for Principals from potential liability in respect of process contracts.

Timely introduction of new forms

The Standards Committee, in response to feedback from the sector, has decided to publish three new Standards in place of NZS3910:2003. The other two Standards, due out shortly, are:

  • NZS3916 Conditions of contract for building and civil engineering – Design and construct, and
  • NZS3917 Conditions of contract for building and civil engineering – Fixed term.

These new forms are timely given that construction activity in New Zealand is about to intensify, particularly in Christchurch and Auckland. However, with a number of projects already in train in Christchurch using NZS3910:2003 as the base document, and given the numerous changes in NZS3910:2013, it may take time for the updated version to catch on.

Our thanks to Arthur Chung for writing this Brief Counsel.

The information in this article is for informative purposes only and should not be relied on as legal advice. Please contact Chapman Tripp for advice tailored to your situation.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.